Road Crew Report September 2018
September 4 - 6
Pour curb in parking lot
Stone and form apron in parking lot
Remove plat from Evansville Road and backfill trench with roller
Pull plate on Millennium Drive and provide traffic control for televising pipe
Pour apron
Paint Dries Road and Golden Road
Remove asphalt on Walnut Tree Drive
Stone in front of curb in parking lot
Remove stone on Walnut Tree Drive, put base in
Spread topsoil in parking lot
Backfill bank of curb in parking lot
September 10 - 14
Collect trash
Change sign at Community Park
Take scrap wood to Zwicky
Replace two stop signs on Hecktown Road and Ridge Road
Insulate and plastic attic
Layout center line and edge lines on Evansville Road
Empty trash at parks
Sealed drains
September 17 - 20
Collect trash
Brush collection
Take four loads of scrap metal to Pollock from clean up
Mow grass
Saw cut Prescott Road, dig out around pipe to repair sink hole
September 24 - 28
Collect trash.
Backfill sinkhole on Prescott Road
Ten loads to Zwicky
Work on leaf vac
Clean up garage
Install True Grid on Schaeffer Road
Mow grass

Paint East Wesner Road
Trim Genesis Drive traffic island