MAIDENCREEK TOWNSHIP BOARD OF SUPERVISORS
AUGUST 13, 2020
ENGINEER'S AGENDA
Subdivision Review Status Checklist
Next Supervisors Meeting September 10, 2020
JoJaz review period expires 9/1/2020
Redners review period expires 9/1/2020
Kopfer review period expires 9/1/2020
Subdivision / Zoning / LDP
JoJaz Subdivision Prel./Final see SDE review Itr. Dated 8/4/20.
Redner's Quickshop & Car Wash Prel. Plan see SDE Itr. Dated 8/4/20.
David Kopfer Sketch Plan for Record see SDE Itr. Dated 6/3/20.
Gun Range regulations draft reviewed w/P.C. on 1/8/20 revisions/additions
being made.
Burning Ordinance regulation draft reviewed by P.C. on 7/1/2020 additional
revisions/additions being made.
Projects
Street Projects 2020
Excelsior Drive & June Ave. BOS awarded:
Contract "A" to Recon Construction in the amount of
$206,038.00.
Contract "B" to New Enterprise Stone & Lime Co. in the amount of
$135,317.50
Pre-construction meeting held on 8/6/20
Start date wk. of Aug. 17
Schedule
Recon Construction approx.. 5 days
10-14 day cure time
New Enterprise 5 days: night work expected
Lutz Property E. Wesner Rd. storm water issue
Reviewed Walnut Manor & Golden Manor Subdivision Plans (Plans start
in 1987). There is no storm water easement on plans. No notes for
storm water system maintenance on plans.
Storm Damage -- Made numerous inspections/mtgs.
Inspected Tree Tops Basin
No evidence of overflow
Page 1 of 2
I:(Projects\Maidencreek Township/20-0019-0100/Engineer's Agendal8.13.20.docx

Needs maintenance
Inspected Shadow Ridge - corner of Schaeffer
Basin overflowed; masonry block placed in front of orifice.
Schaeffer Road Bridge
Bridge appeared unaffected
Stream blockage approx.. 100' downstream of bridge
Melrose
Inspection of basin, mtg. w/residents, mtg. with developer
Inlets & basin outlet clogging major issue
Basin spillway erosion; investigate with design engineer larger
riprap or concrete
Inlet to basin height to be investigated w/design engineer
Investigate reconfigure of Walnut Tree inlet for overflow
Mtg. w/design engineer to investigate off site water control
Maidencreek Village Retirement Community
Basin overflowed; clogged outlet
Needs maintenance
Community Park Stream
Reviewed w/Keith S. Twp. To continue removal of debris &
stone from channel; reconstruct stone banks
620 Guldin Rd.
Twin outlet pipes & endwall erosion into stream.
611 June Ave
Met w/owner representative; reviewed washed out bank
between properties.
Subdivision Improvement LOC / Escrow Release
See Attached
Sewage Enforcement Officer Activity Report
See Attached
Page 2 of 2
I:(Projects/Maidencreek Townshipl20-0019-0100/Engineer's Agendal8.13.20.docx

Most Recent
Letter Date
5/1/2020
8/5/2020
8/5/2020
Review
6/3/2020
Approval conditioned on SDE
Comments
No action taken by PC,
No action taken by PC,
No action taken by PC,
resubmission needed
resubmission needed
resubmission needed
review letter
Approved
BY BOS
05/14/20
MAIDENCREEK TOWNSHIP, BERKS COUNTY
(may reflect more
than one extension)
Extension
SUBDIVISION STATUS
8/13/2020
Period Ends
07/16/20
09/01/20
09/01/20
90-Day
Review
09/01/20
Review Period
04/17/20
06/03/20
06/03/20
90-Day
Begins
06/03/20
Plan Stage
Prelm/Final
Prelm/Final
Prelm Plan
Sketch Plan
for Record
Plan
Plan
APPROVED / PENDING PLANS:
Redner's Quickshop and Car Wash
David Kopfer Subdivision
CURRENT PLANS:
Schick Dental Office
Jojaz Subdivision
Project Name
No.

