ORDINANCE NO._________

AN ORDINANCE OF THE TOWNSHIP OF MAIDENCREEK, BERKS COUNTY,
PENNSYLVANIA AMENDING THE TOWNSHIP OF MAIDENCREEK ZONING
ORDINANCE OF 1993 (TOWNSHIP ORDINANCE NO. 136, ADOPTED JANUARY
27, 1993, AS AMENDED), BY AMENDING ARTICLE II, BY ADDING A
DEFINITION FOR POWER GENERATION; BY AMENDING ARTICLE XII,
SECTION 1202 BY DELETING CERTAIN PERMITTED USES AND MOVING THEM
TO CONDITIONAL USES, BY ADDING NEW SECTION 1202(C) CONDITIONAL
USES; BY AMENDING ARTICLE XIII BY ADDING A NEW SECTION 1323
REGARDING ADDITIONAL REGULATIONS AND STANDARDS FOR POWER
GENERATION AND BY ADDING A NEW SECTION 1324 PROVIDING FOR AN
ENVIRONMENTAL IMPACT ASSESSMENT REPORT; AND AMENDING ARTICLE XV
BY ADDING A NEW SECTION 1504 PROVIDING FOR CONDITIONAL USES AND
STANDARDS RELATED THERETO

WHEREAS January 27, 1993, the Township of Maidencreek, Berks County,
Pennsylvania, enacted Township Ordinance No. 136, known as the Maidencreek
Township Zoning Ordinance of 1993 (the Zoning Ordinance); and,

WHEREAS certain amendments have been made to the Zoning Ordinance
including but not limited to Ordinance No. 140-A, Ordinance No. 143,
Ordinance No. 145, Ordinance No. 156, Ordinance No. 157, Ordinance No. 163,
Ordinance No. 164, Ordinance No. 171, Ordinance No. 189, Ordinance No. 190,
Ordinance No. 191, and Ordinance No. 197; and,

WHEREAS the Planning Commission of the Township of Maidencreek, Berks
County, Pennsylvania, has recommended further changes to Article XII, to
provide for certain commercial industrial uses now permitted by right to be
permitted by conditional use and for certain additional uses to be provided
by conditional use; and,

WHEREAS the Planning Commission of the Township of Maidencreek, Berks
County, Pennsylvania, has recommended further additions to Article XIII, to
provide for additional regulations and standards for power generation as
power generation is being added as an additional use to be provided by
conditional use in Article XII.

NOW THEREFORE be it Enacted and Ordained pursuant to the authority set
forth in the Pennsylvania Municipalities Planning Code and the Pennsylvania
Second Class Township Code, that the Board of Supervisors of the Township
of Maidencreek, Berks County, Pennsylvania, hereby enacts and ordains as
follows:

Ordinance No. 136, known as the Maidencreek Township Zoning Ordinance
of 1993, adopted January 27, 1993, as amended from time to time, is hereby
further amended in the following respects:

Section 1. Amendment to Article II.

Article II, SECTION 204, SPECIFIC TERMS, shall be amended by adding
the following definitions in alphabetical order:

"BIOMASS ENERGY: Shall mean the generation of electricity utilizing
the following:
A. organic material from a plant that is grown for the purpose
of being used to produce electricity or is protected by the Federal
Conservation Reserve Program (CRP) and provided further that crop
production on CRP lands does not prevent achievement of the water quality
protection, soil erosion prevention or wild life enhancement purposes for
which the land was primarily set aside; or

B. any solid non-hazardous, cellulosic waste material that is
segregated from other waste materials including, waste pallets, crates and
landscape or right-of-way tree trimmings or agricultural sources, including
orchard tree crops, vineyards, grain, legumes, sugar and other crop by-
products or residues, but excluding other materials such as hazardous
waste, infectious waste and animal waste as defined in Pa Code title 25,
section 271.1."

"POWER GENERATION: The creation of electrical power by the use of
facilities that encompass the following energy sources; (1) solar (2) wind
(3) geothermal (4) biologically derived methane gas (5) fuel cells (6)
demand cite management (7) distributed generation system and/or (8) biomass
energy, excluding the following: municipal solid waste and animal waste..

Section 2. Amendments to Article XII.

(A) Article XII , SECTION 1201 PURPOSE shall be amended as follows:

(1) Deleting the word "and" at the end of Subparagraph D.

(2) Deleting the period at the end of Subparagraph E. and
replacing it with a semi-colon.

(3) Adding new Subparagraph F. to read: "F. To provide for
heavy commercial uses and heavy industrial uses under certain controlled
conditions; and"

(4) Adding new Subparagraph G. to read: "G. To allow for
heavy commercial, industrial and special intensified agricultural
activities consistent with these purposes."

(B) Article XII, SECTION 1202 PERMITTED USES, Subparagraph A USES BY
RIGHT shall be amended by deleting Paragraphs 5 and 6 and by renumbering
existing Paragraphs number 7 and 8, as number 5 and number 6.

(C) Article XII, SECTION 1202 PERMITTED USES shall be further
amended by adding new Subparagraph D, conditional uses as follows:

"D. CONDITIONAL USES. The following uses are permitted when
allowed by the Board of Supervisors as conditional uses, subject to the
performance standards set forth in this ordinance including but not limited
to section 1204, the other requirements of Article XIII, and the
requirements of Article XV, Section 1504 of this Ordinance:

1. Manufacture of landscape, soil and fuel products.
within a completely enclosed building.
2. Public utility uses.
3. Power generation.
4. Electrical substation.
5. Heavy Commercial uses which shall be carried on in a
completely enclosed building except for off street
parking and loading facilities, including but not
limited to wholesale business, warehousing
establishments, truck and freight terminals, delivery
and distribution centers, mechanical and vehicle
equipment repair, and dyeing and dry cleaning plants.
6. Heavy Commercial or Industrial uses including retail
or wholesale sale of building materials, farm
equipment, construction equipment, businesses for the
sale or storage of new and used machinery, businesses
for the sale or storage of vehicles or trailers.

