PRESENT: Karl Bolognese - Supervisor, Terry Rarick - Supervisor, Richard
Orwig- Solicitor, Thomas Unger - Engineer, Terry Manmiller - Operations
Director, and Ruth Manmiller - Recording Secretary.

GUESTS: Nancy Werner, Keith Weidner, Daniel Miller, Sr., Richard Thren,
Elizabeth Hartman, Keith Hartman, Daniel Becker, Cindy Stump, David Stump,
Donald Glass, Paul Martin, Jonas Martin, Lindford Weber, Robert Ludgate,
Jr., Harold S. Burgert, Fay Isamoyer, Ernie Marshall, Lee Poole, Tina
Poole, Gloria Kline, Ronald Kemmerer, Gloria Kemmerer, Randy Wolfe, Larry
Kunkel, William Hunter, Frank Wheeler, Gary Rollman, Ruth Malenda, Claude
Beaver, James Schoellkopf and May Roth - Eagle/Times Reporter.

Karl Bolognese called the November 9, 2000 Board of Supervisors meeting to
order at 7:00 PM and asked everyone to rise for the Pledge to the Flag.

Terry Rarick made a motion, seconded by Karl Bolognese approving the
October 12, 2000 Board of Supervisors meeting minutes. Motion carried.

POLICE REPORT

Ruth Manmiller read the October Northern Berks Regional Police Department
activities report.
TOTAL CALLS 617
MAIDENCREEK ONTELAUNEE LEESPORT
CALLS 273 196
148
CRIMES/OFFENSES 14 1 1
FINES COLLECTED $2582.29 $2961.88
$1061.19

ROAD REPORT

Terry Rarick gave the Operations Director's report for October:

EQUIPMENT REPORT

1. The mowing equipment will be serviced and stored.
2. Unit #3 tailgate has been installed.
3. The backhoe the township has been testing for the past week is in the
garage for inspection.

ROAD CREW COMPLETED THE FOLLOWING

1. Crack sealing is in progress. Grove Road, Hoch Road, E. Wesner Road,
Hill Road and Lee Spring Road will be completed this fall.
2. All new road index signs have been installed.
3. Numerous potholes have been repaired.
4. Mowing is completed for the season.

DRIES ROAD

The Engineer reported Penn Dot should grant approval for the stormwater
agreement by the end of the year. The Supervisors agreed to wait for the
approval to arrange a meeting with Ontelaunee Township Supervisors.
Ontelaunee Township agreed to pave Dries Road and Maidencreek Township
agreed to install storm water improvements.

EMERGENCY GENERATOR

Terry Rarick made a motion, seconded by Karl Bolognese, authorizing the
Operations Director to proceed with the Emergency Generator Project by
purchasing the Emergency Generator from Grainger for $13,177.00. Motion
carried. The Maidencreek Township Building, the Andrew Maier Elementary
School, and the Blandon Fire Company are designated emergency headquarters
for Maidencreek Township. This would improve the township building in
case of an emergency.

Terry Rarick made a motion, seconded by Karl Bolognese, to add David I.
Brown to the Part Time Employee list for snow removal during 2000-2001.
Motion carried.

Terry Rarick made a motion, seconded by Karl Bolognese, to purchase a Case
Backhoe form Powerco for $56,078.00. The Board agreed the liability
issues, concerns of repair, general usage and maintenance they would
purchase the backhoe, rather than purchase the backhoe jointly with the
Maidencreek Authority. Motion carried.

TREASURER'S REPORT

Ruth Manmiller read the Treasurer's Report for October and requested
approval of the following payouts:
GENERAL CHECKING $103,480.25
PAYROLL $ 16,190.93
GOLDEN MANOR III IMPROVEMENTS $ 2,699.80
RECREATION TAX CHECKING $ 5,303.28
TRAILS, INC. $ 1,265.87
Terry Rarick made a motion, seconded by Karl Bolognese, approving the
Treasurer's Report for October 2000. Motion carried.

