ENGINEER'SAGENDA
SubdivisionReviewStatusChecklist
Next SupervisorsMeetingMay10,2018
Subdivision/Zoning/LDP
Plans currently in review.
GSPPropertiesPreliminaryLDP-SeeMaidencreekTwp.PC4/5/18Itr.andSDE
Itr.dated 3/6/18.
BerkshireBuildingServicesFinal LDP-SeeSDEItr.dated3/5/18.
Melrose Place-Stormwater/Grading
Work on grading swale &properties is onhold due to weather
Projects
StormwaterProjects
Ina/Rt. 73 - Lindbergh/Adele - on hold.
Investigating storm Water control for QuarryRd.&Municipal Bldg.parking lot.
Discuss plansandoptions-see attached parking requirements.
WestShoreDrive
Meet with inspector for state regarding Bridge Inspection. Report.
Repairs are somewhat extensive;Twp.Involvement is possible
Three (3) 60" dia. Pipes required as alternative to existing opening. Not
desirable due to maintenance.
Twp.to make repairs as schedulepermits.
Dog Park
Bids received and opened on March 1, 2018; Bid Tabulation,reviewed w/Bos.
BOS awarded contract to Fehl's in the amount of $32,537.
Intent to Award sent to Fehl's getting bonds & contracts together.
2018RoadProjects
Advertised to receive bids and open bids on April 11 @ 10:00am: bids to be
presented at the April 12 BOS meeting.
MunicipalBldg.HVACSystem
SDE did cursory inspection; will have report for BOS mtg.
SubdivisionImprovementLOC/EscrowRelease
Sewage EnforcementOfficerActivity Report-NoActivity
Page 1of 1
I:\Projects\MaidencreekTownship|18-0019-0100\Engineer'sAgenda\4.12.18.docx

Most Recent
Letter Date
3/6/2018
2/8/2018
Review
3/5/2018
See SDE ltr.3/6/18 and MTPC ltr.
1/3/18&2/8/18
See SDE Itr. Dated 3/5/18
Comments
P.C. Action Itr. 1/4/18
Dated 4/5/18
See SDE Itr.
Approved
BY BOS
02/08/18
BERKSCOUNTY
(may reflect more
than one extension)
Extension
8I/S0/90
SUBDIVISIONSTATUS
MAIDENCREEKTOWNSHIP,
4/12/2018
Period Ends
03/06/18
03/06/18
Review
90-Day
06/05/18
Review Period
I:IProjectsIMaidencreek Townshipl18-0019-01001Subdivision Status14.12.18
12/06/17
12/06/17
90-Day
Begins
03/07/18
Plan Stage
Final
Prel.
LDP
Prel.
LDP
LDP
APPROVED/PENDINGPLANS:
BerkshireBuilding Services
Berkshire Building Services
CURRENT PLANS:
Project Name
GSPProperties
No.

SYSTEMSDESIGN
SDE
"A Passion forEngineering Excellence"
ENGINEERING,INC
sdei.net
March 6, 2018
Maidencreek Township Planning Commission
POBox319
Blandon PA 19510
Re:
Business Park at Maidencreek Land Development Plan
Preliminary Plan Review #2
Maidencreek Township
Berks County
Dear Planning Commission Members:
We are in receipt of a Preliminary Plan entitled Business Park at Maidencreek prepared by
Stackhouse Bensinger Inc. (SBI) of Sinking Spring PA. The owner of the tract is GSP
Properties-North Bethlehem, LLC of Allentown PA.
The site consists of 9.4 acres and is located in the “CR-Commercial Residential District". The
site is located along the south west side of Rt. 222, has 260 feet of frontage and is approximately
925 feet deep being rectangular in shape. A single access private drive/parking lot is being
proposed through the center of the tract terminating in a cul-de-sac. There are 22 - 1,479 square
foot office buildings being proposed in 11 duplexes with perpendicular parking provided fronting
the units.
The SBI plan submittal consists of 17 sheets as follows:
TITLE
PLAN NUMBER
DATE
REV.
Cover Sheet
C-1.1
11-27-17
2-21-18
Ex. Cond. Site Analysis
C-2.1
11-27-17
2-21-18
Demolition
C-3.1
11-27-17
2-21-18
Land Development
C-4.1
11-27-17
2-21-18
Grading and Utility
C-5.1
11-27-17
2-21-18
Landscaping
C-6.1
11-27-17
2-21-18
Lighting
C-6.2
11-27-17
2-21-18
Driveway, Storm, Sanitary Profiles
C-7.1
11-27-17
2-21-18
Site Construction Details
C-8.1
11-27-17
2-21-18
Site Construction Details
C-8.2
11-27-17
2-21-18
Site Construction Details
C-8.3
11-27-17
2-21-18
Site Construction Details
C-8.4
11-27-17
2-21-18
Pre-Construction Cond. Plan
C-PCC
11-27-17
2-21-18
PCSM and O&M Plan
C-PCSM1
11-27-17
2-21-18
PCSMandO&MPlanDetails
C-PCSM2
11-27-17
2-21-18
PCSM and O&MPlan Details
C-PCSM3
11-27-17
2-21-18
1032JamesDrive, Leesport,PA19533。P:610.916.8500。F:610.916.8501
SchuylkillHaven,PAP:570.385.5549
Boyertown,PAP:610.369.1319

