Maidencreek Township Planning Commission
Wednesday, April 7, 2010

Attending: Jim Schoellkopf Jr., Joel High, David Anspach, Jeff Futchko, Matt Davenport, Eugene
Orlando, Jr. – Orlando Law Office, Tom Unger– Systems Design Engineering, Inc., Diane Hollenbach
– recording secretary

Guests: Jason Nix, Michael Hartman, Gary Katz, Sherri Katz, Angelo Corrado, Jeff Warmkessel, Eric
Mountz, Matt Bressler, David Weiss, Nick Feola, Eugene Martin

Jim Schoellkopf called the Maidencreek Township Planning Commission regular meeting to order
at 7:30 p.m. in the Maidencreek Township Municipal Building and asked everyone to rise for the
Pledge to the Flag.

APPROVAL OF THE AGENDA
A motion was made by David Anspach, seconded by Jeff Futchko, to approve the agenda for the
Maidencreek Township Planning Commission regular meeting. The Chairman asked for public
comment on the motion. Hearing none, all members voted, “Aye.” Motion carried.

APPROVAL OF PRIOR MEETING MINUTES
A motion was made by David Anspach, seconded by Matt Davenport, to waive the reading of the
March 3, 2010 regular meeting minutes and approve the minutes as presented. The Chairman
asked for public comment on the motion. Hearing none, all members voted, “Aye.” Motion
carried.

A motion was made by Matt Davenport, seconded by Joel High, to waive the reading of the March
31, 2010 special meeting minutes and approve the minutes as presented. The Chairman asked for
public comment on the motion. Hearing none, all members voted, “Aye.” Motion carried.

ACCEPTANCE OF PLANS
A motion was made by Matt Davenport, seconded by David Anspach, to accept the Villa at
Maidencreek Land Development Plan for review. The Chairman asked for public comment on the
motion. Hearing none, all members voted, “Aye.” Motion carried.

A motion was made by Joel High, seconded by Jeff Futchko, to accept the Moyer Subdivision 2 Final
Plan for review. The Chairman asked for public comment on the motion. Hearing none, all
members voted, “Aye.” Motion carried.

COMMUNICATIONS – None.

PUBLIC COMMENT – None.

ENGINEER'S AGENDA
SUBDIVISION STATUS CHECKLIST
The Engineer noted that the Corrado Commercial Plan expires in May and will need a time
extension.

1

Maidencreek Township Planning Commission
Wednesday, April 7, 2010

PLAN REVIEWS
Villa at Maidencreek Land Development Plan – Tom Unger distributed the April 7, 2010 Systems
Design Engineering, Inc. review letter for the plan. Changes have been made to the storm water
design and grading for the plan. The developer agreed to withdraw the previous plan that
received preliminary plan approval. There are no outstanding zoning issues. The plan needs
Authority approval. An improvements agreement and financial security will be required. The
retaining wall drawings are still being reviewed by the Township Engineer. Stan Stubbe made one
comment on site lighting, asking that a backlight shield be added. There were several storm water
comments since the storm water system was changed. The change was made so that less fill
would need to be brought to the site, thus saving money. A traffic impact analysis was done and
will be reviewed by the Supervisors. No action was taken on the plan.

The Crossing at Maidencreek Subdivision and Land Development Plan- Tom Unger distributed the
April 7, 2010 Systems Design Engineering, Inc. review letter for the plan. The plan currently has
conditional final plan approval; however, due to economic conditions, the developer has decided
to phase the project. The Township will require recording of the entire plan and posting of
financial security to cover the improvement construction in all three phases. There were no
zoning issues. An improvement agreement, storm water operation and maintenance agreement,
payment of fee – in- lieu of open space and posting of financial security is outstanding. The
manager asked Mr. Corrado to supply a draft copy of the Letter of Credit for the Township
Solicitor’s review.

A motion was made by Matt Davenport, seconded by Joel High, upon the recommendation of the
engineer, to recommend that the Board of Supervisors grant approval to the Crossings at
Maidencreek Final Subdivision and Land Development Plan conditional upon satisfactory
completion of the items in the April 7, 2010 System Design Engineering, Inc. review letter, which is
incorporated by reference, entering into an Improvements Agreement and posting financial
security in a form satisfactory to the Township. Jim Schoellkopf, Joel High, Matt Davenport and
David Anspach voted, “Aye.” Motion carried. Jeff Futchko abstained from voting.

Alternative Fuel Manufacturing Facility Preliminary Land Development Plan - Tom Unger
distributed the April 2, 2010 Systems Design Engineering, Inc. review letter for the plan. Nick
Feola, Jeff Warmkessel, Eric Mountz, Matt Bressler, David Weiss and Gene Martin were in
attendance representing the plan. The proposal is for an alternate fuel manufacturing facility on
Lot 3 of an Industrial zoned parcel along Maidencreek Road. The facility will take municipal solid
waste and turn it into an alternate fuel.