(D) New Section 1204 shall be added to read:

"SECTION 1204 PERFORMANCE STANDARDS FOR CONDITIONAL USES:

A. The following performance standards shall be met for all
conditional uses provided in Section 1202 (D). These standards supplement
the performance standards set forth in Article XIII of this Ordinance which
shall also be met. However in the event of any conflict, the specific
provisions of these performance standards shall control.

1. All operationsAny operations that will emit sound
beyond the boundary lines including but not limited to deliveries, fuel
loading, materials movement, and the use of vehicles that emit warning
beepers shall only be operated between the hours of 7:00 a.m. and 108:00
p.m. unless they are operated within a completely enclosed, insulated
enclosed structure with all windows and doors being closed during such
operations outside of those hours.

2. The owners shall demonstrate full compliance
with all federal and state statutes and regulations applicable to the
particular activity. The Applicant must demonstrate that as at the time of
the conditional use hearing applications have been filed with all other
governmental authorities having jurisdiction. While permits are not
required as and at the date of hearing, the Board may condition any
approval upon receipt of such permits. Under no circumstances shall any
use or occupancy permit be issued without proof of receipt of all other
governmental permits and approvals.

3. Maximum height may be exceeded if demonstrated to the
satisfaction of the Board of Supervisors that exceeding maximum height is
required based on the technology and/or permitting of the activity
involved. However, the specific height shall be determined as part of the
conditional use process. In addition and notwithstanding any contrary
provision in this Ordinance, additional front, side, and rear yard setbacks
shall be required at the rate of three (3) feet additional setback for
every one foot addition of height exceeding the maximum height provided in
section 1203. In addition, if height is exceeded, lot size requirements
shall also be increased to the extent necessary to accommodate the proposed
structure. The five (5) acre minimum lot size and the additional setback
requirements for exceeding height shall not be used to justify a variance
for lot size or yard setback requirements.

4. The minimum height size for screen plantinglandscape
buffer, including berm, shall be plantings of eight (8) feet tall upon
planting, reaching a height of eleven (11) feet no later than three (3)
years from the date of planting. The minimum height of plantings shall be 5
(five) feet. The minimum depth of screen plantingthe landscape buffer shall
be twenty (20) feet.

B. In addition the above, Power Generation Facilities shall meet
the requirements of Article XIII, Section 1323."

Section 3. Amendments to Article XIII.

(A) Article XIII, Section 1304 B is hereby amended by adding the
following sentence:

"This exception does not apply to Power Generation Facilities or
electrical substations."

(B) Article XIII is hereby amended by adding a new section 1323:

"Section 1323. Additional Regulations for Power Generation

AI. Power Generation Facilites

1A. Lot Size. Minimum lot size for lots to be used for power
generation is ten (10) acres. Lot size shall be increased if required to
meet setbacks as described in section 1204 A (3).

2B. Power Generation Facilities Location

1a. Power Generation Facilities shall be located, sited
and constructed in areas that provide the least visual impact and where
they do not interfere with agricultural and natural resource production and
conservation.

2b. They shall be sited in locations that will not pose
a significant threat to health, safety and security of the community,
residents, schools, livestock, universities or correctional facilities.

3C. Height of Power Generation Facility

a1. The height of any Power Generation Facility shall
accord with municipal zoning and shall not exceed the height required to
meet power generation and environmental quality objectives. The applicant
shall submit with the application such documentation as is necessary to
establish these standards.

b2. No facility shall be approved which is of such a
height as to require artificial lighting unless it can be clearly
established by the applicant that such greater height is required based
upon technological consideration.

4D. Appearance and Visibility of Power Generation Facility

a1. No facility shall be artificially lighted or marked
except as required by applicable laws, ordinances, statutes, codes, rules
and regulations. However,
if artificial lighting is required, it shall be as unobstructive and
inoffensive as is possible under appropriate ordinances, statutes, laws,
rules, regulations and codes. The applicant shall provide a detailed plan
for such lighting.

b2. Power Generation Facilities shall be sited and
designed to have the least visually intrusive effect possible on the
surrounding area. Wind turbines, emissions stacks and other towers shall be
constructed of a non-reflective materials, painted with a rust-preventive
paint of an appropriate color, and the remainder of the facility shall be
designed to include building materials, colors, textures, and landscaping
consistent with the immediate area and shall utilize concealment
technology. Wind turbines, emissions stacks and other towers shall be
constructed of a non-reflective materials, painted with a rust-preventive
paint of an appropriate color. They shall be The facilities shall be
compatible and blend with the surroundings and be maintained in a safe and
stable condition.

3. If artificial lighting is required it shall be as
unobstructive and inoffensive as is possible under appropriate ordinances,
statutes, laws, rules, regulations and codes. The applicant shall provide
a detailed plan for such lighting.

5E. Security of Power Generation Facility

a1. All turbines, towers, supporting structures
including guy wires, transmitters, transformers, transmission lines,
control points, sheds and other related facilities shall be secured and
maintained in such manner as to prevent access by any persons other than
those authorized to operate or service the said facilities. The manner in
which the facility is to be secured shall be based on a security plan
subject to the approval of the Township. In no case shall site perimeter
security fencing be less than eight (8)fifteen (15) feet in height.

b2. Warning signs shall be conspicuously posted on and
around the perimeter of the propertyy as determined by the Township
Engineer.

6F. General Requirements

a1. The design, construction and maintenance of the
Power Generation Facility shall be in accordance with all applicable local,
state and federal ordinances, laws, statutes, codes, rules and regulations
and industry standards and certification of compliance shall be provided by
the applicant.

b2. All utilities servicing the Power Generation
Facility shall be installed underground.

3. All Power Generation Facilities shall be sited and
designed to have the least visually intrusive effect possible on the
surrounding area. The facility shall be designed to include building
materials, colors, textures, and landscaping consistent with the immediate
area and shall utilize stealth or concealment technology.

