MAIDENCREEKTOWNSHIPBOARDOFSUPERVISORS
August 8, 2019
ENGINEER'SAGENDA
SubdivisionReview StatusChecklist
Next SupervisorsMeetingSeptember12,2019
Subdivision/Zoning/LDp
Plans currently in review.
5G Ordinance - P.C. has recommended draft regulations for approval by
BOS.
Gun Range regulations being discussed by PC.
MelrosePlace
Original punchlist items completed; maintenance issues remain to be
completed; recommend release of original LoC with the cash
maintenance security of $43,262.10 being held.
Projects
StormwaterProjects
OIna/Rt.73 --- Lindbergh/Adele. on hold.
West Shore Drive
Meet with inspector for state regarding Bridge Inspection.Report.
Repairs are somewhat extensive; Twp.Involvementis possible
Three (3)60" dia.Pipes required as alternative to existing
opening. Not desirable due to maintenance.
Twp.to make repairs as schedule permits.
2019RoadProjects
Notice of Award given to Ronnie C. Folk Paving in the amount of
$268,772.60.
Pre-construction mtg.held on 7/9/19 at 9:00AM.
Work scheduled to start 8/8/19.
Sinkholes
Meadow Brook--Millennium Drive.
RepaircompletedbyWexconon6/21/19;completeinoneday.
Page1of2
I:\Projects\MaidencreekTownship/19-0019-0100\Engineer'sAgenda/8.8.19.docx

Page 2 of 2
SewageEnforcementOfficerActivityReport
SubdivisionImprovementLOC/EscrowRelease
cellular tower regulations.
tower installation. P.C. has made recommendation to BOs to approve 5G
SDE reviewed w/P.C. draft Zoning Ordinance amendments for 5G cellular
Zoning/5GCellularTowerInvestigation
phasing.
Park & Rec preparing a Master Plan topresent to BOSwith proposed
BlandonFireCo.CommunityPark

Most Recent
Letter Date
10/31/2018
3/6/2018
2/8/2018
9/1/2018
7/6/2018
Review
4/29/2019
SeeSDElItr.3/6/18andMTPCItr.
1/3/18&2/8/18
See SDE Itr.Dated 10/31/18
PC recommended conditional
See SDE Itr. Dated 9/1/18
See SDE Itr.Dated 7/6/18
Comments
Approved w/conditions
P.C. Action ltr. 1/4/18
Approved w/conditions
PC action ltr. 5/2/19
Dated4/5/18
See SDE Itr.
approval.
Approved
04/12/18
BY BOS
02/08/18
09/13/18
11/08/18
11/08/18
05/09/19
MAIDENCREEKTOWNSHIP,BERKSCOUNTY
(may reflect more
than one extension)
Extension
06/05/18
09/14/18
10/12/18
11/09/18
SUBDIVISION STATUS
8/8/2019
Period Ends
03/06/18
03/06/18
06/05/18
07/31/18
01/01/19
90-Day
Review
07/02/19
Review Period
I:/ProjectsIMaidencreek Townshipl19-0019-01001Subdivision Status7.11.19
12/06/17
12/06/17
03/07/18
05/02/18
Begins
10/03/18
90-Day
04/03/19
Plan Stage
LDP
Prel.
Prel.
Final
Final
LDP
LDP
Final
LDP
Final
Plan
Plan
APPROVED/PENDINGPLANS:
GSP Properties - Business Park
GSP Properties - Business Park
Berkshire Building Services
BerkshireBuildingServices
Messinger Annexation Plan
GroveRoad Subdivision
CURRENT PLANS:
Project Name
No.

12
or leased.
COMMERCIAL PARKING - A parking lot or garage wherein parking spaces are rented
supports atleastone non-tower WCF.
including antennae, on an existing tower-based WCF, or on any structure that already
COLLOCATION - the mounting of one or more wireless communication facilities,
private entity.
transmitters, repeaters, or similar devices owned or used by more than one public or
pole, mast, tower, cable, wire or other structure supporting multiple antennas, dishes,
COLLOCATED SMALL CELL INSTALLATION - means a single telecommunication
also be sold.
other non-alcohol beverages and where light refreshments and limited menu meals may
COFFEEHOUSE -- A retail commercial establishment offering the sale of coffee, tea, and
environmentally sensitive areas, or agriculture.
the remaining land area is devoted to open space, active recreation, preservation of
under a conventional subdivision or increase in the overall density of development, and
and bulk requirements, provided there is no increase in the number of lots permitted
CLUSTER SUBDIVISIONS - A form of development that permits a reduction in lot area
include adult-related uses, as defined herein.
organizations, labor unions, as well as social and athletic clubs. Private clubs shall not
membership of such club. Clubs shall include, but not be limited to, service and political
conducted for profit, provided they are not conducting any vending stands,
CLUBHOUSE - An organization catering exclusively to members and their guests, or
members and their guests.
facilities owned or operated by a corporation, association, person or persons, for a social,
payment of fees and dues, regular meetings, and a constitution and bylaws; buildings and
interests, or activities and usually characterized by certain membership qualifications,
CLUB - A group of people organized for a common purpose to pursue common goals,
and/orday-care facilities.
definition shall include rectories, convents, cemeteries, and church-related educational
structures, including accessory uses, designed or intended for public worship. This
CHURCH AND RELATED USES - A building, structure, or group of buildings or
CHANNEL FLOW - That water which is flowing within the limits of a defined channel.
confine and conduct continuously or periodically flowing water.
CHANNEL - A natural or artificial watercourse with a definite bed and banks which