SYSTEMSDESIGN
SDE
ENGINEERINGINC
sdei.net
August 5, 2020
Diane Hollenbach,Township Manager
Maidencreek Township
1 Quarry Road
Blandon, PA 19510
Re:
JoJaz Subdivision
Preliminary/Final Plan -Review #3
Ms. Hollenbach:
Systems Design Engineering, inc. is in receipt of a Preliminary/Final Plan entitled "JoJaz
Subdivision." The site has two (2) access points to Maiden Creek Road and the subdivision would
result in four (4) new individual lots. The southern access point is to be a local single access
street and the northern access is via a proposed easement. The Plan was prepared by The
Crossroads Group, LLC. The submission consisted of the following:
Cover Sheet
Undated
Subdivision Plan
Sheet 1of 8
Dated 5/6/2020, Rev 7/31/2020
Sheet 2 of 8
Existing Features Plan
Dated 5/6/2020, Rev 7/31/2020
Sheet 3 of 8
Demolition Plan
Dated 5/6/2020, Rev 7/31/2020
Road Plan & Profile
Sheet 4 of 8
Dated 5/6/2020, Rev 7/31/2020
E&s Control Plan
Sheet 5 of 8
Dated 5/6/2020, Rev 7/31/2020
Sheet 6 of 8
Construction Details
Dated 5/6/2020, Rev 7/31/2020
Sheet 7 of 8
Pre-Dev Drainage Plan
Dated 5/6/2020, Rev 7/31/2020
Sheet 8of 8
Post-Dev Drainage Plan
Dated 5/6/2020, Rev7/31/2020
Additional materials reviewed consisted of the following:
Response Letter dated 7/15/2020
Stormwater Control Narrative, last revised 7/13/2020
Erosion and Sedimentation Control Narrative, last revised 7/13/2020
Waiver request letter dated 7/15/202
Erosion &Sediment Control PlanadeguacyletterfromBCCDdated7/1/2020
IAProjects/MaidencreekTownshipPCI20-0024-0715 Jojaz Subdivision/Prelim-FinalPlantPrelim-FinalPlan Review#3.docx
1032 James Drive, Leesport, PA 19533  P: 610.916.8500 - F: 610.916.8501
Schuylkill Haven, PA  P: 570.385.5549
Boyertown, PA  P: 610.369.1319

Maidencreek Township Planning Commission
August 5, 2020
Re:
JoJaz Subdivision
Page 2 of 8
Preliminary/Final Plan Review #3
BACKGROUND:
The purpose of the plan is to subdivide an existing tract that is zoned industrial. The tract is
currently 24.57 acres in size. Four (4) new lots would be created, two (2) existing parcels
adjacent to the proposed lots would remain unchanged and would have various easements in
common. Lots are to be served by private individual wells and individual on-site sewage disposal.
REVIEW:
This letter presents comments on the third review of the Preliminary/Final Plan.
ZONING:
The property is located in the I - Industrial Zoning District. The uses of the proposed parcels are
not determined at this time. Each lot will require a Land Development Plan in order to develop a
particular use.
1. Per $220-49, Area and Bulk Regulations
The Zoning Data table states that each of the four (4) proposed lots would meet
the area and bulk requirements. However, upon examination of the arc lengths in
the Curve Table on Sheet 1, it appears that proposed Lots 1 and 3 wouid not meet
the required lot width of 200 feet.
To remedy this: clarification on the Curve Table should be provided, the
Plan should be amended to reflect the 200-foot requirement, or applicant
may wish to seek relief from the Zoning Hearing Board.
1. Applicant's Engineer has been contacted regarding this issue.
Items for future consideration:
1. An Environmental Impact Assessment will need to be prepared by the Applicant and
approved by Maidencreek Township at the time of any future land development.
SALDQ:
1. Per §190-16, Information to Accompany a Preliminary Plan
SDE