4. All Power Generation Facilities shall be serviced by
either a public or private road having adequate area for the ingress and
egress and operation of all service, construction, and emergency equipment
and vehicles. The use of existing and public roads shall be maximized.
Where access is by private road the applicant shall provide evidence of the
perpetual legal right to utilize the private road for the applicant's
purposes.

7G. Annual Certification

The operator of a Power Generation Facility shall annually certify in
writing to the Township that is in compliance with all applicable local,
state and federal laws.

H. Removal of Power Generation Facility

The applicant and/or developer of the Power Generation Facility shall
certify that all antennas, towers, turbines, dams, supporting structures
including guy wires, transmitters and control points, sheds and other
related facilities will be removed and the site restored to its original
state upon discontinuance of use of the facility for a period of two (2)
years, unless extended by the Township, at his/her sole expense.

8.I. Traffic Impact Analysis

a1. A traffic impact analysis prepared by a professional
traffic engineer shall be provided and shall address all aspects of traffic
safety and improvements which will be necessitated by the traffic
generation of the facility.

b2. The traffic impact analysis shall contain the
following:

(1)a. A study impact area determined by the Township
Engineer in conjunction with the owner's
traffic engineer.,

(2)b. An inventory of site conditions which shall
include:

(a1) A sketch plan of the proposed
development.

(b2) Existing average daily traffic (ADT) on
roads within the study area. This shall include traffic
volumes at peak highway hours and at peak development
generated hours.

(c3) Existing levels of service (A through F)
as defined in the Highway Capacity Manual of the Institute
of Transportation Engineers on roads and intersections
within the study area. The level of service for signalized
intersections refers to the average stopped delay per
vehicle during a fifteen-minute analysis period.

(d4) List of pending or proposed development
within a reasonable distance of the development and
impacted intersections determined by the Township.

(e5) Other information requested by the Township.

(3)c. The impact of the proposed development on the
Township's transportation system, which shall include:

(a1) The number of trips generated by the
proposed development (in and out at peak hours).

(b2) This distribution of trips for all area
roads immediately postdevelopment and the future
distribution of traffic five years after development. Note
the annual growth rate assumed.

(c3) The estimated average daily traffic on
roads within the study area and the proposed development.

(d4) The levels of service (A through F) as
defined in the Highway Capacity Manual of the Institute of
Transportation Engineers after the anticipated development.

(e5) Documentation of the sources(s) of
generated traffic estimates (such as the Institute of
Transportation Engineers, Trip Generation Report).

(f6) Evaluation of the adequacy of the
development's ingress and egress points.

(4)d. Documentation of improvements proposed to
mitigate any projected adverse transportation impacts caused by the
proposed development on Township roads. This shall include, when
warranted, such improvements as road widening, intersection
improvements, acceleration/deceleration lanes, traffic control
devices, signs, or other improvements deemed necessary by the
Township.

BII. Additional Performance Standards for Power Generation

The following performance standards shall apply to Power Generation
Facilities within the Township. Should the Township, at any time, have
reason to suspect that the performance standards of this article have been
violated, the Township shall give due notice and order to the suspected
violator to provide evidence of compliance or to cease, abate and correct
the violation, within 10 days of the notice.

1. Air Quality. There shall be no emission of smoke, ash, dust, fumes,
vapors gases or other matter toxic or noxious to air which violates local,
state or federal Air Quality standards and/or rules and regulations.
A. Smoke control.

1. No visible grey smoke shall be emitted from any chimney,
stack or other source of visible grey smoke, greater than No. 1 on the
Ringlemann Smoke Chart as published by the United States Bureau of
Mines.

2. Smoke of a shade not darker than No. 2 on the Ringlemann
Smoke chart may be emitted for not more than four minutes in any 30
minutes.

3. These provisions, applicable to visible grey smoke, shall
also apply to visible smoke of a different color, but with an
equivalent apparent opacity.

B. Control of dust and dirt, fly ash, fumes, and gases.

1. No emission shall be made which can cause any damage to
health, to animals, vegetation or other forms of property, or which
can cause any excessive soiling at any point.

2. No emission of liquid or solid particles from any chimney,
stack or otherwise shall exceed 0.3 grains per cubic foot of the
covering gas at any point.

3. For measurement of the amount of particles in gases
resulting from combustion, standard correction shall be applied to a
stack temperature of 500�F. and 50% excess air.

2C. Control of noise. Noise that exceeds the standards set forth
in the Maidencreek Township Noise Ordinance, as amended, shall not be
permitted to emanate from the property.

3D. Control of odors. There shall be no emission of odorous gases
or other odorous matter in such quantities as to substantially impair the
use and enjoyment of surrounding properties. Any process which may involve
the creation or emission of any odors shall be provided with a secondary
system, so that control will be maintained if the primary safeguard system
shall fail. There is hereby established as a guide in determining such
quantities of offensive odors, Table III (Odor Threshold) in Chapter 5, Air
Pollution Abatement Manual, copyright 1951 by Manufacturing Chemists'
Association, Inc., Washington DC.

4E. Control of glare or heat. Any operation producing intense
glare or heat shall be performed within an enclosed building or behind a
solid fence in such manner as to be completely imperceptible from any point
beyond the lot lines.

5 F. Control of vibration. No vibration which is discernible
to the human sense of feeling shall be perceptible without instrument at
any point beyond the lot line. Vibration which is not discernible to human
sense but which is at low or high frequencies capable of causing discomfort
or damage to life or property is prohibited beyond the property line and
must be monitored and controlled within the property line to meet
acceptable industrial use standards.

6G. Control of radioactivity or electrical disturbance. There
shall be no activities which eemit dangerous or harmful radioactivity.
There shall be no electrical disturbance (except from domestic household
appliances) adversely effecting the operation of any equipment located
beyond the property of the creator of such disturbances.

7H. Refuse areas, waste disposal and outdoor storage facilities.

1. No flammable or explosive liquids, solids or gases shall
be stored in bulk above ground; provided, however, that tanks or drums
of fuels directly connecting with energy devices, heating devices or
appliances located on the same lot as the tanks or drums of fuel are
excluded from this provision.