BLANDON FIRE COMPANY REPORT

Daniel Miller reported Fire Company activities for October 2000:
Fire Calls 1
Accident Calls 9
AFA Calls 6
Other Calls 3

TOTAL CALLS 19

Fire Police Calls 15
Training Hours 270

PUBLIC COMMENT

Fay Isamoyer, Allentown Pike, expressed her safety concerns for a section
of Allentown Pike located in front of her home. She stated vehicles
traveling in the center left turning lane at a high rate of speed making it
difficult for residents to exit from their properties. She feels the
development of Maidencreek Township has contributed to the unsafe
conditions along this section of highway and any additional development
such as the proposed development of the former Schaeffer property will only
make it worse. She asked that the Police monitor this section of highway.

Keith Hartman and Elizabeth Hartman, Allentown Pike, agreed with the
previous comments made by Fay Isamoyer. They hoped the Board would take
their safety concerns into consideration when the proposal for the zoning
change of the Schaeffer property is considered.

Karl Bolognese stated he would ask the police department to monitor this
section of the Allentown Pike for any traffic violations.

Terry Rarick agreed the conditions along the Allentown Pike (SR 222) are
unsafe in many areas. Penn Dot is in the process of conducting a study of
this area. The length of time to complete the study and the improvements
will not be happening in the near future. The developments may have
contributed to the traffic problems, but the majority of traffic on the
Allentown Pike is through traffic, not residents from the developments in
Maidencreek Township.

Heather Quillman, a member of the Park and Recreation Board, questioned why
$20,000.00 in wages came out of the Park and Recreation Budget. When will
the Board make a decision to increase the recreation fee for developments?

Terry Rarick explained the budgeted $20,000.00 for payroll in the Park and
Recreation Budget pays employees when work is completed in recreational
areas. Work in recreational areas includes mowing, and general maintenance
of the areas. The Board will act on the increase of the Park & Recreation
Fee in the near future. Increasing the Park and Recreation Fee for
residential areas is not the problem; the Board must examine their options
to assess Commercial development

Nancy Werner, Troxel Road, asked about the status of the proposed Noise
Ordinance and will any existing problems be grandfathered in this new
ordinance?

The Board informed Nancy Werner there were several issues that must be
addressed before adoption of the proposed Noise Ordinance. No areas will
be "grandfathered".

Marty Buck, Troxel Road, feels the residents of Troxel Road are being
"picked on" because they received notices to change their addresses. He
is very unhappy that he was not made aware of the address change before it
occurred and being forced to comply will be very costly.

Ruth Manmiller explained address changes have been in the process for the
past three years. All planning has been in conjunction with Berks County
Communications, the Post Office, and the township. Maidencreek Township
residents receive mail service through six different post offices.
Starting January 2000 each postal area has been notified of the new
addresses. Address corrections and/or adjustments should be completed by
December 31, 2000. Notification of address changes and/or corrections
have been in the Township newsletter for the past three years.

Carol Kopher, Pleasant Hill Road, is concerned about the increase of
traffic and everyone's disregard for safety. Her husband on numerous
occasions must move large farming equipment through the intersection of
Allentown Pike and Pleasant Hill Road. Should another development be
approved (Schaeffer property) traffic would become worse. Her concern for
her husband's safety when crossing Allentown Pike has caused her to
seriously consider calling the police to stop traffic.

Terry Rarick stated the traffic congestion is caused for the most part by
through traffic, not development traffic. Karl Bolognese advised Carol
Kopher to call the police, if she thinks it is necessary to stop traffic
when her husband must travel through the Allentown Pike and Pleasant Hill
Road intersection.

Cindy Stump, Maidencreek Road, has concerns about the increased traffic on
the Allentown Pike. She questioned why zoning rules and regulations are
adopted, if they are changed so easily.

Lynford Weber, Hoch Road, stated the developments have caused an impact on
the roadways in this area. He can remember riding bike or taking a walk on
Hoch Road and not be concerned about traffic. He feels he no longer can
safely walk or ride bike on Hoch Road.

Harold Burgert, East Wesner Road, questioned with all the homes built in
the past three years, where are all the cars coming from? He wants to know
when the Board will draw the line to stop the developments or at least slow
them down. He feels the Board is inviting developers to the township.

Karl Bolognese and Terry Rarick agreed the Board is doing all they can to
preserve the agriculture areas by increasing the Agriculture Security
areas. However, the Board can not control what a property owner does with
their land. If they choose to sell their property to a developer, the only
thing the Board can do is make sure the project conforms to all subdivision
and zoning regulations.