Maidencreek Township Planning Commission
August 5, 2020
Re:
JoJaz Subdivision
Page 3 of 8
Preliminary/Final Plan Review #3
Per Subsection G(5), a deed must be prepared and submitted to the Township
prior to recording. The deed shall include descriptions of the proposed right-of-
way and all easements.
Partially addressed. The Applicant stated that deeds will be prepared for
each lot closer to final approval.
2. Per S190-17, Final Plan Reguirements
The plans should be sealed by a Professional Engineer prior to Final Plan approval.
O Partially addressed. The Applicant stated that the plans will be sealed
closer to final approval.
3. Per §190-31, Improvement Specifications
Per Subsection A, the Applicant shall submit a Subdivision Improvements
Agreement to the satisfaction of the Planning Commission and Board of
Supervisors. The agreement should also be reviewed by the Township Solicitor.
o Partially Addressed. The Applicant stated Improvements Agreement will
be submitted closer to Final approval.
4. Per §190-32, Streets
Per Subsection i(2), in no case shall a public single-access street be the sole means
of vehicular access to a non-residential use.
O A waiver is being requested to this section.
Per Subsection L(3), curbs and sidewalks shall be provided in accordance with
Section §186.
o A waiver is being requested to this section.
Per Subsection L(5), Streetlights may be required by the Board of Supervisors. If
required, the streetlight plan shall be included with any Preliminary Plan or Final
Plan submittal and shall be approved by mutual agreement between the
Township, developer, and any appropriate public utility; a utility easement would
also be required for maintenance.
SDE

Maidencreek Township Planning Commission
August 5, 2020
Re:
JoJazSubdivision
Page 4 of 8
Preliminary/Final Plan Review #3
A waiver is being requested to this section. The Applicant believes the
necessity of street lights should be determined by the Board of Supervisors
at the time of land development on the subdivided lots.
5. Per $190-39, Soil Percolation Test Requirements
Soil percolation tests are required for all subdivisions where on-site sewage is
provided.
The Applicant should coordinate percolation test requirements with the
Sewage Enforcement Officer and DEP.
A waiver request to this section has been withdrawn. The
Applicant stated that testing results and any waivers from DEp
would be submitted upon receipt.
6. Boundaries between Proposed Lot 1, Proposed Lot 4 and the proposed right-of-way are
unclear. The plan should be updated to clearly show the boundaries of each parcel
and/or center line of the proposed right-of-way.
•Addressed. The plan has been updated to show the boundaries at the centerline.
7. Paving details and cross sections should be provided to clarify the shaded areas provided
on Sheet 3.
Addressed. Clarification was provided.
STORMWATER MANAGEMENT:
1. Per S182-11, Erosion and Sediment Control -- The revised Erosion & Sediment Control Plan
should be resubmitted to the Berks County Conservation District for re-approval. A copy
of the new approval letter should be submitted to the Township prior to Final Plan
approval.
2. Per $182-13.A.(2)(b) and 13.B, Groundwater Recharge - The ordinance requires the
design soil infiltration rate for Trench A to be based on field testing. The submitted design
uses an average of the typical range of permeability rates published in the NRcs soil
survey. In lieu of performing infitration testing in the Trench A area at this time, an
acceptable alternative is to add a note to Sheet 1 reguiring the future lot infiltration BMPs

Maidencreek Township Planning Commission
August 5, 2020
Re:
JoJaz Subdivision
Page 5 of 8
Preliminary/Final Plan Review #3
to be designed to provide a total additional infiltration volume of 700 cubic feet (approx.
50% of the requirement for Trench Aj. This will provide an additional safety factor in the
event the actual rate is less than the assumed design rate.
3. Per $Per $182-21.B, Exemptions - The project meets the requirements for an exemption
from the drainage plan requirements. The total new impervious area of 11,526 SF
(allowable area is 15,000 SF), is referenced in Note 11 on Sheet 1.
4. Per §182-21.C.(3), Exemptions -- The project is located in RAWA's Source Water Protection
Area. The Applicant's engineer has indicated they have contacted RAWA to discuss
possible issues with the project. Written acknowledgement from RAWA that the
proposed Stormwater management BMPs meet their requirements should be submitted
to the Township.
5. Per s182-3o, Performance Guarantee - A financial guarantee should be provided for the
proposed stormwater management controls prior to Final Plan approval. A certified
construction cost estimate shouid be submitted for the proposed stormwater
management BMPs.
6. Per §182-32 and 182-34, Operations and Maintenance Agreement for Privately Owned
Stormwater Controls and BMPs -- Prior to Final Plan approval,the Applicant should
execute the maintenance agreement contained in Appendix A.
MISCELLANEOUS STORMWATER MANAGEMENT PLAN AND REPORT COMMENTS:
1. A concrete trench drain is now proposed for the access driveway to the Township's grass
clippings drop off site. The driveway profile notes the centerline of the trench drain at
only 5.75' off the edge of the cartway. This places the headwall wings immediately
adjacent to the edge of the road. We recommend increasing the distance to the center of
the trench drain to at least 7.75.
2. The Rational Method computations for Swale Zo1 and for the trench drain are based on
different rainfall intensity values (4.95 in/hr and 4.12 in/hr for a 15-min time of
concentration). It appears that one computation is based on the PennDOT Region 4
values and one on NOAA rainfall data. The ordinance allows either of these rainfall data;
however, the same rainfall data must be used for all Rational Method computations.
SDE