or more common party walls and each unit having its own separate entrance from
the outside. (Figure 5).
DWELLING UNIT - A building, or portion thereof, arranged or designed for occupancy
by not more than one (1) family, and having separate cooking and sanitary facilities.
EARTHMOVING ACTIVITY - Any construction or other activity which disturbs the
surface of the land, including, but not limited to, excavations, embankments, land
development, subdivision development, mineral extraction and the moving, depositing or
storing of soil, rock or earth.
EASEMENT - An interest in land owned by another that entitles the holder to a specific
limited use or enjoyment.
EATING AND DRINKING ESTABLISHMENT - A commercial activity, the principal
purpose of which is the remunerated furnishing or serving of food and beverages for
consumption on the premises. This definition includes restaurants and any other activity
which may include a restaurant-type facility, such as hotels, country clubs, and social
clubs, regardless of whether such activity is open to the general public.
EXEMPTED TELECOMMUNICATIONS FACILITIES - Includes, but not limited to
the following.
A single ground or building mounted receive-only radio or television antenna
inchuding any mast, for the sale use of the tenant occupying the residential parcel
on which the radio or television antenna is located, with an antenna height not
exceeding twenty-fivefeet.
A ground or building mounted citizens band radio antenna, including any mast, if
the height (post and antenna) does not exceed thirty-five feet.
A ground, building or tower mounted antenna operated by a federally licensed
amateur radio operator as part of the Amateur Radio Service, if the height (post
and antenna) does not exceed thirty-five feet.
A ground or building mounted receive-only radio or television satellite dish
antenna which does not exceed thirty-six inches in diameter, for the sole use of
the resident occupying a residential parcel on which the satellite dish is located,
provided the height of said dish does not exceed the height of the ridgeline of the
primary structure on said parcel.
Mobile services providing public information coverage of news events of a
temporary nature.
Hand-held devices such as cell phones, business-band mobile radios, walkie-
talkies, cordless telephones, garage door openers and similar personalouse
devices.
17

18
rebuttable presumption that four or more persons living together in a single dwelling unit,
FAMILY - One (1) or more persons living together in a single dwelling unit as a
front lot line.
provides access. The facade is typically, but not necessarily, more or less parallel to the
which the lot has frontage; that surface through which the main building entrance
FACADE - The front surface of a building, usually visible from the public street upon
and 47 U.S.C. $332(c)(7).
[also known as 86409(a) of the Middle Class Tax Relief and Job Creation Act of 2012]
in $27-745 of this Douglass Township Code relate to FCC Rules 47 U.S.C. $1455(a)
systems and other small cells. Applicable rules reflected in the requirements as set forth
which regulate both traditional telecommunication towers as well as distributed antenna
FCC RULES -- recent Federal Communication Commission Rules effective April 8, 2015
as the removal of materials for fill operations.
of sand, clay, shale, gravel, topsoil, stone, ore, or minerals; also, similar operations such
EXTRACTIVE INDUSTRY or EXTRACTIVE OPERATION - The mining or quarrying
primates.
cougars, servals, ocelots, hyenas, venomous or constricting snakes, and non-human
chinchillas, hedgehogs, wallaroos, lions, tigers, bobcats, leopards, cheetahs, jaguars,
amphibians, foxes, bears, wolves, skunks, degus, civets, genets, kinkajous, raccoons,
as a household pet. Examples of such animals include but are not limited to: alligators,
domesticated, retaining its wild, carnivorous and or predatory nature making it unsuitable
EXOTIC ANIMALS - An exotic animal is a rare or unusual animal which has not been
sadomasochism, pedophilia; bestiality; or masturbation.
EROTIC ACTIVITIES - Actual or simulated genital, anal, or oral intercourse;
the right-of-way to be unusable and result in loss of the service provided.
health, welfare or safety of the public, or (2) has caused or is likely to cause facilities in
EMERGENCY -- a condition that (1) constitutes a clear and immediate danger to the
employees/vehicles of said company in the course of business.
Telecommunication facilities, including multiple antennas located on an industrial
feet.
public utilities, operations and maintenance if the height does not exceed seventy
and/or irrigation systems, with heights not exceeding thirty-five feet.
water, flood alert, traffic control devices and signals, storm water, pump stations

LOT TYPES DIAGRAM
STREET
CORNER
INTERIOR
Lor
CORNER
THROUGHLOT
CORNER AND
Lor
STREET
THROUGHLOT
LOT
FLAG
LOT
CORNER
CORNER
LOT
INTERIOR
LOT
LOT
STREET
LOTS
LOT AREA - For the purpose of determining compliance with minimum lot area
requirements specified by this chapter and for all other instances where the term "lot
area" or "lot size" is used without a preceding modifier, the "lot area" shall be the total
area of land and surface waters contained within the legal limits of the property lines of a
lot, excluding lands within public rights-of-way. The calculation of lot area for a flag lot
shall not include the lands occupied by the access strip.
LOT DEPTH - The horizontal distance measured between the street right-of-way line and
the closest rear property line. On corner and through lots, the depth shall be measured
from the street right-of-way of the street of address to the directly opposite property line.
LOT LINE - A line of record bounding a lot which divides a lot from another lot, from a
public or private street, or from any other public or private space.
LOT LINE, FRONT - A line of record separating a lot from the dedicated right-of-way of
a public or private street.
LOT LINE, REAR - The lot line or lines parallel to, or within thirty degrees (30°) of
being parallel to, and most distant from the front lot line.
LOT LINE, SIDE - Any lot line which is not a front lot line or a rear lot line, including
all lot lines tangent to the front lot line.
LUMBERYARD - The principal use of land and structures involving the loading and
unloading, storage and sales of lumber and millwork materials.
MAJOR TELECOMMUNICATIONS FACILITY -- means telecommunication towers,
poles or similar structures greater than 50 feet in height, including accessory equipment
such as transmitters, repeat microwave dishes, horns, and other types of equipment for
the transmission or receipt of such signals, as well as support structures, equipment
buildings and parking areas.
26