2. All outdoor storage facilities for fuel, raw materials and
products and all fuels and all raw materials and products stored
outdoors shall be secured by a fence or other approved structure.

3. No materials or wastes shall be deposited or stored upon a
lot in such form or manner that may be transferred off the lot by
natural causes or forces.

4. All materials or wastes which might cause fumes or dust or
which constitute a fire hazard or which may be edible or otherwise be
attractive to rodents or insects shall be stored outdoors only in
closed containers.

8I. Materials handling, transfer and storage areas. All indoor and
outdoor material handling and transfer storage areas shall provide for
accidents caused by natural occurrence, equipment failure or human error so
as to contain spillage or leakage of solid, liquid or gaseous materials and
to further facilitate the cleanup or dispersal of said materials without
causing damage to life, ecological systems, property or the sanitary sewer
system

9J. Electric, diesel, gas or other power. Every use requiring
power shall be so operated that the service lines, substation, etc., shall
conform to the most acceptable safety requirements recognized by the
Pennsylvania Bureau of Labor and Industry, shall be so constructed,
installed, etc., to be an integral part of the architectural features of
the plant or if visible from adjacent residential properties, shall be
concealed by landscape screening in accordance with Article XII, Section
1204 A (4) of this Ordinance.

10K. Industrial waste or sewage. No use shall be conducted in such
a way as to discharge any treated or untreated sewage or industrial waste
treatment and disposal except as shall be approved by sanitary engineers or
other qualified persons employed by the Township at the expense of the
owner of the premises. Where the sanitary sewers of the Township and its
Municipal Authority are involved, approval of the Sewer Authority shall be
required.

11L. Provision and use of water. All water requirements shall be
stated in the application. Water shall be supplied by the Maidencreek
Township Municipal Authority unless said Authority is unable or so chooses
not to provide water use at which time the applicant may use well supplied
water. Water may be supplied from wells only after approved or accepted
geologic study furnished by the applicant and certification by a
professional hydro-geologist that the underground water supply and levels
will not be appreciably altered in such a way as to endanger the water
level and supply for other properties.

12. M. New technology of significant hazard potential. Any
industrial process or research activity conducted using chemical,
biological or radiological techniques and agents which are new to the
industry or process and which may present significant hazard to the
physical environment beyond the site of process application or research, or
in which environmental hazards, because of their use, is unknown, must be
disclosed to the Board of Supervisors prior to use.

CIII. Supplemental Information

In addition to the other requirements of this Ordinance, subdivisions
and land developments involving the establishment of Power Generation
Facilities, including but not limited to solar, water, and wind power shall
provide the supplemental information noted in this Section.

1A. The applicant shall attach a statement to the application
stating that the facility shall be designed, built beand maintained in a
safe manner and in compliancein accordance with all applicable local, state
and federal ordinances, statutes, rules and regulations; the statement
shall be signed by the applicant.

2B. If the applicant is an entity other than a person the type of
entity shall be identified and it shall submit with the application proof,
satisfactory to the Township, that it is authorized to do business in the
Commonwealth of Pennsylvania, that is properly organized and operating
under the laws of its state of organization and the Commonwealth of
Pennsylvania, and that it has legal authority to make the application,
construct, lease or operate the facility.

3C. If the applicant is not the person or entity that will be
operating the facility, the applicant shall, in writing, identify the
operator by name, address and telephone number.

D. Documentation that demonstrates the need for the Power
Generation Facility. Such documentation shall include propagation studies
of the proposed site and all adjoining planned, proposed, in-service or
existing sites within a 50-mile radius.

4E. A diagram, drawn to scale, setting forth distances, dimension
and heights for all structures, landscaping, trees, fences, existing or
proposed, located within 500 feet of the property boundary of the proposed
facility.

5F. A narrative description with diagrams, drawings and plans, done
to scale, of the proposed Power Generation Structures and all related
fixtures, appurtances, and apparatus, materials, color, lighting and height
above present existing grade.

6G. The applicant shall submit proof that the proposed facility is
permitted and/or licensed or will be permitted and/or licensed at or prior
to final plan approval. The applicant shall submit as proof, as applicable,
copies of the permits and/or licenses required by law, rule, ordinance,
regulation and code, including, but not limited to the PA DEP, PUC, US EPA
and United States Department of Energy (US DOE) license applicable to the
intended use of the facility.

7H. The applicant shall demonstrate that the site is adequate to
assure the stability of the proposed facility after considering such
matters as are appropriate, including but not limited to topographic and
geomorphologic studies and analysis, subsurface and substrate conditions,
drainage plans, and biological resource surveys.

8I. The applicant shall demonstrate that the Power Generation
Facilities and all components are designed and will be built and maintained
in accordance with all local, state and federal ordinances, statutes, rules
and regulations.

9J. The applicant shall submit an environmental impact assessment
report satisfactory to the Township in accordance with Section 1324 of this
Ordinance.

10K. A hazardous and solid waste management plan shall be prepared
and submitted that documents the type and amount of wastes, storage and
disposal methods, and an emergency response action plan shall be submitted
that meets local, county, state and federal requirements. No final plan
shall be approved unless the hazardous and solid waste management plan is
approved by the Township.

11L. The applicant shall submit a Visual Impact Assessment which
shall include (i) a Zone of Visibility Map to determine the locations from
which the facility may be observed, (ii) pictorial representations of key
viewpoints as may be appropriate, including but not limited to public
roads, public parks, public lands, historic districts and sites and from
such other locations where the site is visible to large numbers of persons,
(iii) an assessment of the visual impact of the facility as it relates to
appropriate screening and (iv) any applicable assessments from the
Pennsylvania Historic and Museum commission related to historic property
impacts.

12M. The applicant shall submit a plan for water discharge, detailing
how local, state and federal water quality requirements will be met and how
water will be cooled to the average seasonal temperature of the receiving
body prior to discharge in order to prevent thermal pollution.

13N. The applicant shall submit a written determination as to the
necessity of lighting the Power Generation Facility or any of its
components in accordance with Federal Aviation Administration (FAA)
regulations, as well as all correspondence and filing with, to and from the
FAA.