Maidencreek Township Planning Commission
August 5, 2020
Re:
Jojaz Subdivision
Page 6 of 8
Preliminary/Final Plan Review#3
Either the trench drain design flow should be increased, or the swale design flow
decreased. It should be noted that decreasing the swale design flow will limit the
allowable combined post-construction flow to Swaie zo1 from Lots 1 through 3.
3. An additional check dam and clay core should be noted on the plan and in the detail
tables at approximate STA 2+50.
4. In discussions with the design engineer, our office indicated that the modeling procedure
for Trench A to show compliance with the Streambank Erosion Requirements did not
accurately reflect the storage volume that would be provided in Trench A as currently
designed. It was agreed that the plan would show an area of approximately 12,000 sF of
existing impervious cover that would be removed to the stone subbase at the time of the
roadway widening construction to offset the new roadway widening impervious area.
If the plan does not delineate removal of offsetting impervious cover, revised
computations to show compliance with the Streambank Erosion Requirements must be
submitted.
CONSTRUCTION DETAILS /ACCESS ROAD PROFILE:
1. The following revisions should be made to the Trench Drain section:
A. The width of the concrete outside the grate should be noted.
B. The required 23" trench drain depth should be dimensioned on the Trench Drain
Detail from the trench invert to the bottom of the grate.
MISCELLANEOUS:
1. Traffic
a. Trucks are prohibited on Evansville Road. Trucks will be required to use Maiden
Creek Road to Route 73 and to Pleasant Hill Road.
Addressed. Note 18 has been added to Sheet 1.
b. The previous submission included a full turning radius for vehicles entering and
exiting onto Maiden Creek Road. The current submission shows larger vehicles but
does not show full turn radii.

Maidencreek Township Planning Commission
August 5, 2020
Re:
JoJaz Subdivision
Page 7 of 8
Preliminary/Final Plan Review #3
It appears the turn radii may be too small for the larger vehicles. Full
turning radi should be pravided. Any construction to increase the radii will
reguire new PennDOT HOP approval.
Note #9 on the Plan should state to the effect: "Any ingress or egress from
Maiden Creek Road that exceed the current capability of truck
movements" would require the applicant to apply for new HoP approval.
2. On-lot sewage is proposed.
a. A public sewer system should be investigated to determine feasibifity to include
Molltown area and Maiden Creek Road users.
Partially Addressed. The Applicant stated that they are discussing this with
the Township.
3. Maidencreek Township currently maintains a Township residential grass clippings drop-off
location on the northwest corner of the property along Maiden Creek Road. The future
status of this facility should be noted.
a. Partially Addressed. Note 14 was added to Sheet 1. This note acknowledges the
use of Lot 4 for "yard waste." However, the proposed access driveway to the
disposal area would be moved significantly and would be reduced to only 15 feet
in width. The Township should determine if the location and the width are
satisfactory.
b. It appears the existing area labelled "brush pile" crosses the proposed boundary
line between Lot 4 and Lot 1. Note 14 should be amended or a new note should
be added to the plan to ciarify the grass clippings drop-off location.
4. The proposed road is to remain private; a Maintenance agreement for the proposed road
should be submitted by the Applicant and commented on by Township Solicitor.
a. Partially addressed. The Applicant stated that a Maintenance Agreement would
be submitted closer to final approval.