38
pollution, orenvironmental degradation.
deposits of solid waste without creating public health or safety hazards, nuisances,
SOLID WASTE LANDFILL - A site on which engineering principles are utilized to bury
Regulations, Title 40, Chapter 1, Part 261, dated July 1, 1984, or as amended.
biological excrement nor hazardous waste materials, as defined in the Code of Federal
commercial, agricultural and residential activities. Such wastes shall not include
limited to, solid and liquid waste materials resulting from municipal, industrial,
SOLID WASTE - Garbage, refuse and other discarded materials, including, but not
wouldinterferewith solaraccess.
location by forbidding and activity, including placement of objects, live or otherwise, that
that protects the solar sky space of a proposed solar energy collector at a described
instrument executed by or with the landowners permission, on behalf of any landowner,
the form of an easement, covenant or other property interest in any deed or other property
and cooling, and hot water heating.
includes solar collectors, storage facilities, and distribution components, for space heating
Agriculture's Soil Survey for Berks County, Pennsylvania.
SOIL SURVEY - The latest published version of the United States Department of
equipment required for the transmission or receipt of such signals.
antennas, microwave dishes, power supplies, transformers, electronics, and other types of
SMALL CELL INSTALLATION - means all equipment required for the operation and
SLASH - Woody debris left in the woods after logging, including logs, chunks, bark,
any means.
SKIDDING - The dragging of felled trees on the ground from the stump to the landing by
deployed on the ground.
that area in proximity to the structure and to other transmission equipment already
currently related to the site, and, for other eligible support structures, further restricted to
the leased or owned property surrounding the tower and any access or utility easements
SITE -- for towers other than towers in the public right-of-way, the current boundaries of
traffic and directional signs.
pennant, or other insignia of any nation, state, city, or other political unit as well as public
includes billboard. For the purposes of this chapter, the term "sign" shall exclude the flag.

Chapter 220
s220-81 Wireless Communication Facilities
A. Purpose.
(1)
To accommodate the need for cellular communications antennas while
regulating their location and number in the Township
(2)
To minimize adverse visual effects of wireless communications antennas
and support structures through proper design, siting and vegetative
screening.
(3)
To avoid potential damage to adjacent properties from antenna support
structure failure and falling ice, through engineering and proper sighting
of antenna support structures.
(4)
To encourage the joint use of existing and any new antenna support
structures to reduce the number of such structures needed in the future.
(5)
At the discretion of the Maidencreek Township Board of Supervisors,
municipal uses for the purposes of police protection, fire protection,
ambulance service and road maintenance shall be exempt from these
regulations.
B. Use regulations.
This section addresses the various types of Wireless Communication Facilities
(WCF's) permitted in the Township either as a Use by Right or by Conditional
Use in all or selected zoning districts. The following table presents an overview
of the various WCF Uses and where they are permitted.
WCFUses PermittedBy Zoning District
WCF Use Type
Permitted By
Zoning District(s) Permitted
Towers on
Municipal Property
$220-81.B(1)(a)
By Right
All Districts
New Antenna /
ExistingStructure (l)
$220-81.B(1)(b)
By Right
All Non-Residential
Districts
Antenna / Equipment

Township.
use approval, provided a license and/or lease authorizing such
by Maidencreek Township without the need for a conditional
this Chapter, are permitted by right on land owned or controlled
Towers on Municipal Property. Antennas and/or towers (Tower-
(a)
subject to the specific requirements set forth below.
facilities are permitted as a Use by Right in all or selected zoning districts
Permitted Uses By Right. The following wireless communication
(1)
(3) Height increase of existing structure in excess of twenty (20) feet.
(2) Compliant with “No Substantially Change" standards.
Notes:
Public Street ROW's
All Districts -- Inside
Conditional Use
$220-81.B(2)(e)
Public ROW
WCF Inside
New Non-Tower
ROWofRt.222&ParkRoad
AllDistricts-- Inside
Conditional Use
$220-81.B(2)(d)
OfPublicROW
Pole/Tower Inside
NewCommunication
Industrial District
Conditional Use
$220-81.B.2(c)
Of Public ROW
Tower Outside
NewCommunication
All Districts
Conditional Use
$220-81.B(2)(b)
Existing Structure (3)
New Antenna /
All Districts
Conditional Use
$220-81.B.2(a)
Existing Tower
Relocation of
All Districts
By Right
s220-81.B(1)(d)
Existing Tower (2)
Collocation on
New Antenna
All Districts
By Right
$220-81.B(1)(c)
Replacements