14O. All certifications, reports, materials, drawings, diagrams or
similar materials shall be prepared, signed and attested to be accurate and
correct by a person, persons, or entity, satisfactory to the Township, who,
by training or education or both is, in the judgment of the Township,
qualified to prepare them; when appropriate, the person preparing these
certifications, reports, drawing, diagrams, and related material shall be
an engineer licensed by the Commonwealth of Pennsylvania."

(C) Article XIII is hereby amended by adding a new section 1324.

"Section 1324. Environmental Assessment Report Required for Industrial
and SIA Uses

A. In order to more effectively evaluate a proposed subdivision
and/or land development zoning special exception or conditional use
request, the applicant shall be required to disclose the environmental
consequences or effects of such proposals through the submission of an
Environmental Impact Assessment (EIA) Report.

B. An EIA report shall be submitted for all proposed uses in
Industrial and SIAthe following.:

1. Any proposed land development and/or subdivision
containing ten (10) or more lots/dwelling units.

2. Any proposed land development and/or subdivision where a
use, building, driveway or other improvement is proposed and is governed by
the conditional use or special exception provisions of the zoning
ordinance.

3. The submission of an EIA Report is exempted for the
division of land for agricultural purposes into parcels of more than ten
(10) acres not involving any new street or easement of access.

C. The EIA report shall contain text, tables, maps and analyses
which document the probable impact resulting from the proposed subdivision
and/or land development which is the subject of the special exception or
conditional use request in accordance with the format and content outline
specified below.

D. Eight (8) copies of the EIA report shall be submitted in
accordance with the format and content specified below. Within the EIA
report, specific emphasis shall be directed toward the proposed project's
effects on and relationship to applicable site, neighborhood (including
areas in adjacent townships where applicable) and township-wide resources,
conditions or characteristics. The EIA report shall include text, tables,
maps and analyses for the purpose or describing the project site, proposed
uses(s), environmental characteristics and the environmental effects of the
proposal.

E. Methods for evaluating cumulative environmental effects will
depend upon the availability of data, but the scope and goal of the
evaluation should remain consistent. Methods may involve one or more of
the following:

1. Geographic Information System Analyses
2. Questionnaires, Interviews & Panels
3. Checklists
4. Matrices
5. Networks & System Diagrams
6. Modeling
7. Trend Analyses

F. The EIA report shall be prepared by a registered engineer,
architect, landscape architect or land planner and shall address the
following issues presented below.

1. An identification of the site location and area through
the use of a location map drawn at a scale of not more than two thousand
feet (2000') to the inch. The location map shall depict all streets,
adjoining properties, zoning district boundaries and municipal boundaries
within three thousand (3000') feet of any part of the tract. In the case
of development of a section of the entire tract, the location map shall
also show the relationship of the section to the entire tract.

2. An identification of the site character and appearance
through the presentation of black and white photographs or copies thereof..
Such photographs shall provide a representation of what the site looks
like from the ground. Photographs should be properly identified or
captioned and shall be keyed to a map of the site.

3. An identification of the nature of the proposals through
the presentation of the following:

a. A site development plan including notes pertaining to
the number and type of lots or units, the square footage and/or acreage of
the tract and a depiction of the features which are proposed such as
streets, driveways, parking area, buildings and other structures, and all
impervious surfaces. The plan shall be drawn at a scale of not more than
one hundred feet (100') to the inch and may be submitted as an attachment
to the report. The plan shall reflect all the information required for a
preliminary plan under the Township's Subdivision & Land Development
Ordinance.

b. Plans and elevations depicting the proposed size,
square footage, height, number of rooms (where applicable) of buildings
and/or other structures.

c. A statement indicating the existing and proposed
ownership of the tract and where applicable, the type of ownership,
operation and maintenance proposed for areas devoted to open space or
otherwise not under the control of a single lot owner.

4. An identification of physical resources associated with
the natural environment of the tract including such features as geology,
topography, soils, hydrology and the like. The identification of physical
resources shall include a narrative description of the qualitative and
quantative aspects of each of the resources mentioned above. In addition,
these resources shall be mapped at a scale of not more than one hundred
feet (100') to the inch as specified below and may be either incorporated
into the EIA report or submitted as attachments to the report.

a. A map depicting the geological characteristics of the
tract. Such map shall define the location and boundaries of the rock
formations at or influencing the tract and features such as faults and/or
fractures.
b. A map depicting the topographical characteristics of
the tract. Such map shall contain contours with at least two (2) foot
intervals; and, shall depict slopes from zero to four (0-4) percent, four
to ten (4 - 10) percent, ten to fifteen (10 - 15) percent, fifteen to
twenty-five (15 - 25) percent, and greater than twenty-five (25) percent.

c. A map depicting the scoil characteristics of the
tract. Such map shall depict all soil types and shall include a table
identifying soil characteristics pertinent to the proposed subdivision
and/or land development such as depth of bedrock, depth of water table,
flood hazard potential, and limitations for septic tank filter fields.

d. A map depicting the hydrological characteristics of
the tract. Such map shall depict: surface water resources, their drainage
characteristics, watershed and flood plains, and groundwater resources.
Surface water resources include features such as creeks, runs and other
streams, ponds, other natural bodies of water, springs, wetlands, and any
man-made impoundments. Groundwater resources include features such as
aquifers and aquifer recharge areas.

5. An identification of biological resources associated with
the natural environment of the tract including such features as vegetation
and wildlife. The identification of biological resources shall include a
narrative description of each of the resources mentioned above. In
addition, these resources shall be mapped at a scale of not more than one
hundred feet (100') to the inch, as specified below; and, may be either
incorporated into the EIA report or submitted as attachments to the report.

a. A map depicting the vegetation characteristics of the
tract. Such map shall define the locations and boundaries of the wooded
areas of the tract and shall note the types of vegetation associations
which exist in terms of their species types and sizes. In addition, all
trees twelve (12) inches in caliper or greater, shall be accurately located
on the map either as free standing trees or as tree masses.

b. A map depicting characteristics associated with
wildlife habitats. Such map may draw upon the vegetation, hydrology and
soil maps in order to express habitat characteristics associated with
terrestrial and aquatic wildlife on the tract and the relationship of the
overall habitat(s).