Maidencreek Township Planning Commission
August 5, 2020
Re:
JoJaz Subdivision
Page 8 of 8
Preliminary/Final Plan Review #3
5. Number of the notes on the Plan skip number "13." The notes shouid be amended such
that numbering is chronological.
WAIVER REQUESTS:
Waivers to three (3) sections are requested via a letter dated July 15, 2020.
1. Waiver to Section §190-32.l.2 regarding a public single access street to be the sole
vehicular access to a nonresidential use
2. Waiver to Section $190-32.L.3 regarding the requirement for curbs and sidewalks.
3. Waiver to Section §190-32.L.5 regarding street lights. The Applicant wishes to address
street lights at the time of land development on the subdivided parcels.
If you should have any questions or comments, please do not hesitate to contact our office.
Sincerely,
SYSTEMS DESIGN ENGINEERING, INC.
Philip J. Ashear
Township Planning Consultant
Cc:
Maidencreek Township Planning Commissioners
Diane Hollenbach / Township Manager
Eugene Orlando, Jr. / Township Solicitor
The Crossroads Group
SDEFile#20-0024-0715

SYSTEMS DESIGN
SDE
ENGINEERING, INC
sdei.net
August 5, 2020
Diane Hollenbach,TownshipManager
Maidencreek Township
1 Quarry Road
Blandon,PA19510
Re:
Redner's Quickshop and Car Wash
Preliminary Plan Review #2
Ms. Hollenbach:
Systems Design Engineering, Inc. is in receipt of a Preliminary Plan entitled "Redner's Quickshop
and Car Wash." The site has three (3) access points; two on Allentown Pike (Us Route O222) and
another on Lake Shore Drive (PA Route 0073). The proposal would result in gas pumps, a
convenience store, and car wash. The Plan was prepared by Bogia Engineering, tnc. The
submission consisted of a response letter to SDE's June letter, BMP and O&M Recommendations,
a Lot Consolidation Plan, a Stormwater Management report and the following:
Cover Sheet
Sheet 1 of 11
Dated 5/20/2020, Rev 7/22/2020
Sheet 2 of 11
Existing Conditions Plan
Dated 5/20/2020, Rev 7/22/2020
Grading and Utility Plan
Sheet 3of 11
Dated 5/20/2020, Rev 7/22/2020
Details Plan
Sheet 4of 11
Dated 5/20/2020, Rev 7/22/2020
Details
Sheet 5 of 11
Dated 5/20/2020, Rev 7/22/2020
Landscaping Plan
Sheet 6 of 11
Dated 5/20/2020, Rev 7/22/2020
Sheet 7 of 11
Lighting Plan
Dated 5/20/2020, Rev 7/22/2020
E&S Plan
Sheet 8of 11
Dated 5/20/2020, Rev 7/22/2020
Sheet 9 of 11
E&SPlanDetails
Dated 5/20/2020, Rev 7/22/2020
Drainage Area
Sheet 10 of 11
Dated 5/20/2020, Rev 7/22/2020
Sheet 11 of 11
Truck Turn
Dated 5/20/2020, Rev 7/22/2020
BACKGROUND:
The purpose of the plan is to establish a gas station, car wash and convenience store on parcels
zoned C-1 Local Commercial. The subject site consists of three (3) neighboring parcels that total
1.75 acres in size. The site is to be served with public water and sewer. The site previously
I:AProjectsiMaidencreek TownshipPC120-0024-0717Redner's Quickshopand CarWash/Redner's Prel Plan Rev#2.docx
1032 James Drive, Leesport, PA 19533 - P: 610.916.8500. F: 610.916.8501
Schuylkill Haven, PAP:570.385.5549
Boyertown, PA P: 610.369.1319