(b)
New Antenna/Existing Structure. A new cell site antenna (Non-
Tower WCF) may be located on an existing smoke stack, water
tower, farm silo or other tall structure in all non-residential zoning
districts provided:
1)
Submission of a zoning permit for the cell site antenna.
2)
Provide a report from a structural engineer licensed in the
State of Pennsylvania on the structural adequacy of the
existing structure to accommodate the added weight and
wind load of the proposed antenna location.
3)
That the height of the antenna shall not exceed the height
of the existing structure by more than twenty (20) feet
above the permitted height of the applicable zoning
district.
4)
Building mounted communications antennas shall not be
located on any single-family dwelling.
5)
Omnidirectional or whip communications antennas shall
not exceed twenty (20) feet in height and seven (7) inches
in diameter.
6)
Directional or panel communications antennas shall not
exceed five (5) feet in height and three (3) feet in width.
7)
Any applicant proposing communications antennas to be
mounted on a building or other structure shall submit
evidence of agreements and/or easements necessary to
provide access to the building or structure on which the
antennas are to be mounted so that installation and
maintenance of the antennas and communications
equipment building can be accomplished.
8)
Any applicant proposing communications antennas to be
mounted on a building or other structure shall submit
detailed construction and elevation drawings indicating
how the antennas will be mounted on the structure for
review by the Township Engineer for compliance to
applicable building codes.
9)
The antenna complies with all applicable FCC and FAA
regulations.

change).
determine if it is considered as a substantial change" or
The proposed antenna collocation will be reviewed to
4)
wind load of the new antenna array.
existing cell tower to accommodate the added weight and
State of Pennsylvania on the structural adequacy of the
Provide a report from a structural engineer licensed in the
3)
appropriate to show the proposed collocation work.
Submission of a plan set and other information as
Submission of a zoning permit for the antenna collocation.
1)
permitted in all zoning districts subject to:
tower location. Collocation of new antennas on existing towers is
existing cell tower is encouraged over the construction of a new
New Antenna Collocation. Location of a new antenna array on an
(d)
building codes.
(s
applicable FCC and FAA regulations.
The replacement antenna array(s) comply with all
4)
wind load.
State of Pennsylvania on the structural adequacy of the
Provide a report from a structural engineer licensed in the
2)
replacement.
Submission of a zoning permit for the antenna/equipment
1)
antennas or existing equipment such as electrical cabinets are
(c)
The antenna complies with all applicable building codes.
10)

5)
Timing of the zoning application for a new collocation
antenna will be approved within the time frames set forth
under s220- 81.C. Should a zoning variance be required
due to a height conflict, the prescribed review period will
not start until the required zoning approval has been
secured and the application is then deemed to be complete.
6)
The new collocation antenna array complies with all
applicable FCC and FAA regulations.
The new collocation antenna array complies with all
applicable building codes.
(2)
Uses Permitted by Conditional Use. The following wireless
communication facilities are permitted subject to Conditional Use
approval from the Maidencreek Township Board of Supervisors, in all or
specific zoning districts subject to the specific requirements set forth
below in additional to those presented in 220-81.C below.
(a)
Relocation of an Existing Tower.
A tower which is being rebuilt to accommodate the
collocation of an additional antenna may be moved on its
site within fifty (50) feet of its existing location as long as
all other applicable requirements have been met.
2)
After the tower is rebuilt to accommodate collocation, only
one (l) tower may remain onsite.
3)
A relocated onsite tower shall continue to be measured
from the original tower location for purposes of calculating
separation distances between towers pursuant to these
regulations. The relocation of a tower hereunder shall in no
way be deemed to cause a violation of these regulations.
4)
The onsite relocation of a tower which comes within the
separation distances to residential units or residentially
zoned land shall only be permitted with additional
approvals
(b)
New Antenna/Existing Structure. A new cell site antenna (Non-
Tower WCF) to be located on an existing smoke stack, water
tower, farm silo or other tall structure in all non-residential zoning
districts where the height of the new antenna will exceed the height
of the existing structure in excess of twenty (20) feet shall require
Conditional Use approval provided:
25

public rights-of-way are permitted in the I Industrial District
New communication towers (Tower-based WCF's) outside of
New Communication Tower Outside Public Rights-of-Way.
(0)
The antenna complies with all applicable building codes
(6
regulations.
The antenna complies with all applicable FCC and FAA
(8
applicable building codes.
review by the Township Engineer for compliance to
how the antennas will be mounted on the structure for
detailed construction and elevation drawings indicating
equipment building can be accomplished.
maintenance of the antennas and communications
antennas are to be mounted so that installation and
provide access to the building or structure on which the
mounted on a building or other structure shall submit
Any applicant proposing communications antennas to be
(9
Directional or panel communications antennas shall not
in diameter.
Omnidirectional or whip communications antennas shall
4)
located on any single-family dwelling.
wind load of the proposed antenna location.
existing structure to accommodate the added weight and
State of Pennsylvania on the structural adequacy of the
Provide a report from a structural engineer licensed in the
Submission of a zoning permit for the cell site antenna.
1)