The Township Engineer offered the following comments:
There are 36 trailers and a building used to store tires on the site. The Township is
unaware of these uses on the site. Permits have not been issued. The property owner
should address this with the Township.
After review of the plan and the Zoning Ordinance, the Zoning Officer has determined that
the use is processing of municipal solid waste, which is not a permitted use by right and a
Special Exception is required. If the applicant feels otherwise, they should submit in

2

Maidencreek Township Planning Commission
Wednesday, April 7, 2010

detailed written form their arguments to convince the Zoning Officer that the municipal
waste is feedstock and the process is manufacturing.
The parking layout must be revised so that all buildings that are on the lot have the
designated amount of parking required by the Zoning Ordinance. If buildings will be vacant
and there is no intent for occupation, will the applicant stipulate no use and occupancy on
the plan or demolish the vacant buildings?
The plan must be compatible with the performance standards of section 220-62.
All buildings must be served by an adequate sanitary sewer system and well. A Public
Water Supply permit is required for more than 25 employees.
The site is located within a Pennsylvania Natural Diversity Inventory site, Lake Ontelaunee
at Peters Creek. A PNDI search was conducted by the applicant with results of no known
impacts with respect to PA Game Commission, PA Department of Conservation and Natural
Resources, PA Fish and Boat Commission, and US Fish and Wildlife Service.
Several Permit will be required – Air Quality from PA DEP, Solid Municipal Waste General
Permit from PA DEP, NPDES from PA DEP, Erosion and Sediment Control from the Berks
County Conservation District, Driveway Highway Occupancy Permit from Penn DOT, Non-
Community No-Transient Public Water Supply from the PA DEP.
If the applicant’s Solid Waste General Permit is for processing 750 tons of municipal waste
per day, then all calculations should have used this maximum number.
The Township will require the applicant to submit their contract with a landfill to accept
those items that are not able to be used in the process.
What will happen with the waste trucks coming in if machinery breaks down?
Traffic Impact issues will be reviewed separately. The Commission was very concerned
about the additional traffic and how it will affect the residents.

The applicant and their consultants offered the following comments:
This is a site redevelopment project. The applicant has been working on this process with
the PA DEP for ten years. There are no other facilities like it in the United States.
Everything will be contained within the building. The building will be kept under negative
pressure so there will be no smell. There will be air quality control measures.
The facility will process 500 tons of municipal waste per day and produce 350 tons of
alternate fuel per day. The applicant would be willing to stipulate that they will process an
average of 500 tons per day. The applicant will use a combination of individual and major
waste haulers. A tipping fee will be charged to the haulers for disposal of the waste.
There will be 15 laborers on each shift. There will be two ten hour shifts.
There will be a leachate tank under the building which will be regulated under the Solid
Waste Permit. None of the leachate will evaporate off. It will all be collected prior to the
process beginning.
Waste will be dumped in the building on the tipping floor. There would be approximately
46 trucks per day bringing in waste and about 13 trucks per day to take away the finished
product. The area of collection will be local.
The waste will be manually and mechanically separated to remove ferrous and non ferrous
metals, ash and glass. The mechanical separation unit will be a fiber optic sorting system.

3

Maidencreek Township Planning Commission
Wednesday, April 7, 2010

Excavators will pick out the obvious things that can’t be used such as engine blocks. The
remaining waste will go into a grinder which will cut the waste into fourteen inches square
and smaller pieces. From here larger metal pieces will be picked out by hand. The waste
will move through the fiber optic system and then into another grinder to be reduced in
size to two inches and smaller. The waste finally goes into a dehydrating vortex which is
powered by compressed air and heat. It is heated to 600 degrees. The pressure and
vacuum rings turn the waste into a fluff which is the alternate fuel. It may be left in this
form or pelletized. Customers for the finished product include coal fired generation plants,
or plants like Corstacks in Reading.
The air will carry the moisture off. The twenty five foot stack will be heated to 250 degrees.
The air will go through a bag house and a thermal oxidizer where it will be heated to 2000
degrees for two seconds to destroy any volatile chemicals. An Air Quality Permit is needed.
All equipment comes with a performance guarantee from its manufacturer. If equipment
breaks down, the waste trucks will be instructed to go to a landfill until the facility is
running again.
The only noise from the site will be the fans and slow speed grinder.
The thermal oxidizer will not be in the building.
Electricity will be used to generate heat. The process consumes 2.5 to 3 megawatts of
electricity to produce a fuel that generates 12 to 14 megawatts of electricity.

SOLICITOR’S COMMENTS – None

OLD BUSINESS
Revisions to the Zoning Ordinance – The Commission authorized the Secretary to advertise a
special meeting to discuss the revisions to the Zoning Ordinance on Wednesday, April 28, 2010
beginning at 7 PM.

NEW BUSINESS
Each Planning Commission member has received a copy of the Codification of Ordinances.

Wind Energy Draft Ordinance – Tabled.

Having no other business, a motion was made by David Anspach, seconded by Joel High, to
adjourn the regular April meeting. The Chairman asked for public comment on the motion.
Hearing none, all members voted, “Aye.” Motion carried. Meeting adjourned at 9:23 p.m.

Respectfully Submitted,

Diane E. Hollenbach, secretary

CC: Board of Supervisors Tom Unger, SDE Barbara Hassler
Planning Commission
Park & Recreation Eugene Orlando, Solicitor Chief Scott Eaken
Authority
Patrick Donovan Dan Miller

Zoning Hearing Board & Alt.