MAIDENCREEKTWP.PLANNINGCOMMISSION
P.O.BOX319,BLANDON,PA 19510
March 5, 2015
John Hoffert Surveying
32 E Lancaster Avenue
Shillington, PA 19607
Dear Mr. Hoffert,
At their March 4, 2015 meeting, the Maidencreek Township Planning Commission
recommended that the Maidencreek Township Board of Supervisors grant final plan
approval to the Brandywine Transportation Land Development Plan conditional upon
completion of the items in the Great Valley Consultants March 3, 2015 review letter, which
is incorporated by reference, approval by the Maidencreek Township Authority and
completion of any required agreements.
Sincerely,
Pam dllelch
Diane Hollenbach
Manager
Maidencreek Township
cc:
File
Maidencreek Township Board of Supervisors
Maidencreek Township Authority

PHONE:(610)375-8822
GREATVALLEY CONSULTANTS
1-800-733-4821
FAX:(610) 375-8977
75COMMERCEDR/VEWYOMISSING,PA19610-3323
March 3,2015
Maidencreek Township
Planning Commission
P.O.Box 319
Blandon,PA19510
Attention:
Diane Hollenbach, Township Manager
Re!
Brandywine Transportation
Final Plan Review
GVC File4026-001
Dear Planning Commissioners:
We received for review a Final Plan titled“Brandywine Transportation," submitted by John
Hoffert Surveying. The plan proposes the development of property located along West Wesner
Road and adjacent to railroad tracks which are roughly parallel to Park Road. The property will
be used as a maintenance facility for school buses and other associated uses.
Please note comments in bold typeface require action by or consideration of the Planning
Commission and Board of Supervisors. The remaining comments should be addressed by the
Applicant or his consultant, directly with Township staff or our office.The plan was reviewed
for conformity with Township Ordinances and Standards, as well as accepted engineering
practice. We offer the following comments for your consideration:
SUBMISSION INFORMATION
1.
Final Plan titled “Brandywine Transportation,prepared by Applied Surveying
Technologies, Inc., consisting of ten plan sheets as listed:
Date
Plan No.
Sht. No.
Description
Originated
Revised
2/17/15
1of10
8/11/14
5410-11-56-9323-D-001
Title Sheet
2 of 10
8/11/14
2/17/15
5410-11-56-9323-D-002
Overall Boundary
3of10
8/11/14
2/17/15
5410-11-56-9323-D-003
Rights-of-Way/Easements
8/11/14
4of 10
2/17/15
5410-11-56-9323-D-004
Land Development Plan(East)
5of10
8/11/14
2/17/15
5410-11-56-9323-D-005
LandDevelopmentPlan (West)
6of10
8/11/14
2/17/15
5410-11-56-9323-D-006
Profile and Details
7of10
8/11/14
2/17/15
5410-11-56-9323-D-007
ExistingFeaturesPlan(East)
8of10
8/11/14
2/17/15
5410-11-56-9323-D-008
ExistingFeaturesPlan (West)
9of10
1/21/15
5410-11-56-9323-D-009
2/17/15
TemporaryAccessDetailPlan
10of10
2/17/15
5410-11-56-9323-D-010
Sanitary Sewer Details
2.
Erosion and Sediment Pollution Control Plans prepared by John Hoffert Surveying
consisting of seven plan sheets as listed:
EngineersArchitectsPlannersConsultantsSurveyors
printed onrecyoled paper

GREATVALLEY CONSULTANTS
Maidencreek Township
March 3, 2015
Planning Commission
Plan No.
Originated
Description
D-15-01-ES1
1/21/15
Erosion and Sediment Pollution Control Plan
1/21/15
D-15-01-ES2
Erosion and Sediment Pollution Control Plan
1/21/15
D-15-01-ES3
PCSMPlan
1/21/15
D-15-01-ES4
PCSM Plan
1/21/15
D-15-01-ES5
ESPCNotes/Details
1/21/15
D-15-01-ES6
ESPC Details
1/21/15
D-15-01-ES7
Erosion and Sediment Pollution Control Plan
3.
Lighting Plans prepared by Visual consisting of two plan sheets as listed:
Date
Sheet No.
Description
Originated
Revised
1of8
1/28/15
PhotometricPlan
1of 1
Lighting Details
4.
Application for review of a Final Plan dated February 17, 2015.
5.
John Hoffert Surveying Transmittal letter.dated January 21, 2015.
John Hoffert Surveying letter dated January 21, 2015 addressing previous review
comments.
7.
Email chain relating to DEP Sewage Planning Modules.
8.
Draft of Storm Water Management, Storm Water Controls and BEsT Management
Practices Operations and Maintenance Agreement.
9.
Environmental Impact Assessment dated December, 2014.
LIGHTING PLANS
1.
The Photometric Lighting Plan indicates that the fixtures will have a light cutoff so that
the footcandle levels at the property line are less than 0.1 footcandles.
2.
The proposed light fixtures are high cutoff fixtures.
3.
The proposed lighting plan is acceptable per Section 220-62.F(1) of the Township's
Zoning Ordinance.
PREVIOUS OUTSTANDING REVIEW COMMENTS
This review will address only those items that were outstanding in the most recent review
completed by Great Valley Consultants (GVC) dated January 29, 2015.

GREATVALLEY CONSULTANTS
Maidencreek Township
March 3, 2015
Planning Commission
The following comments are offered for your consideration:
1.
A Water Resources Study required by Section 190-16.I. of the SALDO was submitted for
MTA consideration.
2.
A separate plan was included in this submission titled Temporary Access Detail Plan to
address the construction of the temporary access within the easement. Legal issues
regarding this temporary access are being addressed by the developer's attorney. The
completion of certain regrading by adjacent property owner John Farina was discussed.
Such regrading would be necessary for the feasibility of the project. A legal document
indicating Mr. Farina's willingness to complete this work should be submitted to the
Township Solicitor for his review and recommendation.
3.
Sewer Extension plans were submitted directly to MTA for approval. Email
correspondence was provided to indicate that DEP is not requiring sewage planning
modules for this project.
4.
Erosion and Sediment Pollution Control Plans were included in this submission. Review
and approval of these plans by the Berks County Conservation District is required
according to Section 190-41 of the SALDO.
A draft of the Stormwater Management Operations and Maintenance Agreements was
previously submitted as required by Section 182-32 of the Stormwater Management
Ordinance.
6.
Approval of the Final Plans by the Maidencreek Township Authority should be provided.
7.
Additional comments may result from any revisions to the plans currently under review.
Please do not hesitate to call our office with any questions regarding the above review.
Sincerely,
CHARLES M. JONES, PE, PLS
Project Manager
CMJ:lam
cc:
Maidencreek Township Board of Supervisors
Maidencreek Township Authority
Eugene Orlando, Esq.
William E. Gross, Wesner Land Associates, LLC
Karen M. Krater, John Hoffert Surveyor

Archived from the Maidencreek Township website. Reproduced unaltered; not an official records repository.