subject to Conditional Use approval. Consideration for
approval would be subject to compliance with the criteria
listed below as well as those of s220-81.C of this Chapter:
1)
Annual Permit Fee -- The Applicant shall pay the Township
an annual Permit Fee as set by Resolution by the Board of
Supervisors.
2)
Location -- the Applicant shall be required to demonstrate,
using technological evidence, that the tower-based WCF
must be located where it is proposed.
3)
Height -- The Applicant must demonstrate that the tower-
based WCF is the minimum height required to function
satisfactorily. Maximum height of the tower shall be two-
hundred (200) feet. Accessory facilities shall meet the
height requirements of the zoning district in which it is
located.
4)
Structure Design -- The applicant shall demonstrate that the
proposed tower-based WCF is safe and that the surrounding
area will not be negatively affected by support structure
failure, falling ice or other debris, electrometric fields,
radio or satellite frequency interference. A licensed
professional engineer shall certify that the tower can
structurally accommodate the number of shared users being
proposed by the applicant and that the tower meets the
setback, requirements, separation distances.
5)
Fence -- A fence shall be required around the tower-based
WCF and other equipment. The fence shall be eight (8)
feet in height. Any wire on top of the fence shall not be
included in the measurement of the height of the fence.
6)
Landscaping -- The following landscaping shall be required
to screen as much of the tower-based WCF support
structure as possible, the fence surrounding the support
structure, and any other ground level features (equipment
cabinets, etc.):
(a)
An evergreen screen shall be required to surround
the site. The screen can be either a hedge or a row
of evergreen trees. The evergreen screen shall be a
minimum height of six (6) feet at planting, and shall
grow to a minimum height of fifteen (15) feet at
maturity.

125
exposure to electromagnetic radiation.
standards established by the FCC governing human
proposed to be mounted thereon comply with all applicable
Communication Tower and communications antennas
Applicant shall demonstrate that the proposed Wireless
present evidence that it has obtained such license. The
Communications Commission (FCC), the Applicant shall
agency, including but not limited to the Federal
tower-based WCF requires licensing by any state or federal
Federal Communication Commission -- If the use of a
11.
commencement of construction for any tower-based WCF
permit in accordance with Township requirements prior to
Building Permit -- The applicant shall obtain a building
10.
be made available at no cost.
communication systems, if desired by the Township shall
proximity of the choses site. Space for Township
the antenna on an existing tower or structure within close
demonstrate that a reasonable effort has been made to site
construction of a new tower, the applicant shall
police, fire and emergency services. Prior to proposing the
accommodate other users, including but not limited to
any proposed support structure shall be designed to
tower-based WCF's needed in the Township in the future,
Accommodating Use -- In order to reduce the number of
the zoning district in which the site is located.
located on the site unless the use is otherwise permitted in
studio, maintenance depot, or vehicle storage shall not be
tower-based WCF such as a business office, transmission
(2) off-street parking spaces.
the largest shirt, but in any event, may not be less than two
required parking spaces shall equal the number of people in
required. If the site is not automated, the number of
automatic, two (2) off-street parking spaces shall be
Parking Spaces - If the tower-based WCF is fully
possible.
the site shall be preserved to the greatest extent
In addition, the existing vegetation on and around
(q)

12)
Lighting -- No wireless communication towers shall be
artificially lighted except when required by the Federal
Aviation Administration or by state regulations.
Communication towers shall comply with all applicable
federal Aviation Administration, Commonwealth Bureau of
Aviation and applicable Airport zoning Regulations.
13)
Lot Requirements. A new tower-based WCF may be
permitted as the sole use on a lot, or in combination with an
existing use, except residential, subject to the following
conditions:
a)
The existing use on the property may be any
permitted use in the applicable zoning district, and
need not be affiliated with the WCF.
b)
The minimum lot size shall comply with the
applicable district and shall be the area needed to
accommodate the tower-based WCF, its guy wires,
the equipment building, security fence, and buffer
plantings in addition to the existing use.
The minimum lot size for a stand-alone WCF lot
shall be one (1) acre.
14)
Setbacks - The setback of a tower-based WCF from all
property lines, existing street right-of-way lines and above
ground utility lines shall be no less than the height of the
tower. All guy wire anchors shall be setback a minimum of
forty (40) feet from the property lot lines and existing street
right-of-ways. No more than one (1) tower shall be
permitted on a single lot.
15)
Signs -- No portion of any communication tower or antenna
shall be used for a sign or other advertising purpose. No
routine lighting of a tower, antenna, or accessory facilities
shall be permitted.
16)
The WCF shall employ the most current Stealth
Technology in an effort to appropriately blend into the
surrounding environment and minimize aesthetic impact.
Application of the Stealth Technology chosen by the
applicant shall be subject to approval of the Township.
17)
Annual Certification -- In January of each year an
inspection shall be performed by an independent engineer
acceptable to the Township and paid by the Applicant and

SZ/s1
10
designed and shall submit the same to the zoning officer.
Engineer's Certification that the tower is constructed as
Occupancy being issued, the Applicant shall provide an
Occupancy Permit -- Prior to a Certificate of Use and
20)
accordance with all applicable Subdivision and Land
and any accessory structures. Said Plan shall be in
communication tower, buildings, fences, buffering, access,
required for tower-based WCF sites showing the
elevations prepared by a professional engineer, shall be
19)
infrastructure is to be stabilized and anchored.
demonstrate how the proposed tower and related
communications tower is to be located. The owner shall
submit geotechnical evaluation of the site in which the
Geotechnical investigation. The owner shall complete and
18)
thetower
Review of all reasonable requests of shared use of
Copy of current FCC license
(8
the operator
Height of antenna
Manufacturer, type and model of equipment
power
Transmission and maximum effective radiated
Frequency, modulation and class of service
b)
Direction of the signal
a)
including at minimum:
approved at the time of conditional use application,
characteristics of the commercial tower-based WCF as
officer that there have been no changes in the operating
verification shall be provided to the Township zoning

