Maidencreek Township Authority
November 13, 2014

Present: Earl Rothermel, Karl Bolognese, Daniel Novakovich, Marie Coraluzzi, James
Nothwehr, Patrick Donovan – General Manager, Gregory Unger – Systems Design Engineering
Inc., Daniel Becker – Kozloff Stoudt and Meagan Dompkowski – recording secretary

Guests: Kevin Manmiller, Diane Hollenbach, Steve Moyer

Earl Rothermel called the November 13, 2014 meeting of the Maidencreek Township Authority
to order at 11:00 a.m. in the Maidencreek Township Municipal Building and asked everyone to
rise for the Pledge of Allegiance to the Flag.

PUBLIC COMMENT
Kevin Manmiller – Giorgio Foods

Kevin Manmiller of Giorgio Foods came to ask the Authority Board to sign the drawings
of the recombined property where St. Matthew’s had planned to build a church. The St.
Matthew’s plan fell through and Giorgio wants to recombine the subdivided properties and
record the land development plans. The Solicitor did not see the need for the Board to sign
because it had no impact on the Authority currently, but feels that Greg Unger should review the
plans first. Mr. Unger feels there should be a note on the plans that say it is a non-building lot,
but will review the drawings to make sure there is nothing for the Authority to worry about
before the Board signs or not.

A motion was made by Karl Bolognese to approve the drawings contingent upon Greg’s
review. The motion was seconded by Dan Novakovich and hearing no questions on the motion,
it passed unanimously.

PLAN REVIEW STATUS
Esbenshade’s Greenhouses – Patrick Donovan reported that the backflow prevention device is
installed and SDE needs to inspect it. Greg Unger will be scheduling the inspection of the
backflow prevention device soon.

Village at Summit Crest Phase 2 – Nothing to report. Waiting for invoices.

APPROVAL OF THE MINUTES
A motion was made by Karl Bolognese to waive the reading of the minutes and approve

the October 9, 2014 regular meeting minutes as presented. The motion was seconded by Dan
Novakovich and hearing no questions on the motion, it passed unanimously.

NEW BUSINESS
MXU Proposal and Meter Installs
Patrick Donovan reported that he had talked to LB Water and there are still 1,500 meters to be
installed. LB Water would not give a break on price if the Authority were to buy all 1,500 at
once, so Mr. Donovan has advised that we continue to buy the 500 meters at a time. Mr.
Donovan also advised the board to consider the vehicle gateway technology over the antenna
technology. The antenna technology would not be a cost effective investment. Mr. Donovan

2

suggested dedicating the new Authority vehicle to the gateway technology if the board decided
to consider the gateway investment.

A motion was made by Karl Bolognese to move on the recommendations of the General
Manager to purchase 500 MXUs at a cost of $135 each, and the vehicle gateway technology at a
cost of $26,100. The motion was seconded by Marie Coraluzzi and hearing no questions on the
motion, it passed unanimously.

Electrical Evaluation Report
The Authority is up for a policy renewal and the insurance company requested a review of the
electrical systems at all sites due to sustaining more damage from electrical surges than the
insurance company would like. Greg Unger advised that they are looking to upgrade the transient
voltage surge protectors at each of the sites. Mr. Unger mentioned that the clamp down voltage
on the current protectors did not protect the sites and gave individual recommendations for each
site. Mr. Unger recommended replacing the existing surge protector devices with Current
Technology Select SL3 unit, 300kA per mode which is the top of the line technology.

A motion was made by Dan Novakovich to approve upon the recommendations of the
engineer the electric system upgrade at a cost of $75,300. The motion was seconded by James
Nothwehr and hearing no questions on the motion, it passed unanimously.

Mt Airy Escrow
A motion was made by Karl Bolognese to approve the release of the Mt. Airy escrow.

The motion was seconded by Dan Novakovich and hearing no questions on the motion, it passed
unanimously.

Special Meetings for 2015 Budget
Patrick Donovan will contact the board by e-mail to schedule a special budget meeting.

Christmas Party Invite List
The Christmas party will be December 18, 2014 at noon. The invite list will consist of the
employees and Boards of the Authority and the Township.