6. An identification of the land use conditions and
characteristic associated with the tract such as: current and past use,
land cover, and encumbrances; and, the relationship of these to adjacent
tracts. The identification of land use conditions and characteristics
shall include a narrative description of the above. In addition, the
following maps drawn at a scale of not more than one hundred (100') feet to
the inch, unless otherwise noted, shall be incorporated into the EIA report
or submitted as attachments to it.

a. A map depicting the land cover characteristics of the
tract. Such map shall define existing features including: paved or other
impervious surfaces, wooded areas, cultivated areas, pasture, old fields,
lawns and landscaped areas and the like.

b. A map depicting any encumbrances to the tract. Such
map shall define easements and other areas where certain use privileges
exist.

c. A map depicting the land uses adjacent to the
proposed tract. Such map may be at the same scale as the location map.

7. An identification of the historic resources associated
with the tract such as areas, structures and/or routes and trails which are
significant. Areas, structures and/or routes and trails included on the
National Register of Historic Places, the Pennsylvania Inventory of
Historic Places and the Historic American Building Survey, and those
identified in the Comprehensive Plan shall be identified. The
identification of historic resources shall include a narrative description
of the above. In addition, a map drawn at a scale of not more than one
hundred feet (100') to the inch depicting historic resources shall be
incorporated into the EIA report or submitted as an attachment to the
report.

78. An identification of the visual resources associated with
the tract and surrounding areas such as areas which have a particular
amenity value and areas which offer interest in viewing the tract. The
identification of visual resources shall include a narrative description of
the above. In addition, a map drawn at a scale of not more than one
hundred feet (100') to the inch depicting visual resources shall be
incorporated into the EIA report or submitted as an attachment to the
report.

9. An identification of the community facility needs
associated with the user and/or resident of the proposed subdivision and/or
land development. The community facility needs assessment shall indicate
in narrative form the type of services which will be in demand. Were
applicable, community facilities (such as schools, park and recreation
areas, libraries, hospitals, and other health care facilities, fire
protection, police protection, ambulance, and rescue service and postal
services) shall be discussed in terms of the ability of existing facilities
and services to accommodate the demands of future users and/or residents of
the lots and/or tract and the need for additional or expanded community
facilities.

10. An identification of the utility needs associated with the
user and/or resident of the proposed subdivision and/or land development.
The utility needs assessment shall indicate in narrative form the type of
installations which will be in demand. Utilities (such as those used for
water supply, sewage disposal, refuse disposal, storm drainage,
communications and electrical transmission) shall be discussed in terms of:
the ability of existing utility installations to accommodate the demands
of the future users and/or resident of the lots and/or tract; the need for
additional or expanded utility installations; the ability to achieve an
adequate, potable quantity of water whenever individual wells are proposed;
the ability to achieve an adequate system for on-site sewage disposal
whenever such a system is proposed; and, the ability to achieve an adequate
system for storm drainage and stormwater management.

811. An identification of the relationship of the
transportation and circulation system needs of the proposed subdivision
and/or land development to the existing street or highway network. A
discussion of this relationship shall be in narrative form and shall
indicate factors such as methods to be used for traffic control within the
tract and at points of ingress to and egress from it; and, expected traffic
volumes generated from the subdivision and/or land development including
their relationship to existing traffic volumes on existing streets for both
peak-hour and non-peak hour traffic conditions. In addition, there shall
be a discussion of the physical condition of existing streets which will
service the proposed subdivision and/or land development and what
improvements are proposed to remedy any physical deficiencies.

12. An identification of the social and demographic
characteristics related to the proposed subdivision and/or land
development. The characteristics which shall be presented in narrative
form shall include a profile of the future users and/or residents of the
lot and/or tract including information such as the number of people
expected. Such information shall be related to initial and completed
subdivision and/or land development conditions.

13. An identification of the economic and fiscal
characteristics related to the proposed subdivision and/or land
development. The characteristics which shall be presented in narrative
form shall include a profile of the township, county and school district
revenues which the proposal may generate and the township, county and
school district costs it may create. Such information shall be related to
initial and completed subdivision and land development conditions.

914. An identification of characteristics and conditions
associated with existing, construction related, and future air and water
quality and noise levels, vibration, toxic materials. Electrical
interference, odor, glare and heat, fire and explosion, smoke, dust, fumes,
vapors and gases and/or radioactive materials.

1015. The implications of the proposed subdivision and/or land
development in terms of: the type of beneficial or adverse effects which
may result from it; and, the duration of these effects in terms of their
short-term or long-term nature. To indicate such effects, there shall be a
discussion of the implications of the proposed subdivision and/or land
development to the resources, conditions and characteristics described in
subsections 4 through 14 above. In addition to a narrative presentation of
implications, the applicant shall display where the subdivision and/or land
development adversely affects the tract's resources, conditions or
characteristics through the use of a map drawn at a scale of not more than
one hundred feet (100') to the inch, wherein the areas adversely affected
from proposed development are highlighted. Such map(s) may be either
incorporated into the EIA report or submitted as an attachment to the
report. Further, the applicant must demonstrate and specify in the EIA
report how and where the findings in the EIA report and its attachments are
reflected in the subdivision and/or land development plan. Potential
environmental impacts resulting from the proposed subdivision and/or land
development can be defined as: cumulative, direct, indirect, positive,
negative, or combination of above. Typical impacts from a proposed
development may occur in the following areas:

a. Landforms (topography, floodplains, related water
quality)

b. Subsurface Conditions (soils, groundwater)

c. Hydrology (drainage, stormwater, water quality, water
supply)
d. Wildlife & Vegetation (vegetation, endangered species
parklands, conservation areas, ecologically critical areas)

e. Land Use (existing zoning, land use, proposed
community comprehensive plans, productive farmland or timberland)

f. Natural Hazards (seismic, other)

g. Cultural Resources (Historic concerns,
architecturally sensitive, archaeologically sensitive)

h. Utilities/Services (energy, solid waste disposal,
water supply, sewer system and drainage)

i. Socio-Economic (employment, demographics, income
levels, aesthetic quality, housing, retail markets, fiscal impacts)

j. Transportation (traffic volumes, traffic circulation,
parking, public transit system)

k. Hazardous Materials (underground storage tanks, site
contamination, storage of hazardous substances, other)

l. Air/Noise (air quality, ambient noise)

