Attending: Jim Schoellkopf, Jr., David Brown, Joel High, David Anspach,
Eugene Orlando, Jr. - Orlando Law Offices, Tom Unger and Karen Pollock -
Systems Design Engineering, Inc., and Diane Hollenbach - recording
secretary

Guests: Michael Hartman, Claude Beaver, Steve DeLucas, Gloria E. Kemmerer,
Greg Bogia, Seth Walizer, Scott Miller

Jim Schoellkopf called the Maidencreek Township Planning Commission regular
meeting to order at 7:33 p.m. in the Maidencreek Township Municipal
Building and asked everyone to rise for the Pledge to the Flag.

APPROVAL OF THE AGENDA
A motion was made by Joel High, seconded by David Brown, to approve the
agenda for the Maidencreek Township Planning Commission regular meeting as
presented. The Chairman asked for public comment on the motion. Hearing
none, all members voted, "Aye." Motion carried.

APPROVAL OF PRIOR MEETING MINUTES
A motion was made by Dave Anspach, seconded by Joel High, to waive the
reading of the April 1, 2009 regular meeting minutes and approve the
minutes as presented. The Chairman asked for public comment on the motion.
Hearing none, all members voted, "Aye." Motion carried.

ACCEPTANCE OF PLANS
A motion was made by David Brown, seconded by Dave Anspach, to accept the
Esbenshade Land Development Plan for review. The Chairman asked for public
comment on the motion. Hearing none, all members voted, "Aye." Motion
carried.

COMMUNICATIONS - None

PUBLIC COMMENT - None

ENGINEER'S AGENDA
Review Period Expiration Corrado Commercial Preliminary Plan expires May
14, 2009
A motion was made by David Brown, seconded by Dave Anspach, to recommend
the Board of Supervisors reject the Corrado Commercial Preliminary Plan for
failure to comply with the January 7, 2009 Systems Design Engineering, Inc.
review letter, which is incorporated by reference, unless a letter granting
an extension to the review period is received prior to the May 14, 2009
Board of Supervisor's meeting. The Chairman asked for public comment on
the motion. Hearing none, all members voted, "Aye." Motion carried.

Melrose Place C4 & C5 Revision to the Plan of Record Plan - The plan was
submitted in order to provide adequate parking for a restaurant/bar
proposed for building C5 in the Melrose Place Subdivision by annexing Lot
29 to the existing C5 lot and increasing the parking area. The developer
addressed most items from the last review letter. Berks County
Conservation District approval is outstanding. The Developer's Improvement
Agreement will need to be amended and a cost estimate for public
improvements should be submitted to the Township Engineer for review.

A motion was made by David Brown, seconded by Joel High, to recommend that
the Board of Supervisors approve the Melrose Place Lot C4 and C5 Revision
to a Plan of Record conditional upon compliance with the May 6, 2009
Systems Design Engineering review letter, Berks County Conservation
District approval, and submission of a combined legal description of Lot C5
and Lot 29 for recording with the plan to create a combined lot. The
Chairman asked for public comment on the motion. Hearing none, all members
voted, "Aye." Motion carried.

Village at Summit Crest Phase III Preliminary Plan (private water system) -
Tabled.

Esbenshade's Greenhouse Land Development Plan - Neither the developer nor
his representative was present to discuss the plan. Karen Pollock of SDE
briefed the Commission on the review generated for this project. The plan
is titled and was reviewed as a "preliminary plan" but a final plan
application has been received. The well is still shown on the plan and the
Maidencreek Township Authority has not changed their position that the
property is required to connect to the public water system. The Authority
has not received these plans for review and the developer should make a
formal application to the Authority. Waivers have been requested to
eliminate curb, sidewalk and street lights requirements. The Commission
took no action on the plan.

Praise Christian Fellowship Request for an Exemption to the Land
Development Process - Tom Unger of SDE stated that this plan is being
reviewed in anticipation of approval in June of the revisions to Section
411 of the Subdivision and Land Development Ordinance that sets criteria
for a plan to be considered exempt from the land development process.
Praise Christian Fellowship would like to convert a building in the
Excelsior Industrial Park into a House of Worship. Because this use is not
permitted in the Industrial Zoning District, they applied for and
subsequently were denied a request for a variance to the Township Zoning
Ordinance by the Maidencreek Township Zoning Hearing Board. The Zoning
Hearing Board decision was overturned in Berks County Court. The applicant
has now requested that the Township waive the land development process and
allow them to occupy the building. Mr. Unger asked the Commission if they
had any concerns regarding this project.

Dave Anspach stated that he has concerns about public safety. No parking
is allowed on June Avenue. It does not appear that the church would have
enough parking on their own lot for special events such as weddings. Mr.
Anspach also pointed out that the Industrial Park operates seven days a
week. A rough estimate of trips in and out of the Industrial Park for the
two largest businesses is: 400 tractor trailers per week for Can Corp, 400
tractor trailers per week for the Fresh Pack Building, 400-500 light trucks
a week between Giorgio facilities and 300-400 employees making at least two
trips a day. There are other businesses operating in the Industrial Park
as well and once James Hardie becomes operable again, there will be
significantly more traffic.