Ernie Marshall, Troxel Road, did not understand the reasoning behind the
recent notice to change his address. He is unhappy with the inconvenience
the changes will cause him, but he will comply.

Tina Poole, Lee Spring Road, is concerned about the on-lot sewage problems
on the Martin Retirement Village property. She stated the sewage is on the
surface causing odor and possible contamination. She questioned if an
inspection had been made and will Mr. Martin be forced to pump the septic
tank. She felt he should pump the tank on a regular basis out of respect
and courtesy to the neighbors.

The Engineer informed Tina Poole the SEO had inspected the septic tank and
surrounding area upon receiving a call from Terry Manmiller. Details are
being discussed about having the system pumped and if Mr. Martin, owner of
Retirement Village, does not comply he will be cited.

Terry Rarick made a motion, seconded by Karl Bolognese, authorizing the
Solicitor to inform
Mr. Martin he has ten (10) days to clean up the area or he will be cited.
Motion carried. Terry Manmiller was advised to inspect on a regular basis
to make sure this would not happen again. As Phase II of Retirement
Village nears final approval and completion, the sewage problems will be
corrected.

Larry Kunkel, 5 Lake Shore Drive, questioned the results of the lighting
problems at Tom's.

The Engineer stated he would have a report by the December 14, 2000 Board
of Supervisors meeting.

Gary Rollman, Orchard Road, requested permission for his Bike Club to use
the roadways behind Lake Ontelaunee for time trials in Spring of 2001.

The Board thanked Gary Rollman for advising the Board of his event and
asked that he comply with all notifications, as he had in the past.

Randy Wolfe, West Walnut Tree Drive, questioned if the tax revenue received
through the millage increase is deposited in a separate account. He
requested emergency headquarters information to be published in the next
newsletter.

The Board informed Randy Wolfe tax revenue received for Park and Recreation
is deposited in CD's and a checking account at the First National Bank in
Leesport Bank.
Daniel Miller, Blandon Fire Company Chief, informed Mr. Wolfe, the type of
emergency and
location would determine which emergency command center would open. He
asked the Board to consider amending the Burning Ordinance to reflect, no
burning in any residential area. It no longer is safe to burn in any of
the residential sections of the township.

ENGINEER'S REPORT

MARTIN RETIREMENT VILLAGE: Terry Rarick made a motion, seconded by Karl
Bolognese to approve the review extension to 2/21/01 for Martin Retirement
Village. Motion carried. A permit to dig under the railroad must be
obtained and language in the sewage connection agreement is in review by
DEP.

GOLDEN MANOR REVISION: Terry Rarick made a motion, seconded by Karl
Bolognese to approve the review extension to 12/31/00 for Golden Manor
revision. Motion carried.

BLANDON MEADOWS V, PHASE II: Robert Ludgate, Jr. presented a final plan
with the addition of the alley and necessary corrections for plan approval.
The developer will proceed with the installation of the pedestrian bridge
and sidewalk. A fee-in-lieu of Open Space will be paid to the Township.
Upon completion, the developer will be reimbursed for his costs to install
the bridge and sidewalk from the funds on account with the township. Terry
Rarick made a motion, seconded by Karl Bolognese, to approve Blandon
Meadows V, Phase II - Final plan. Motion carried. A GPA permit has been
applied for to address the storm water problem in Phase I of Blandon
Meadows V.

PENN BIOMEDICAL, Land Development: Terry Rarick made a motion, seconded by
Karl Bolognese, granting waivers to 504.A.5 allowing driveway width of 20',
and to Section 406.A.2. Preliminary plan requirement to final plan review
per 10/26/00 Planning Commission letter. Waiver
of 515. F. & G screening requirements was rejected. Motion carried.

EAST WESNER ROAD, STREAM RELOCATION: Terry Rarick made a motion, seconded
by Karl Bolognese, authorizing the Chairman to sign the contracts for
relocation of the stream along East Wesner Road, contractor must start with
in the next ten (10) days. Motion carried.

SUBDIVISION IMPROVEMENTS AGREEMENTS LOC/ESCROW RELEASE LETTERS: Terry
Rarick made a motion, seconded by Karl Bolognese, authorizing the Chairman
to sign the Subdivision Improvement Letters of Credit for payment of
$44,834.47. Motion carried.