21)
Access -- Access shall be provided to thetower-based WCF
by means of a public street or easement to a public street.
The easement shall be a minimum of twenty (20) feet in
width and shall be improved to a width of at least ten (10)
feet with a dust-free, all weather surface for its entire
length.
22)
If a tower-based WCF is to be designed as a structure or
natural feature, the communications tower and antenna
shall be disguised and/or camouflaged within the
surrounding area. The type, style, color, design, size and
location of the disguised and/or camouflaged
communications tower and antenna shall be subject to the
approval of the Township Board of Supervisors as part of
theconditional useprocess.
23)
Removal -- The Applicant shall submit a plan for the
removal of a tower-based WCF when it becomes
functionally obsolete or is no linger in use. Any antenna or
tower that is not operated, and for which there is no intent
or attempt to operate, for a continuous period of time of
twelve (12) months shall be considered abandoned, and the
owner of such tower or antenna shall remove the same
within ninety (90) days after receipt of notice from the
Township notifying the owner of such abandonment.
Failure to remove an abandoned antenna or tower within
said ninety (90) days shall be grounds to remove the tower
or antenna, at the owner's expense. If there are two or
more users of a single tower, then this provision shall not
become effective until all users have abandoned the tower
orantenna.
Replacement -- when future technology avails itseif with
radiation suppressant devices and/or less harmful
equipment to humans, such equipment shall replace dated
equipment as soon as possible.
(d)
New Communication Pole/ Tower Inside Public Rights-of-Way.
New communication towers (Tower-Based WCF's) of forty
(40) (50) feet or shorter may be permitted inside the public
right-of-way of Rt. 222 and Park Road throughout the
Township, regardless of the underlying zoning district,
provided they are compliant with the following:
11

12
PennDOT design provisions.
practicable, under the HOP and applicable
facilities shall be installed outside the shoulder and
location of new poles and other above ground
(2) feet from edge of cartway if no curb. The
(18) inches of the face of curb or a minimum of two
walls, or landscaping be located within eighteen
In addition:
equipment shall be 14 feet from the surface of the ground.
PennDOT. Minimum height of antennae & associated
motorists or to otherwise inconvenience public use of the
otherwise create safety hazards to pedestrians and/or
visual obstruction to pedestrian or vehicular traffic, or to
equipment shall be located as not to cause any physical or
Tower-Based WCF's inside public right-of-way and related
(9
within a state highway right-of-way.
PennDOT as may be required when the proposed WCF is
Securing of a Highway Occupancy Permit (HOP) from
(s
Utility Code.
powers of the Township and the requirements of the Public
manner requirements shall be consistent with the police
considerations. For public utilities, the time, place and
physical burden on the right-of-way, and related
right-of-way based on public safety, traffic management,
and/or removal of all Tower-Based WCF's in the public
place and manner of construction, maintenance, repair
The Township and PennDOT shall determine the time,
4)
be located in the front facade area of any structure.
Tower-Based WCF's inside public right-of-way shall not
located underground.
prohibited in residential areas or areas in which utilities are
Tower-Based WCF's inside public right-of-way are
an area in which utilities are underground.
public right-of-way is not located within fifty (50) feet of
The location of the proposed Tower-Based WCF inside
1)

b)
Ground-mounted related equipment that cannot be
placed underground shall be screened, to the fullest
extent possible, through the use of landscaping or
other decorative features to the satisfaction of the
Township and PennDot.
Required electrical meter cabinets shall be screened
to blend in with the surrounding area to the
satisfaction of the Township
d)
Any graffiti on the tower or on any related
equipment shall be removed at the sole expense of
the WCF owner.
Any underground vaults related to tower-Based
WCF's shall be reviewed and approved by the
Township and PennDOT.
f)
The WCF shall employ the most current Stealth
Technology in an effort to appropriately blend into
the surrounding environment and minimize
aesthetic impact. Application of the Stealth
Technology chosen by the applicant shall be subject
to approval of the Township and PennDot
g)
Any proposed WCF shall be designed structurally,
electrically, and in all respects to accommodate both
the WCF applicant's antennae and comparable
antennae for future users.
h)
 Reimbursement for right- of way use. In addition to
permit fees as deseribed in this section, every.
Tower Based WCF in the Township right of way is
subjeet to the Township's right to fix annually a fair
and reasonable fee to be paid for use and occupaney
of the right-of way. Such compensation for right-
of way use shall be directly related to the
Township's aetual right of way management costs--
ineluding, but not limited to, the costs of the.
administration and performance of all reviewing,
inspeeting, permitting, supervising and other right-.
of way management aetivities by the Township.
The owner of each Tower-Based WCF shall pay an -
annual fee to the Township to compensate the
Township for the Township's cost incurred in
connection with the activities described above. Said
fee is to be set by Resolution of the Township.
13
25