116. Alternatives to the proposed subdivision and/or land
development. To indicate such alternatives, the applicant shall submit
exhibits or diagrams which will depict the type of alternatives such as:
revised location, re-design, layout or siting of buildings, roads and other
structures, alternate methods for sewage disposal and water supply,
reduction in size of proposed structures or number of structures, and the
like would preclude, reduce or lessen potential adverse impact or produce
beneficial effects.

127. Probable adverse effects which cannot be precluded. In
indicating such effects a discussion shall be presented regarding whether
they will have primary or secondary implications, that is, whether the
adverse effects will have direct, or indirect influence on a particular
resource, condition or characteristic.

138. Measures to mitigate adverse effects. To indicate such
measures, the applicant shall submit exhibits or diagrams which will depict
the type of remedial, protective and mitigative measures described in
narrative form. These resources shall include those required through
existing procedures and standards and those unique to a specific project,
as follows:

a. Mitigation measures which pertain to existing
procedures and standards are those related to current requirements of the
state, county and/or township for remedial or protective action such as:
sedimentation and erosion control, storm water runoff control, water
quality control, air quality control and the like.

b. Mitigation measures related to impacts which may be
unique to a specific subdivision and/or land development are those related
to efforts such as: revegation, screening, fencing, emission control,
traffic control, noise control, relocation of people and/or businesses,
land acquisition, and the like.

149. Any irreversible environmental changes which would occur
due to the proposed subdivision and/or land development should it be
implemented. To indicate such changes, the use of non-renewable resources
during the initial and continued phases of the subdivision and/or land
development shall be discussed. Further, the loss of environmental
resources shall be indicated through a presentation of the quantity of loss
and related qualitative effects.

G. In making its evaluation, the Board of Supervisors, the Zoning
Hearing Board and/or the Planning Commission may request any additional
information it deems necessary to adequately assess potential environmental
impacts. Further, whenever any information requested in a subsection above
is not applicable to the proposed subdivision and/or land development, the
applicant shall document such inapplicability in the EIA report."

Section 4. Amendments to Article XV.

Article XV, Section 1504. CONDITIONAL USES is hereby amended by
replacing current Section 1504 with the following:

"Section 1504. CONDITIONAL USES.

Conditional Uses shall be heard and determined by the Board of
Supervisors in accordance with all of the following provisions.

A. Application. An Application for Conditional Use shall be
made in writing by filing the same with the Township Manager and/or
Secretary. The filing shall include an original and four (4) copies of a
completed Application together with the prescribed Application Fee.
Applications shall be on forms provided by the Township and shall contain
all of the supplementary information required in the Application. Unless
and until a specific application form is prepared, the Application form for
proceedings before the Township of Maidencreek Zoning Hearing Board shall
be used and shall be supplemented by including the following: (i) a copy
of the current deed of record showing ownership of the parcel involved;
(ii) a plan that at a minimum contains the information required for
preliminary plan submission by the Maidencreek Township Subdivision and
Land Development Ordinance; and (iii) a list of all other governmental
agencies or regulators and a list of related permits to be issued by the
same that are required and/or associated with the activity proposed. The
Applicant may attach such other data and information to enable the
Supervisors to determine compliance with the provisions of this Ordinance.

B. Conditional Use Standards. In order to grant a conditional use,
the Supervisors shall consider and determine that:

1. The use shall be one which is specifically authorized as
a conditional use in the Zoning District wherein the Applicant is seeking a
conditional use;

2. Conditional Use meets all specific standards established
pursuant to the Zoning Ordinance including specific use provisions, as well
as all performance standards and general regulations;

3. The Use conforms with the goals, objectives and policies
of the Township's Comprehensive Plan;

4. The Use conforms with the spirit, purposes and intent of
all other applicable provisions of all other Township Ordinances;

5. The Use conforms with all federal and state regulations
and requirements;

6. Services and utilities are or shall be made available
to service the proposed use;

7. The Use will not generate traffic that will cause undue
congestion or hazardous conditions;

8. The Use is appropriate to the particular site in
question.

9. The Use shall not adversely affect the character of the
general neighborhood, nor the health and safety of residences or workers on
adjacent properties and in the general neighborhood;

C. Review by the Township of Maidencreek Planning Commission. Upon
receipt of a completed Conditional Use Application, the Township Manager
and/or Secretary shall forward a copy of the Application to the Township of
Maidencreek Planning Commission for review and comment. The Planning
Commission shall review and provide comment to the Board of Supervisors
that addresses the requirements for Conditional Use and recommendations
from the Township Planning Commission on all relevant topics related to the
Application.

D. Hearings. The Board shall conduct hearings and make decisions
in accordance with the following requirements:

1. Public notice shall be given and written notice shall be
given to the Applicant, the Zoning Officer, such other persons as the
governing body shall designate by Ordinance and to any person who has made
timely request for the same. Written notices shall be given at such time
and in such manner as shall be prescribed by Ordinance or, in the absence
of Ordinance provision, by rules of the Board. In addition to the written
notice provided herein, written notice of said hearing shall be
conspicuously posted on the affected tract of land at least one week prior
to the hearing.
2. The governing body may prescribe reasonable fees with
respect to hearings before the Boards in accordance with the Pennsylvania
Municipalities Planning Code and/or the Second Class Township Code, as
amended.