Maidencreek Township Planning Commission
Re:
Business Park at Maidencreek LDP
PreliminaryPlanReview#2
March 6, 2018
Page 2
PCSM andO&M Plan Notes and Details
C-PCSM4
11-27-17
2-21-18
Additional plans submitted is a set of PennDOT Highway Occupancy Permit (HOP) drawings,
by Dimmerling Consulting, Inc., consisting of three (3) sheets as follows:
TITLE
PLAN NUMBER
DATE
REV.
General Notes
17011 2of 4
Feb.2018
Typical Sections/Details
17011 3 of 4
Feb.2018
Construction Plan
17011 4 of 4
Feb. 2018
Also submitted and reviewed was a “Post-Construction Stormwater Management Plan
Narrative, prepared by Stackhouse Bensinger Inc., dated February 21, 2018.
We have reviewed the above referenced plan and have the following comments for your
consideration:
Zoning:
1. Additional Regulations for Commercial Use.
Section 220-39-A. Where any property abuts a property the principal use of which is
residential, regardless of whether the property is vacant or not, the owner of such
property shall provide a screen planting in conformance with Section 220-64 along all
property lines which abut the property used or zoned for residential purposes.
Although the boundary of this tract presently contains many trees which screen the
adjoining properties, the applicant should assure the Township that after the site is built,
all areas on this tract adjacent to residential use shall remain screened or screening must
be provided. A Note has been placed on the plan addressing this and should be
reviewed by the Planning Commission.
SALDO:
1. Erosion and Sediment Control. Section 190-41. An erosion and sediment control plan
will need to be submitted and approved by the Berks County Conservation District prior
to Final Plan approval.
2. Improvement Specifications. Section 190-31. An Improvements agreement will be
required prior to final plan endorsement by the Planning Commission and the Township
Supervisors.
Stormwater Comments (Chapter 182 Stormwater Management):
SDE

Maidencreek Township Planning Commission
Re:
Business Park atMaidencreek LDP
Preliminary Plan Review #2
March 6, 2018
Page 3
1. PennDOT Approval, Section 182-9.H. This project will need to be coordinated with
PennDOT's S.R. 222 improvements. We will defer to PennDOT for authorization of
work in and adjacent to their right-of-way.
2. Erosion and Sediment Control/NPDES Permit, Section 182-11. Evidence of approval
of the E&S and NPDES permit applications by Berks County Conservation District shall
be provided to the Township, prior to plan approval. A copy of the plan should be
provided to the Township.
3. Storm Sewers, Section 182-17.D.(16) Rain water conductor outfalls into forebays
should be evaluated for erosion protection (i.e., riprap aprons, etc.). We understand this
will be provided with the erosion control plans.
4. Plan Detail, Section 182-22.D.(1) A detail of the flapgate should be provided.
5. BMP Operations and Maintenance, Section 182-32. An O&M agreement is required
to be executed prior to plan approval.
6. Stormwater Easements, Section 182-33.B. Note 62 on plan sheet C-1.1 offers a
“blanket" stormwater easement in favor of Maidencreek Township for inspection of the
privately-owned stormwater BMPs. We have no objection to the blanket easement
approach, but this should be approved by the Solicitor and Board of Supervisors.
Additional Comments:
1. Landscaping should be discussed with the Planning Commission.
Sincerely,
SYSTEMS DESIGN ENGINEERING, INC
Ed Kopicki
Township Planning Consultant
Cc:
MaidencreekTownship Supervisors
Diane Hollenbach, Twp. Manager
Eugene Orlando Jr., Twp Solicitor.
GSP Properties-North Bethlehem LLC
Stackhouse Bensinger Inc.
File17-0024-0708
SDE