14
feasible.
shall be the smallest and least visibly intrusive equipment
height and that are compatible in scale and proportion to
equipment components that are not more than six (6) feet in
streetlights and joint utility poles, shall consist of
public right-of way including, but not limited to, those on
WCF installations located above the surface grade in the
1)
with the following:
the new WCF's covered under this subsection shall be compliant
surrounding streetscape, whichever is higher. In addition, any of
feet in height or less, or 110% of the height of poles in the
pole is proposed by the applicant, the proposed pole shall be 35
Should none of the above location options be feasible and a new
PennDOT, provided they are compliant with the following:
support structures with the approval of the Township and
poles or freestanding structures that do not already act as wireless
WCF Applicant shall locate its non-tower WCF's on existing
light poles. If collocation is not technologically feasible, the
shall be collocated on existing poles, such as utility poles or
New Non-Tower WCF's located within the public right-of-way
New Non-Tower WCF Inside Public Rights-of-Way.
()
provided.
property the facilities are to be located shall be
Agreement from the property owner on whos
the public right-of-way, a copy of an Easment
equpment is proposed to be located outside of
Visual impact analysis with photo simulations.
equipment.
operation.
including all associated equipment necessary for
plans for each proposed WCF installation
Submission of a detailed site and engineering
Submission of a zoning permit.
above. In addition, the application should include:
requirements of Section 220-81.B(2) (d) [1 -6]
applicant shall document compliance with the
based WCF within the public right-of-way, the
As part of the application for a new pole/tower
h)

2)
Antenna and related equipment shall be treated to match
the supporting structure and may be required to be painted,
or otherwise coated, to be visually compatible with the
support structure upon which they are mounted.
3)
The Township and PennDOT shall determine the time
place and manner of construction, maintenance, repair
and/or removal of all Tower-Based WCF's in the public
right-of-way based on public safety, traffic management,
physical burden on the right-of-way, and related
considerations. For public utilities, the time, place and
manner requirements shall be consistent with the police
powers of the Township and the requirements of the Public
Utility Code.
4)
Non-Tower WCF's and related equipment shall be located
as not to cause any physical or visual obstruction to
pedestrian or vehicular traffic, or to otherwise create safety
hazards to pedestrians and/or motorists or to otherwise
inconvenience public use of the right-of-way as determined
by the Township and PennDOT. In addition:
a)
In no case shall ground-mounted related equipment,
walls, or landscaping be located within eighteen
(18) inches of the face of curb, within two (2) feet
of the edge or cartway if no curb, or within an
easement extending onto a privately owned lot.
b)
Ground mounted related equipment that cannot be --
placed underground shall be sereened, to the fullest-
extent possible, through the use of landscaping or-
other decorative- features to the satisfaction of the-
Township and PennDOT.
For sites in residential developments where utilities
are underground, ground level cabinets are
prohibited. Either underground cabinets or pole
mounted cabinets may be used. If a pole mounted
cabinet, it may not exceed 3 cubic feet in volume
and must be finished and/or painted to blend in with
the existing streetscape. Ground level cabinets are
permitted in all non-residential zones provided that
such ground level cabinet is less than 28 cubic feet
in volume, is finished and/or painted so as to blend
in with its background and does not inhibit any
existing sight triangles.
/25
15

16
governmental entity in the right-of-way.
The operations of the Township or other
improvement in the right-of-way.
installation of any Township or other public
The construction, repair, maintenance or
following circumstances:
alteration is reasonably necessary under the
determined that such removal, relocation, change or
Commission regulations and PennDOT, shall have
police powers and applicable Public Utility
Tower WCF when the Township, consistent with its
relocate, change or alter the position of any Non-
Non-Tower WCF in the right-of-way shall, at its
determines is reasonably necessary or such shorter
Township, or such longer period as the Township
(60) days following written notice from the
Relocation or removal of facilities. Within sixty
adjoining existing residence.
to or less than the front yard setback distance of an
WCF's shall not be located within a distance equal
be 300 feet between WCF installations. Small cell
Township and PennDOT.
WCF's shall be reviewed and approved by the
Any underground vaults related to non tower based-
expense of the WCF owner.
related equipment shall be removed at the sole
Any graffiti on the non-tower WCF or on any
(p
the satisfaction of the Township and PennDOT.
screened to blend in with the surrounding area to
located. Above ground level cabinets shall be
the property upon which the equipment is to be
Easement Agreement from the property owner of
above ground, the applicant will need to secure an
the public right-of-way, either underground or
If an electrical meter cabinet is located outside of
satisfaction of the Township and PennDOT.
to blend in with the surrounding area to the
Reguired electrical meter cabinets shall be screened.

Vacation of a street or road or the release of
a utility easement.
iv)
An emergency as determined by the
Township.
g)
Reimbursement for right-of way use. In addition to
permit fees as deseribed in this seetion, every Non-
Tower WCF in the Township right of way is
subject to the Township's right to fix annually a fair
and reasonable fee to be paid for use and oceupancy
of the right of way. Sueh compensation for right --
of way use shall be direetly related to the
Township's actual right-of way management costs--
ineluding, but not limited to, the costs of the
administration and performance of all reviewing,
inspeeting, permitting, supervising and other right --
of way management activities by the Township.
The owner of each Tower Based WCF shall pay an -
annual fee to the Township to compensate the
Township for the Township's cost ineurred in
connection with the activities described above. Said
fee is to be set by Resolution of the Township.
As part of the application for a new non-tower wCF
within the public right-of-way, the applicant shall
document compliance with the requirements of
Section 220-81.B(2) f [1-6] above. In addition, the
application should inchude:
Submission of a zoning permit.
Submission of a detailed site and engineering
plans for each proposed WCF installation
including all associated equipment necessary for
Operation.
Photographs ofproposed WCF antenna and
equipment.
Visual impact analysis with photo simulations.
If any associated ground or underground
equipment is proposed to be located outside of
the public right-of-way, a copy of an Easement
Agreement from the property owner on whose
property the facilities are to be located shall be
provided.
C.
Permit Processing Time Frames
25