SEO REPORTS AND CONSTRUCTION STATUS REPORTS: The Engineer distributed SEO
reports and development/construction status reports to the Board.

SOLICITOR'S REPORT

SCHAEFFER PROPERTY - REZONING REQUEST: The Albert Schaeffer property is
located at the intersection of Allentown Pike and Schaeffer Road. The
developer plans for the 145-acre tract of land include a 270-lot
residential subdivision and commercial development of property fronting
along Allentown Pike. Zoning changes requested are "A" Agriculture to "C-
1" Commercial and "A" Agriculture to "R-2a" Residential. Terry Rarick
made a motion, seconded by Karl Bolognese authorizing the Solicitor to
advertise a Public Hearing for the above Zoning request to be held November
30, 2000 at 7:30 PM. Alternate date December 18, 2000.

RESOLUTION 22-2000 - Amending the fee schedule for performing various
plumbing services within Maidencreek Township. Terry Rarick made a motion,
seconded by Karl Bolognese to adopt the new fee schedule for various
plumbing services with in Maidencreek Township. Motion carried.

RESOLUTION 23-2000 - Establish the standard for construction specifications
for building sewer and water connection lines pursuant to CABO. Terry
Rarick made a motion, seconded by Karl Bolognese to establish the standard
for construction specifications for building sewer and water connection
lines pursuant to CABO. Motion carried.

RESOLUTION 24-2000 - Dedication of Calabria Drive, Carmen Drive, Venice
Drive and Riviera Drive located in Shadow Ridge I. Terry Rarick made a
motion, seconded by Karl Bolognese to accept dedication of Calabria Drive,
Carmen Drive, Venice Drive and Riviera Drive located in Shadow Ridge I.
Motion carried.

OLD BUSINESS

Terry Rarick made a motion, seconded by Karl Bolognese authorizing the
payment of $500.00 to the Tri-Valley YMCA for recreation night held at the
Fleetwood Community Center. Motion carried.

Michael Weiser, Chief of Police conducted a traffic study in the area of
Wales Way and Cassidy Court, as requested. During periodic studies of the
area the Chief has determined installation of a stop
sign is not necessary.

Gloria Kemmerer asked the Board, should they consider purchasing the
commercial property located at the intersection of Park Road and East
Wesner Road to be included in the Community Park, would they conduct a
public hearing?

Terry Rarick stated there would be no public hearing should they decide to
purchase the land located at the intersection of Park Road and East Wesner
Road to be included in the Community Park.

NEW BUSINESS
The Board was waiting for reports from Berks EIT to move forward on the
completion of the 2001 budget. It has been determined there would be no
tax increase for 2001. Another budget meeting will be conducted 11/13/00.

SECRETARY'S QUESTIONS

SHADOW RIDGE STREET LIGHTS: Terry Rarick made a motion, seconded by Karl
Bolognese authorizing the preparation of a resolution from GPU to activate
the streetlights on Calabria Drive, and Riveria Drive in Shadow Ridge II.
Motion carried.

Terry Rarick made a motion, seconded by Karl Bolognese authorizing the
Secretary - Treasurer to make final payment on the loan at the First
National Bank in Fleetwood for the loader and 2000 GMC truck. Motion
carried.

EXECUTIVE SESSION: 9:05 PM - 9:35 PM: Real Estate, Pending Litigation

Terry Rarick made a motion, seconded by Karl Bolognese authorizing the
Solicitor to discuss the proposal and make an offer for the purchase of
land located at the intersection of Park Road and East Wesner Road. Motion
carried.

The meeting was adjourned at 9:35 PM

Respectfully submitted,

Ruth M. Manmiller
Recording Secretary

CC: Board of Supervisors
Terry Manmiller, Operations Director
Richard Orwig, Solicitor

Thomas Unger - Systems Design Engineering, Inc., Township Engineer
Planning Commission
Park and Recreation Board
Zoning Hearing Board
Paul Herbein, Zoning Hearing Board Solicitor
Maidencreek Township Authority
Robert Hobaugh, Esq., Maidencreek Township Authority Solicitor
Tax Collector
Fred Giorgi

Archived from the Maidencreek Township website. Reproduced unaltered; not an official records repository.