SYSTEMSDESIGN
SDE
"A Passion for Engineering Excellence"
ENGINEERING,INC
sdei.net
December 15, 2017
Maidencreek Township Authority
PO Box 289
Blandon PA, 19510
Re:
Folino Commercial
Public Sewer and Water Review
Maidencreek Township
Berks County, Pennsylvania
Dear Authority Members:
We are in receipt of the Plans entitled “Berkshire Building Services" prepared by Berks
Surveying & Engineering, Inc.
The site consists of 5.29 acres and situate in the “R-3" - District. The site is located along
West Wesner Road (T-777). The proposed Plan reflects a proposed warehouse with an
office, a macadam parking lot and stone lot area.
The plan submittal consists of 6 sheets as follows:
Sheet Title
Sheet Number
Date
Revision
Overall Site Plan
LD101
11-22-17
Layout Plan
LD102
11-22-17
Grading/Utility Plan
LD103
11-22-17
Existing Site Plan
LD104
11-22-17
Detail Sheet
LD105
11-22-17
Detail Sheet
LD106
11-22-17
We have reviewed the above referenced plans and have the following comments for your
consideration:
Sewer
1. The Grading/Utility plan submitted shows a sewer lateral of approximately 475 feet
in length connecting the proposed warehouse/office to SSMH-80 on West Wesner
Road. However, the plan and detail sheets do not specify the pipe material, pipe
thickness, pipe diameter, and whether or not it is gravity or low pressure sanitary
sewer. Therefore, the following information should be provided in order to properly
review:
1032 James Drive, Leesport, PA 19533 . P: 610.916.8500 . F: 610.916.8501
Schuylkill Haven, PAP:570.385.5549
Boyertown, PAP: 610.369.1319

Maidencreek Township Authority
Page 2
Folino Commercial Sketch Plan Sewer and Water Review
December 15, 2017
A profile shall be provided illustrating the proposed sewer lateral pipe material,
pipe thickness, pipe diameter, slope (if applicable), and length.
The profile shall include the crossing of the sewer lateral with the 60"
HDPE stormsewer pipe. The sewer lateral must meet the minimum
depth requirement of 3'-6" below grade and a minimum separation of
1'-6" between all utility crossings.
-If the proposed lateral_will_be-gravity sewer, .cleanouts (in accordance with
Authority standards) shall be installed and noted on plans every 50 feet and at all
changes in pipe direction. A detail of proposed cleanout shall be provided on the
Detail Sheet.
 Provide concrete pad if cleanout/vent is located in paved area (in
accordance with Authority standards).
Cleanout/vent shall be installed /2' above final grade in paved and
landscaped areas (in accordance with Authority standards).
 If the proposed lateral will be low pressure sanitary sewer, the make, model,
location, and a detail of the grinder pump station shall be provided.
There is no information regarding the lateral's tie-in at SSMH-80. Provide a
detail illustrating the tie-in location and invert in respect with existing manhole
conditions (i.e. rim/channel inverts, step location, etc.). Ideally, lateral should tie-
in between 6"-12" above existing channel near the top of manhole bench. Clarify
the method for manhole/pipe adapter installation (Link-Seal, Kor-N-Seal Wedge
Korband Connector Assembly, etc.). All pertinent information shall be noted on
plans.
Provide trench backfilling detail of proposed sewer lateral in W. Wesner Road
Right-of-Way.
2. The proposed flow from the facility should be submitted to the Authority to calculate
the tapping fee. The sewer tapping fee using this flow rate will be $13.77/gpd for
this commercial property. In order for the Authority to bill for the sewer flows, a
meter will need to be installed on the water source. The quarterly sewer bills would
be based on the meter readings.
3. A planning module exemption will be required and should be submitted to the
Authority.
4. A note shall be added to the plan stating the proposed sewage flows for this facility
will contain domestic sewage only. If the proposed wastewater discharge will
contain any non-domestic sewage, details will need to be submitted to the Authority
for review and approval.
SDE

Maidencreek Township Authority
Page 3
Folino Commercial Sketch Plan Sewer and Water Review
December 15, 2017
5. The Property Owner will be responsible for all applicable costs (tapping fees, review
fees, permit fees, etc.). The property owner will also be responsible for the cost and
installation of the meter. The meter will be provided by the Authority, but the size of
the meter needs to be determined by the property owner. A note shall be placed on
the plan stating that “Additional fees may be required based on sewer use reviewed
on a yearly basis complying with all rules and regulations of the Maidencreek
Township Authority for tapping fees".
6. A Maidencreek Township road opening permit will be required for the proposed
sewer connection.
7. The proposed lateral shall be private and the sole responsibility of the Property
Owner.
Water
1. Proposed water line from well to warehouse is not shown. Provide plan view of
water line, including the pipe size and material.
2. Provide detail of proposed wellhead protection cover and concrete leveling pad.
3. A backflow prevention device is recommended to be provided to protect the ground
water source.
Due to the lack of information on this drawing set, this review should be considered
preliminary until more information is provided. The Authority reserves the right to add
additional comments based on further review.
If you should have any questions, please contact our office.
Sincerely,
Systems Design Engineering, Inc.
Pamela J. Stevens, P.E.
Authority Engineer
cc:
Maidencreek Township Supervisors
Maidencreek Township Planning Commission
Dan Becker, Esq.
Folino Construction Co., Inc.
Berks Surveying & Engineering
File 17-0466-0539
SDE