Maidencreek Township Board of Supervisor Meeting
August 11, 2016

Present: Claude Beaver, David Franke (arrived 8:15 p.m.), Joseph Rudderow III, Christopher
Garrell – Orlando Law Offices, Ed Kopicki – Systems Design Engineering, Inc., Diane
Hollenbach – Township Manager

Guests: Cody Rhoads, Vicki Solberg, Jean Odenweiler, Linda Epler, Karen Chandler, Jerry
Clay, Dennis and Robin Fink, Daniel Miller

MINUTES & FINANCES
Approval of the Meeting Minutes

A motion was made by Claude Beaver to waive the reading of the minutes and approve
the minutes for the July 14, 2016 regular meeting. Joseph Rudderow III seconded the motion and
hearing no questions on the motion, it passed unanimously.

Treasurer’s Report and Bill List
A motion was made by Claude Beaver to approve the July 2016 Treasurer’s Report and

Bill List. Joseph Rudderow III seconded the motion and hearing no questions on the motion, it
passed unanimously.

PUBLIC COMMENT
Vicki Solberg of 317 Sofia Blvd. updated the Board on progress to rectify her grading issue and
informed the Board she had the Berks County Conservation on her property to take soil samples.

Jerry Clay owner of 531 Main St, Blandon inquired about replacing a garage on the property.
The Board directed him to contact the office during business hours.

Linda Epler of 628 Guldin Road, Blandon asked the Board when something would be done about
speeding on Guldin Road. She stated that she has called the police and the electronic speed sign
did nothing. She stated that the Township trucks, tractor trailers, panel trucks all speed on the
road. The Board encouraged her to continue to call the police department and asked the manager
to talk to the road crew.

Dennis Fink of 325 W Walnut Tree Drive, Blandon asked if the Board had made a decision on
the manhole in his yard. Mr. Fink was opposed to installation of a manhole. He felt there was
no problem inside the pipe only outside the pipe. Mr. Rudderow responded that a manhole
would make it easier to televise and clean the pipe in the future but if Mr. Fink did not want one
installed, the Board would remove it from the project. Without the manhole, if the pipe fails
again, there is a risk that the Finks’ yard will need to be dug up. No bids were received. The
project was tabled.

REPORTS
ENGINEER’S REPORT
W Walnut Tree Drive Storm Water – Ed Kopicki reported that no bids were received and it is
recommended to rebid the project in January.

1

Maidencreek Township Board of Supervisor Meeting
August 11, 2016

2016 Road Work – The contracts have been signed. The preconstruction meeting was held July
21st. Lee Spring Road was completed August 3rd and Evansville Road will be under construction
the week of August 15th.

W Shore Drive Bridge – The bridge inspection was completed by a Penn DOT consultant.
There will be a meeting with the inspector August 23rd.

MUNICIPAL SOLICITOR REPORT
Verizon Lease - Christopher Garrell reported that the Verizon Cell Tower lease and
memorandum had been verified and were okay for signature.

Penn DOT Round About Agreement – Attorney Orlando has concerns about the agreement.
The Board tabled the agreement. Penn DOT was looking for something by the end of the year.

MANAGERS REPORT
Orchard Road Railroad Crossing – Mrs. Hollenbach informed the Board that the rail line
going to Lehigh Cement was seeing increased use. Because the crossing on Orchard Road has
no gate, the road crew installed stop signs to make the public aware of the crossing. Regulations
state that the Township may install a yield sign or a stop sign at these crossings. A stop sign is
enforceable only with a traffic study. The stop signs were on hand and Mrs. Hollenbach felt that
in the interest of public safety, she did what was expedient. The Board asked that yield signs be
ordered and installed.

Maidencreek Township Authority – The Authority is proposing a three percent rate increase
each year for five years. Mrs. Hollenbach distributed a newsletter article that will go out by the
end of August detailing the need for the increase. The Route 222 utility line relocation and loss
of tapping fees due to dwindling development are the two main contributors to the increase.

Park & Recreation – Ed Kopicki of Systems Design Engineering showed the Board the plan to
pave the gravel parking area near Park Road in the Community Park and move and repair
walking trails. Park and Recreation Board recommends this work to help with the parking issues
and to get the walking trail off of private property. Claude Beaver asked Mr. Kopicki to look at
expanding the lot further and adding spaces along the lot entrance and along the driveway. Mr.
Kopicki stated he could bid the project with two options. Dan Miller reviewed the plan in
relationship to the proposed veteran’s memorial.

