Planning Commission

Minutes — December 2, 2009

Date
December 2, 2009
Type
Minutes
Year
2009
File
PDF · 184 KB

Download original Open in browser

Document text

Machine-extracted from the original — formatting is approximate and there may be recognition errors. Always check the original file above before relying on it. 546 words

Maidencreek Township Planning Commission
Wednesday, December 2, 2009

Attending: Jim Schoellkopf, Jr., Joel High, Tom Unger– Systems Design Engineering, Inc., Diane
Hollenbach – recording secretary

Guests: Gene Walters, Jason Nix, Michael Hartman

Jim Schoellkopf called the Maidencreek Township Planning Commission regular meeting to order
at 7:45 p.m. in the Maidencreek Township Municipal Building and asked everyone to rise for the
Pledge to the Flag. Since there was not a quorum of Planning Commission members, no official
action could be taken.

ENGINEER'S AGENDA
PLAN REVIEWS
Villa at Maidencreek Land Development Plan – Tom Unger of Systems Design Engineering
distributed the December 2, 2009 review letter of the Villa at Maidencreek Land Development
Plan. The project is a 124 unit assisted living facility located at the intersection of Park Road and
Hoch Road on a 5.1 acre lot. Michael Hartman of McCarthy Engineering representing the Villa at
Maidencreek submitted a waiver request to Section 305 of the Storm Water Management
Ordinance to not require the site to meet the ground water recharge requirement because the site
is unsuitable for infiltration due to the underlying Karst geology. Mr. Hartman will also be asking
for waivers to the Subdivision Ordinance to the requirement to build curb and sidewalk along
Park Road. The Planning Commission members present were in agreement with this and felt it
would be dangerous for pedestrians to walk along Park Road at this time. The Commissioners
requested a note be placed on the plan to allow the Township to request the installation of
sidewalks if the Supervisors deemed it necessary in the future. The developer is in discussions
with Larken Associates to get an easement to connect the Villa at Maidencreek property with the
Shopping Center property by installing a walkway.

Mr. Hartman explained that bids are being received to perform a traffic impact study and will put
the traffic engineer, when chosen, in touch with Systems Design Engineering (SDE) to discuss the
scope of the study. Mr. Hartman felt that the storm water comments and lighting comments could
be addressed and he will be contacting SDE to discuss inlet filters and the Township solicitor to
discuss the Trust Agreement.

Mr. Unger felt that the biggest challenge for the project would be the landscaping along the
northern property line at the existing storm water easement and the proposed ten foot high
retaining wall. Diane Hollenbach asked the applicant to contact the Maidencreek Township
Authority for their plan review application if they had not already received one.

NEW BUSINESS
Village at Summit Crest Phase III (Private Water) – Mr. Unger informed the Commission that a
Planning Module Exemption Form had been submitted for the Supervisor’s approval. This is for
the private water system’s discharge of backwash. Also, both versions of the Summit Crest Plans’
review period expire in December.

Page 1

Maidencreek Township Planning Commission
Wednesday, December 2, 2009

Joint Comprehensive Plan with Fleetwood Borough and Richmond Township – Jim Schoellkopf
stated he would be interested in representing Maidencreek Township on the Joint Planning Board.

Meeting adjourned at 8:03 p.m.

Respectfully Submitted,

Diane E. Hollenbach, secretary Tom Unger, SDE Barbara Hassler

CC: Board of Supervisors Eugene Orlando, Solicitor Chief Scott Eaken
Planning Commission
Park & Recreation Patrick Donovan Dan Miller
Authority
Zoning Hearing Board & Alt.

Page 2

Archived from the Maidencreek Township website. Reproduced unaltered; not an official records repository.