MAIDENCREEKTWP.PLANNINGCOMMISSION
P.O.BOX319,BLANDON,PA19510
April 5, 2018
Maidencreek Township Board of Supervisors
PO Box 319
Blandon,PA 19510
Dear Board,
At their April 4, 2018 meeting, the Maidencreek Township Planning Commission
recommended by formal motion that the Board of Supervisors grant preliminary plan approval
the Business Park at Maidencreek Land Development Plan conditional upon compliance with the
comments in the March 6, 2018 Systems Design Engineering, Inc. review letter which is
incorporated by reference. Some item in the review letter are final plan items.
If you have any questions, please call me at (610) 926-4920.
Sincerely,
DianeHollenbach
Manager
MaidencreekTownship
cc:
StackhouseBensinger

SYSTEMSDESIGN
SDE
"A Passion for Engineering Excellence"
ENGINEERING,INC
sdei.net
March 5, 2018
Maidencreek Township Planning Commission
PO Box 319
Blandon PA 19510
Re:
Berkshire Building Services Development Plan
Final Plan--1st Review
Maidencreek Township
Berks County
Dear Planning Commission Members:
We are in receipt of a Final Plan entitled Berkshire Building Services (BBS) Overall Site Plan
prepared by Berks Surveying & Engineering, Inc. The present owner of the tract is Jeffrey and
Carol Baum of Fleetwood and the equitable owner is Berkshire Property Management Company,
LLC of reading.
The site consists of 5.29 acres and is located in the “I Industrial District". The site fronts the
Norfolk Southern Rail Road tracks to the north, the Norfolk Southern abandoned rail road
property to the south and is accessed from West Wessner Road to the west. The Final Plan
reflects a proposed warehouse with an office, a macadam parking lot and stone lot area. The site
is presently wooded however many trees have been removed from the site to date.
The plan submittal consists of 7 sheets as follows:
TITLE
SHEETNUMBER
DATE
BBS Overall Site Plan
REV.
LD 101
11-22-17
BBS Layout Plan
02-09-18
LD 102
11-22-17
BBS Grading/Utility Plan
02-09-18
LD 103
11-22-17
BBS Existing Site Plan
02-09-18
LD 104
11-22-17
BBS Detail Sheet
02-09-18
LD 105
11-22-17
BBS Detail Sheet
02-09-18
LD 106
11-22-17
BBS SewerDetail Sheet
02-09-18
LD 107
12-20-17
BBS Lighting Plan
PH 101
02-09-18
We have reviewed the above referenced plans and have the following comments for your
consideration:
1032JamesDrive,Leesport,PA19533.P:610.916.8500.F:610.916.8501
SchuyikillHaven,PAeP:570.385.5549
Boyertown, PA P:610.369.1319