18
23
less than fifty (50) feet in height, to be used as a
pole (utility pole, street light, etc.) or a new pole of
construction of a new small WCF on an existing
attached as defined by the WBCA, or for the
wireless support structure to which they are
substantially change the physical dimensions of the
existing non-tower based WCF that does
90 Days - For collocation of a small WCF on an
applieation.
final decision on whether to-approve the
within ninety (90) days the Township shall make its
which they are attached as defined by the WBCA, 
dimensions of the wireless support structure to
that do Substantially Change the physical
For those applieations for Non Tower Based WCF's
(P)
approve the application.
application, shall make its decision on whether to
Township within 60 days of receipt of a complete
dimensions of the wireless support structure, the
does not substantially change the physical
structure to which they are to be attached which
60 Days -- For collocation of small WCF's (non-
applieation:
final decision on whether to approve the.
within sixty (60) days the Township shall make its-
which they are attached as defined by the WBCA, 
dimensions of the wireless support structure to
that do not Substantially Change the physical
For those applieations for Non Tower Based WCF's
(e)
now complete.
(10) days notify the applicant if the application is
required information, the Township shall within ten
Upon submission to the Township of the additional
(q)
required to complete such application.
Applicant in writing of any information that may be
Township, the Township shall notify the WCF
application for a Non-Tower WCF is filed with the
Within thirty (30) calendar days of the date that an
(a)
For a Non-Tower WCF:
1)
Timing of approval for WCF applications shall be as follows:

wireless support structure to which the WCF's are
to be attached, the Township within 90 days after
receipt of a complete application shall make its
decision whether to approve the application.
(e)
The decision of the Township shall be made in
writing and provided to the applicant.
(f)
If additional information was requested by the
Township to complete an application, the time
required by the WCF Applicant to provide the
information shall not be counted toward the
Township's sixty (60) or ninety (90) day review
periods, as applicable. These timing requirements
in this section shall only apply to proposed facilities
that fall under the Pennsylvania Wireless
Broadband Collocation Act. (Provision to put clock
on “hold"when additional information has been
requested to make an application complete)
2)
For a Tower-Based WCF:
(a)
Within thirty (30) calendar days of the date that an
application for a new Tower-Based WCF is filed
with the Township, the Township shall notify the
WCF Applicant in writing of any information that
may be required to complete such application (i.e.:
the requirement for a Special Exception approval
from the Zoning Hearing Board).
(b)
Upon submission to the Township of the additional
required information, the Township shall within ten
(10) days notify the applicant if the application is
now complete.
(e)
All applications for Tower Based WCF's shall be-
aeted upon within -one hundred fifty (150) days of-
the receipt of a fully completed application for the--
approval of such Tower Based WCF and the
Township shall advise the WCF Applicant in
writing -of its-decision:
90 Days - For collocation of a new small wireless
facility (WCF) on an existing wireless support pole
or tower structure in excess of fifty (50) feet in
height, the Township upon receipt of a complete
19

20
toward the 150-day review period.
Applicant to provide the information or secure the
application, the time required by the WCF
(conditional use or height vanance) to complete the
Township or any required zoning approval
If additionai information was requested by the
(e)
receipt of a complete application.
shall act upon the application within 150 days of
excess of fifty (50) feet in height, the Township
based WCF on a wireless support structure in
150 Days - For construction of a new pole or tower
hundred fifty (150) day review period.
information shall not be counted toward the-one.
required by the WCF Applicant to provide the
(d) --- If additional information was requested by the
application within 90 days.
application shall render its decision in the

Tom Unger
From:
Craig Momose
Sent:
Tuesday,July09,20194:31PM
To:
Steve Bright; Diane Hollenbach; Keith Shuman
Cc:
Chip; Tom Unger
Subject:
RE:Maidencreek Twp tentative schedule
CraigMoee,ve
From:SteveBright[mailto:sbright@ronniefolkpaving.com]
Sent:Tuesday,July09,20194:25PM
To:Craig Momose<c.momose@sdei.net>; Diane Hollenbach<d.hollenbach@maidencreek.net>; Keith Shuman
<k.shuman@maidencreek.net>
Subject: Maidencreek Twp tentative schedule
Here it is for now:
Aug 8 - Misc patching on Hoch and Wyatt
Aug9-MillcurblineandbaserepaironBewley/Lakeside
Aug 12 or so -Oil & Chip Bewley/Lakeside
Aug 15 - OverlayBewley/Lakeside
Aug 12 - Mill joints/patch on Schaeffer Rd
Aug 13 - Leveling on Schaeffer Rd
Aug 14 - Overlay on Schaeffer Rd
Lineptgon SchaefferRd (andBewley)shortlythereafter.
Not set in stone but close....
716WaterStreet
P.O.B0x268
Shoemakersville,PA19555
Email :
Office)610-562-3550
Cell)610-587-1519

S472.02
TOTALAMOUNTDUE
$472.02
AMOUNTDUE
$472.02
96978
7/31/19Maidencreek Twp. Re: SDE, Inc.
Berkshire Property Management Co., LLC
1.
INVOICE NO.
AMOUNT
DATEOFINVOICE/PAYEE
AUGUST1,2019
MAIDENCREEKTOWNSHIPBOARDOFSUPERVISORS
APPROVEDFORPAYMENT
IMPROVEMENTAGREEMENTSINVOICES
SUMMARY

Archived from the Maidencreek Township website. Reproduced unaltered; not an official records repository.