A motion was made by Claude Beaver to authorize the engineer to prepare and bid the paving of
the upper parking lot and repair of the walking trails in the Community Park. Joseph Rudderow
III seconded the motion and hearing no questions on the motion, it passed unanimously.

Emergency Services – Joseph Rudderow commended the Fire Company and thanked the
volunteers, twenty of whom put in a combined total of 160 training hours in the month of July.

2

Maidencreek Township Board of Supervisor Meeting
August 11, 2016

OLD BUSINESS
Technical Deficiency Letter 384 Evansville Road – Mrs. Hollenbach reported that Mr.
Farvardin will drop off the items needed for his planning module requested by the Pennsylvania
Department of Environmental Protection in the technical deficiency letter. These items will be
forwarded to the PA DEP office as required.

LED Streetlight Replacement Bulbs – Mrs. Hollenbach went over the cost of replacing
existing streetlights with LED bulbs, the proposed Met Ed increase of 46% for regular
transmission rates and 94% for LED transmission rates and the projected cost of street lighting in
2017 if the Met Ed rates are approved by the Public Utility Commission. The Board asked the
engineer to look at the streetlights and determine if there can be fewer lights and still meet the
Township lighting standards.

NEW BUSINESS
410 Harvest Drive Tax Refund
A motion was made by Claude Beaver to authorize a refund of $32.93 to Nancy Peters due to an
error in her property assessment. Joseph Rudderow III seconded the motion and hearing no
questions on the motion, it passed unanimously.

926M Loader – The purchase of a loader with a mower attachment was tabled. The Board
agreed that a road mower should be rented to cut the roadside vegetation this year.

Route 222 Roundabout Agreement – The Board tabled discussion on the roundabout
agreement. Mrs. Hollenbach stated that the Maidencreek Township Authority will have
manholes and valve boxes in the center of the island and this needs to be considered in the
Board’s discussions. Mr. Rudderow explained to the audience that the Township is being asked
by Penn DOT to take responsibility for signs, pavement markings, sidewalks, lighting and the
center circle. Jean Odenweiler of 8833 Allentown Pike commented that she has been told her
home is being taken for the road improvements. Mrs. Hollenbach replied that Mrs. Odenweiler’s
property is not in the current project scope.

Zoning Ordinance Revision – Ed Kopicki of Systems Design Engineering, Inc. stated that the
Maidencreek Township Planning Commission had reviewed the comment letter received from
the Berks County Planning Commission (BCPC). Clerical errors were corrected. The BCPC is
recommending that a larger setback be implemented in the Industrial Zoning District where the
district abuts a residential zoning district. The Planning Commission is suggesting a setback of
100 feet instead of the existing 20 feet. The Board of Supervisors was in agreement and
Supervisor Rudderow asked if the Township could still ask for screening or a berm. Mr. Kopicki
indicated that they could. Mr. Kopicki handed out additional regulations on wind energy, solar
energy, outdoor furnaces, medical marijuana and mini cell towers for the Supervisors to review
for the September meeting. The mini cell towers are typically located at lower heights along
roads and are becoming an aesthetic issue in some areas. The proposed ordinance permits them
on Park Road and Allentown Pike. The proposed outdoor furnace ordinance allows outdoor
furnaces on a property that is a minimum of two acres. Mr. Rudderow asked if this restricted
recreational structures like chimineas. Mr. Kopicki said it would not.

3

Maidencreek Township Board of Supervisor Meeting
August 11, 2016

A motion was made by Claude Beaver, seconded by David Franke, to adjourn the August 11,
2016 meeting of the Maidencreek Township Board of Supervisors. Hearing no questions on the
motion, all members present voted “Aye”. Motion carried. Meeting adjourned at 8:33 p.m.

________________________________________________
Township Secretary,

Cc: Board of Supervisors
Eugene Orlando, Solicitor
Thomas Unger, Township Engineer
Planning Commission
Park & Recreation Board
Zoning Hearing Board and Alternates
Joan London, Zoning Hearing Board Solicitor
Maidencreek Township Authority
Patrick Donovan, Maidencreek Township Authority General Manager
JoAnn Schaeffer, Maidencreek Township Authority Secretary
Daniel Becker, Authority Solicitor
Greg Unger, Authority Engineer
Barbara Hassler, Tax Collector
Daniel Miller, Blandon Fire Company Chief
Chief Scott W. Eaken, Northern Berks Regional Police

4