MaidencreekTownship Planning Commission
Re:
Berkshire Building Services LDP
FinalPlan1stReview
March 5,2018
Page 2
Zoning:
No Comments.
SALDO:
1. Erosion and Sediment Control. Section 190-41. An erosion and sediment control plan
will need to be approved by the Berks County Conservation District prior to Final Plan
approval.
The site has had extensive tree removal recently. The ESCP should address
stabilization of all disturbed areas.
2. Improvement Specifications. Section 190-31. An Improvements agreement will be
required prior to final plan endorsement by the Planning Commission and the Township
Supervisors.
3. Financial Security. Improvements Guarantee. Section 190-27.B.4. The Final Plan
shall not be signed until the improvements guarantee has been executed.
4. Maintenance Guarantee. Section 190-27.E.(1). When Maintenance of stormwater
retention facilities is to be the responsibility of the individual lot owner, the Board shall
require that the maintenance responsibilities be set forth in perpetual covenants or deed
restrictions binding on the land owners' successors in interest, and may further require
that an initial maintenance fund be established in a reasonable manner.
Stormwater:
1. Erosion and Sediment Control Permitting. Section 182-11. The E&S and PCSM
Plans should be submitted with the land development plan for review. Evidence of
approval of the E&S and NPDES/Construction permit shall be provided to the Township
prior to earth disturbance activities.
2. Basin Standards. Section 182-17.C.(1) Emergency spillway stability should be
demonstrated. Calculations indicate stability for grass lining. Temporary linings should
be provided at a minimum, to aid in establishment of the grass. We understand this will
be addressed on the E&S Plan, which has not yet been submitted to the Township.
3. Plan Content. Section 182-22.D.(1) Much of the curb formerly proposed has been
driveway runoff into Basin 1. Paving has also been eliminated within the driveway,
leaving curbed gravel, which leads to concerns including rutting and/or ponding along the
curb line. Paving is recommended along the curbed portion of the driveway.
SDE

MaidencreekTownshipPlanningCommission
Re:
Berkshire Building Services LDP
Final Plan 1st Review
March 5, 2018
Page 3
In addition, calculations for the slope into Basin 1 downstream of the end of curb indicate
stability for grass lining, but temporary lining should be provided to aid in establishment
of grass. As above, we understand this will be addressed on the E&s Plan.
The applicant's engineer indicated (at the Planning Commission Meeting held on January
3, 2018) that some narrow paving would be provided (on the Final Plan) in the area of
curbing along the northern driveway to prevent erosion in this area. The Final Plan does
not specify paving; rather, it includes a note on Sheet LD103 stating, “"Driveway surface
along curb shall be resistant to possible erosion from gutter flow.
This is a private driveway and it is incumbent upon the landowner to provide safe
passage for employees and visitors to the property, as well as to abide by the approved
stormwater management plan. If any future issues arise due to neglect or lapse in
maintenance, they can be addressed at that time via the code enforcement process.
4. Operations and Maintenance Agreement. Section 182-32. The property owner shall
sign an O&M agreement with the Township addressing the terms cited in this section,
prior to final plan approval.
5. Stormwater Management Easements. Section 182-33.B. Stormwater easement(s)
shall be provided as specified in this section. Note 29 has been added to LD101,
should review this proposal for adequacy.
Sincerely,
SYSTEMSDESIGNENGINEERING,INC.
Ed Kopicki
Township Planning Consultant
Cc:
Maidencreek Township Supervisors
Diane Hollenbach, Twp. Manager
Eugene Orlando Jr., Twp Solicitor.
Berks Surveying & Engineering
Jeffrey and CarolBaum
Berkshire Property Management Company, LLC
File 17-0024-0707
SDE

Maid.Municipal Bldg
ParKing
JOB
Systems Design Engineering,Jnc.
SHEET NO.
Engineers·Surveyors·Planners·Construction Managers
1032JamesDriveLeesport,PA19533
CALCULATEDBY
(610)916-8500
DATE
FAX (610) 916-8501
CHECKEDBY
DATE
SCALE
mTAfhce
maidTwpofice
Z 730 5940
39x38'
148z..F
maid.twp.mtaRm
19×38
Mard,Garage
1231×38
467459P4
Ooffice
3.5...paces
assemblyhal/withoutfixedseats
/spaceper5o s9.ft.ofFloorarea
inmtg.cm.olus/spacefor
eyeryzoos9..ftof otherlfloorarea
municipat
Garage
Hof employeesroadcreu
max.
2730 f47/1000f+3)
x 3.5
9.56
722F+3/50f+?
14.4
15
max...employaroadlcrew
TOTAL.
34
Plan
Z6+8+ZADA
36
PRODUCT 204-1 (Single Sheets) 205-1 (Padded)