3. The first hearing before the Board or Hearing Officer
shall be commenced within sixty (60) from the date of receipt of the
Applicant's Application, unless the Applicant has agreed in writing to an
extension of time. Each subsequent hearing before the Board or Hearing
Officer shall be held within forty-five (45) days of the prior hearing,
unless otherwise agreed to by the Applicant in writing or on the record.
An Applicant shall complete the presentation of his case-in-chief within
one hundred (100) days of the first hearing. Upon the request of the
Applicant, the Board or Hearing Officer shall assure that the Applicant
receives at least seven hours of hearings within the one hundred (100)
days, including the first hearing. Persons opposed to the Application
shall complete the presentation of their opposition to the Application
within one hundred (100) days of the first hearing held after the
completion of the Applicant's case-in-chief. An Applicant may, upon
request, be granted additional hearings to complete his case-in-chief
provided the persons opposed to the Application are granted an equal number
of additional hearings. Persons opposed to the Application may, upon the
written consent or consent on the record by the Applicant and Municipality,
be granted additional hearings to complete their opposition to the
Application provided the Applicant is granted an equal number of additional
hearings.

4. The hearings shall be conducted by the Board or the Board
may appoint any member or an independent attorney as a Hearing Officer.
The decision, or, where no decision is called for, the findings shall be
made by the Board; however, the Appellant or the Applicant, as the case may
be, in addition to the Municipality, may, prior, to the decision of the
hearing, waive decision or findings by the Board and accept the decision or
findings of the Hearing Officer as final.

5. The parties to the hearing shall be the Municipality, any
person affected by the Application who has made timely appearance of record
before the Board, and any other person including civic or community
organizations permitted to appear by the Board. The Board shall have power
to require that all persons who wish to be considered parties enter
appearances in writing on forms provided by the Board for that purpose.

6. The chairman or acting chairman of the Board or the
Hearing Officer presiding shall have power to administer oaths and issue
subpoenas to compel the attendance of witnesses and the production of
relevant documents and papers, including witnesses and documents requested
by the parties.

7. The parties shall have the right to be represented by
counsel and shall be afforded the opportunity to respond and present
evidence and argument and cross-examine adverse witnesses on all relevant
issues.

8. Formal rules of evidence shall not apply, but irrelevant,
immaterial, or unduly repetitious evidence may be excluded.

9. The Board or the Hearing Officer, as the case may be,
shall keep a stenographic record of the proceedings. The appearance fee
for a stenographer shall be shared equally by the Applicant and the Board.
The cost of the original transcript shall be paid by the Board if the
transcript is ordered by the Board or Hearing Officer or shall be paid by
the person appealing from the decision of the Board if such appeal is made,
and in either event the cost of additional copies shall be paid by the
person requesting such copy or copies. In other cases the party requesting
the original transcript shall bear the cost thereof.

10. The Board or the Hearing Officer shall not communicate,
directly or indirectly, with any party or his representatives in connection
with any issue involved except upon notice and opportunity for all parties
to participate, shall not take notice of any communication, reports, staff
memoranda, or other materials, except advice from their Solicitor, unless
the parties are afforded an opportunity to contest the material so noticed
and shall not inspect the site or its surroundings after the commencement
date of hearings with any party or his representative unless all parties
are given an opportunity to be present.

E. Decision by the Board of Supervisors.

1. The Board of Supervisors shall render a written decision
upon applications for conditional use within sixty (60) days of the last
public hearing before the Board. In authorizing or approving any such
conditional use, the Board of Supervisors shall have the power to attach
such reasonable conditions and safeguards as it may deem necessary to
implement the purpose of this Ordinance or to support the purpose of the
district within which the conditional use is or will be located.

2. Where the application is contested or denied, the written
decision shall be accompanied by findings of fact and conclusions based
thereon, together with the reasons therefore. Conclusions based upon any
provision of the Pennsylvania Municipalities Planning Code or upon any
ordinance, rule, or regulation of the Township shall contain a reference to
the provision relied upon and the reasons why the conclusion is deemed
appropriate in light of the facts found.

3. Where the Board of Supervisors has power to render a
decision and fails to do so within the period required here above, the
decision shall be deemed to have been rendered in favor of the Applicant,
unless the Applicant has agreed in writing to an extension of time.

4. A copy of the written decision shall be delivered to the
Applicant personally or mailed to him postmarked not later than the
business day next following the date of the decision. To all other persons
who have filed their names and addresses with the Board of Supervisors not
later than the date of the last public hearing, the Board shall provide, by
mail or otherwise, brief notice of the Decision and a statement indicating
where the full decision may be examined.

5. Nothing in this subsection shall prejudice the right of
any party opposing the application to urge that the decision of the Board
of Supervisors is erroneous."

Section 5. Severability.

In the event any provision section, sentence, clause or portion of
this Ordinance is held invalid or unconstitutional, such invalidity or
unconstitutionality shall not effect and/or impair any of the remaining
Ordinance. Each provision of this Ordinance is severable for this purpose.
It is the intent of the Board of Supervisors of the Township of
Maidencreek in the event of any such invalidity, that the remainder of the
Ordinance shall remain in full force and effect notwithstanding the fact
that such provision or portion thereof shall be invalid or
unconstitutional.

Section 6. Repealer.

All Ordinances or parts of Ordinances inconsistent with the provisions
of this Ordinance are hereby repealed insofar as, but only insofar as, the
same or inconsistent therewith and as amended by the provisions of this
Ordinance, the Township of Maidencreek Zoning Ordinance of 1993, as amended
is hereby ratified and confirmed.

Section 7. Effective Date.

This Ordinance shall take effect five (5) days after its passage.

IN WITNESS WHEREOF and intending to be legally bound, the Supervisors
ORDAIN and ENACT in lawful session duly assembled, this ______________ day
of ______________, 2008.

MAIDENCREEK TOWNSHIP
BOARD OF SUPERVISORS

BY: _____________________________
Claude Beaver, Chairman

_____________________________
Roy Timpe, Supervisor

_____________________________
Joseph E. Rudderow, III,
Supervisor

Attest:

_______________________
Diane Hollenbach, Secretary