UNFINISHED BUSINESS
Curb Box and Service Agreement Procedure - Tabled

EJB Payment – The Solicitor talked to the insurance agent regarding the Genesis Drive water
main break and the Authority does not have the insurance coverage for this type of situation. The
Solicitor recommended the payment, but under the condition that the Authority admit no
liability.

A motion was made by Dan Novakovich to pay EJB Paving without admitting any
liability in spirit of governmental cooperation. The motion was seconded by Karl Bolognese and
hearing no questions on the motion is passed unanimously.

Condition of Grounds at Well #6 – Patrick Donovan informed the Board that he has safety
concerns about the grounds at Well #6. The grounds in some areas are not level which does not
allow for them to be mowed safely. Mr. Donovan recommends the bank be grated down slightly,
the pile of dirt and debris to be removed, the area around the barn needs to be leveled, the trees

3

and concrete need to be removed, and the ground cellar near the house needs to be more secure.
Mr. Donovan would like to contract this work out, but would go through all the necessary
processes before doing so.

A motion was made by James Nothwehr to follow Patrick’s recommendations with the
caveat to add the building to the list depending on what the Township says. The motion was
seconded by Karl Bolognese and hearing no questions on the motion, it was passed unanimously.

LEAK REDUCTION REQUESTS
Met Management – No action. The Solicitor is waiting to hear back from Met Management.

Berks Transfer
A motion was made by Marie Coraluzzi to give a 75% credit for the last two quarters per

the General Manager recommendation and they would not use their one time reduction request.
The motion was seconded by James Nothwehr and hearing no questions on the motion, it passed
unanimously.

Tauseef Khan 101 Cedrick Ave
A motion was made by Karl Bolognese to approve the one time leak reduction request for

Tauseef Khan. The motion was seconded by James Nothwehr and hearing no questions on the
motion, it passed unanimously.

SOLICITOR’S REPORT
Mr. Becker revised the Vehicle Use Policy and handed out a red lined copy of the policy

for the board to review and approve for next meeting.

ENGINEER’S REPORT
Mr. Unger reported that DEP approved the predrilling plan for Well #6 and will be

bringing estimated costs to the next meeting. Mr. Unger’s assistant, Steve Moyer, gave a brief
demonstration of how the GIS project is proceeding. He gave an inside look of how some of the
different tools worked and what to expect in the upcoming future.

A centrifuge test was run in Hamburg and the Authority shared in with some of the costs
since this is the type of equipment and technology the Authority is interested in. The centrifuge
was producing 85-100 gallons per minute which resulted in 20% cake and it was quiet. Systems
Design Engineering is also looking at the Deer Lake project right now.

AUTHORITY REPORT
Patrick Donovan had nothing to add to his written report.

TREASURER’S REPORT & PAYMENT OF BILLS
Dan Novakovich reported that he reviewed the P & L with the General Manager and

everything appeared to be in order.

A motion was made by Karl Bolognese to authorize the following payments:
Routine/Regular July Bill List - $30,294.81, Construction in Progress - $12,949.40,
Reimbursable Expenses Paid by Developer - $6,537.49, Payroll Transfer from Operator Acct -

4

$26,400.61, Validate Checks Signed Between Meetings - $2,697.22, Special Checks Requiring
Special Handling - $87,139.40, Additional Checks after Board Book Delivery - $14,897.94.
James Nothwehr seconded the motion and hearing no questions on the motion, it passed
unanimously.

CORRESPONDENCE – None

The Board went into executive session from 12:49 p.m. to 1:21 p.m. to discuss personnel.

Having no further business, a motion was made to adjourn the meeting at 1:22 p.m.

Respectfully Submitted,

Meagan Dompkowski

Meagan Dompkowski
Recording Secretary

Minutes are subject to change prior to approval of the Maidencreek Township Authority.

cc: Maidencreek Township Authority Board Maidencreek Township Board of Supervisors

Patrick Donovan, Maidencreek Township Authority General Manager Maidencreek Township Planning Commission

Greg Unger, Systems Design Engineering, Inc., MTA Engineer Eugene Orlando, Esq., Orlando Law Firm, Solicitor

Daniel Becker, Kozloff Stoudt, MTA Solicitor Diane Hollenbach, Maidencreek Township Manager

JoAnn Schaeffer, Maidencreek Township Authority Secretary Ontelaunee Township