Other Township Records
Road Crew Report — September 2018
- Date
- Date unknown
- Type
- Report
- Year
- 2018
- File
- PDF · 389 KB
Document text
Machine-extracted from the original — formatting is approximate and there may be recognition errors. Always check the original file above before relying on it. 203 words
Road Crew Report September 2018 September 4 - 6 Pour curb in parking lot Stone and form apron in parking lot Remove plat from Evansville Road and backfill trench with roller Pull plate on Millennium Drive and provide traffic control for televising pipe Pour apron Paint Dries Road and Golden Road Remove asphalt on Walnut Tree Drive Stone in front of curb in parking lot Remove stone on Walnut Tree Drive, put base in Spread topsoil in parking lot Backfill bank of curb in parking lot September 10 - 14 Collect trash Change sign at Community Park Take scrap wood to Zwicky Replace two stop signs on Hecktown Road and Ridge Road Insulate and plastic attic Layout center line and edge lines on Evansville Road Empty trash at parks Sealed drains September 17 - 20 Collect trash Brush collection Take four loads of scrap metal to Pollock from clean up Mow grass Saw cut Prescott Road, dig out around pipe to repair sink hole September 24 - 28 Collect trash. Backfill sinkhole on Prescott Road Ten loads to Zwicky Work on leaf vac Clean up garage Install True Grid on Schaeffer Road Mow grass Paint East Wesner Road Trim Genesis Drive traffic island