State Farm Insurance Request for an Exemption to the Land Development
Process - Seth Walizer of State Farm Insurance would like to convert an
existing house along Park Road into an insurance office. The house is in
the C-1 Commercial Zoning District and an office is a permitted use. Mr.
Walizer would be open five days a week and by appointment and have one
agent and two employees in the office. The home currently has on lot
sewer, a well and oil heat. A proposed sign location has been shown on the
plan and the driveway has a low volume highway occupancy permit from Penn
DOT. Mr. Unger stated that the applicant should provide additional
information as outlined on the SDE review letter. Simple statements could
be added onto the plan or put into a letter format to meet the requirements
of the plan exemption process.

David Brown asked if the lot or the building is in the floodplain. Mr.
Unger stated that the applicant must show the floodplain but since they are
not changing the building footprint this does not impact the change of use.
Mr. Brown stated that he feels an office is a better use for the property
as it is safer then having someone live there (close to the floodplain).

Village at Summit Crest - Private Water System Variance and Special
Exception -
The applicant is requesting the Zoning Hearing Board grant the following:
. A special exception to permit a mobile home park in the R4 Zoning
District;
. A variance to allow accessory structures to be placed closer than five
feet from the residential units;
. A variance to the side yard setback to permit semi-detached dwellings
in the mobile home park;
. A variance to allow the overflow parking in Phase II, which will be
moved to Phase III, since the three phases have been combined onto one
deed; and
. A variance to extend the special exception and variance expiration
time from six months to two years when failing to obtain a zoning
permit or failing to commence a substantial amount of work.

The Planning Commission, Solicitor and Engineer expressed the following
concerns:
. Since all three parcels are now combined onto one deed, the previous
plan for the Village at Summit Crest III with public water that is
still in the review process violates the facts of record and must be
withdrawn.
. The developer is creating his own hardship by proposing lots that are
not large enough to accommodate accessory structures that can not be
placed with the correct setbacks from residential units. In Phase II,
when the previous variance for accessory structure setbacks was
granted, the Plan was approved, recorded and constructed and then
residents decided that they would like to install sheds.
. The previous plan, Village at Summit Crest III - public water,
received a waiver to reduce the required 15 foot side yard setback to
10 feet. Granting a variance to allow the semi-detached units further
reduces the set back of one side yard for each unit to 0 feet and
increases density. Further, the Commission believed that the
developer had stated the semi-detached units would be connected at the
garage wall. This plan shows some units sharing a common wall in
living area.
. Since the three properties are now on one deed, granting a variance
would allow semi-detached units to be installed in Phases I and II
when homes are replaced, thus increasing the density by half.
. Phase I and Phase II are recorded plans. The Commission asks how
zoning relief could be granted to a recorded plan. Where is the
hardship, when the parking was approved and recorded on the Phase II
Plan? Also, the overflow parking that the applicant would like to
eliminate in Phase II is a good distance and down a hill from the new
proposed parking area in Phase III. There are no internal walkways
connecting these areas, thus raising safety concerns.
. The Commission knows more now than when the previous special exception
for the mobile home park was granted because the plan has been through
the review process. In addition to all of the above, the Commission
is concerned about :
o the amount of fill in this project and binding the developer to
the procedures the Township Engineer feels are necessary to
place and test the fill so safe structures and utilities can be
installed on the fill,
o the steep slope, roads and driveways, and
o storm water control.

A motion was made by Dave Anspach, seconded by David Brown, to recommend
the Board of Supervisors instruct the engineer to appear at the May 21,
2009 Zoning Hearing and address the Planning Commissions' concerns to the
Zoning Hearing Board and to recommend to the Zoning Hearing Board that they
grant the special exception and variances the Village at Summit Crest Phase
3 had received prior; no more and no less. The Commission agreed to
granting the new request to extend the time period from six months to two
years before a Special Exception becomes invalid if a project is not
started. The Chairman asked for public comment on the motion. Hearing
none, all members voted, "Aye." Motion carried.

SOLICITOR'S COMMENTS - None

OLD BUSINESS
Custom Milling and Consulting Variance - Mrs. Hollenbach informed the
Commission that the Custom Milling Variance had been granted by the Zoning
Hearing Board to reduce the parking spaces required by 6 spaces.

Revisions to the Zoning Ordinance for Assisted Living and Congregate Care -
There is still concern that the density proposed is too excessive for the
lot size. Mr. Orlando proposed that a scale be set to allow so many square
feet of building size for so many square feet of lot size. This will
accommodate the smaller lots in the Commercial Residential Zoning District
and the larger lots in the Local Commercial Zoning District.

NEW BUSINESS
Wind Regulations and Outdoor Furnace Regulations - The Engineer distributed
draft regulations for residential and commercial wind mills and outdoor
furnaces for the Commission to review.

Having no other business, a motion was made by Joel High, seconded by David
Brown, to adjourn the May 6, 2009 Planning Commission meeting. The
Chairman asked for public comment on the motion. Hearing none, all members
voted, "Aye." Motion carried. Meeting adjourned at 10:00 p.m.

Respectfully Submitted,

Diane E. Hollenbach, secretary

CC: Board of Supervisors Tom Unger, SDE Barbara Hassler
Planning Commission Eugene Orlando, Solicitor Chief Scott Eaken