MaidencreekTownship Planning Commission
August 5, 2020
Re:
Redner's Quickshop and Carwash
Page 2 of 9
PreliminaryPlan Review#2
existing building, while gas pumps would be moved to the southwest side of the site and a car
wash would be constructed. The existing driveway onto Rt. 222 will be removed and a new
driveway constructed to the south.
The applicant is also in the process of seeking zoning relief from the Maidencreek Township
Zoning Hearing Board.
REVIEW:
This letter presents comments on the second review of the submitted Preliminary Plan.
ZONING:
The subject site is located in the C-1 Local Commercial Zoning District.
1. A deed of consolidation should be submitted and recorded with the plan.
Addressed. A consolidation plan and deed were submitted with the 7/22/2020
submission.
2. The first review did not interpret the proposed car wash as an accessory use. The car
wash is interpreted as a use permitted by Special Exception.
Partially addressed. A special exception application was submitted. The Zoning
Hearing Board has scheduled a hearing for 8/4/2020.
3. Per 5220-61.B, Parking and Truck Loading Requirements
Parking spaces for use by handicapped drivers must be 14' x 20' or otherwise
regulated by the Americans with Disabilities Act.
above requirement. However, according to the ADA Technical Assistance
website, they do appear to meet the requirements of the Americans with
Disabilities Act. The Applicant should ctarify or amend the plan such that it
meets both Township and ADA standards.
1. Addressed. Clarification was provided.

Maidencreek Township Planning Commission
August 5, 2020
Re:
Redner's Quickshop and Carwash
Page 3 of 9
Preliminary Plan Review #2
4. Per 5220-62, Sign Regulations
A previous sign at the corner of Allentown Pike and Lake Shore Drive was
removed. However, new sign details are not provided.
 The Applicant should put sign details on the plan and demonstrate
compliance with Section $220-62.
1. Partially Addressed. The applicant stated that sign regulations
would be in compliance. Details for traffic signage was provided.
Details for business signage is not provided.
5. Special Exceptions
The proposed uses are onty permitted via a special exception subject to conditions
of this section and with the approval of the Zoning Hearing Board.
o The Applicant will need to submit the appropriate application to the
Maidencreek Township Zoning Hearing Board and obtain approval.
Section 5220-65 states special exception requirements for car washes:
Car washes are permitted oniy in an enclosed building that must be at least
100 feet from residential districts and right-of-way intersections.
Additionally, sufficient space must be provided for at least ten (10) stacked
vehicle spaces.
Special exception and variance application was submitted. Decision by the
Zoning Hearing Board is pending.
LIGHTING STANDARDS:
1. Per 186-48, Lighting Plan Submission
Lighting plans are required in the Preliminary Plan stage of all development plan
reviews.
The submitted plan includes light fixture details, but does not include a
lighting schedule with footcandle data and intensities. A lighting plan
should be submitted in conformance with Section s186.

Maidencreek Township Planning Commission
August 5, 2020
Redner's Quickshop and Carwash
Re:
Page 4 of 9
Preliminary Plan Review#2
The Applicant should also see performance standards in Section
$220-63.
Outstanding. The applicant submitted a lighting plan. However,
the lighting plan is not in compliance with the Maintained
Footcandle requirements in Section $186-47.
 The following are comments from SDE's Electrical Designer:
Please indicate luminaires and illuminance levels across the entire parking
area.
Please show luminaires and iluminance levels under the fuel island canopy.
The plan indicates 0.0 lluminance levels under proposed luminaires, please
correct.
The plan indicates illuminance from site lighting within the footprint of the
building; please mask this area so proper illuminance level averages and
average / min levels can be calculated.
Please demonstrate compliance with the average illuminance levels and
uniformity ratios listed in Section §186-47 of the zoning ordinance.
Section §186-47 calls for maintained footcandles to be calculated, yet in
the submitted plan, initial footcandles were calculated.
SALDQ:
1. Per s190-15, Preliminary Plan Requirements
 Per Subsection C, the plan shall be sealed by the professional responsible for the
plan.
Professional Engineer at the time of Final plan approval.
2. Per $190-34 Sidewalks
 Sidewalks may be required for commercial deveiopments by the Board of
Supervisors. Ultimately, the Board of Supervisors should decide on the efficacy of
sidewalks for this proposed development.
Likewise, in accordance with Sections §190-34.D and 5190-35.C, the Board
of Supervisors and Planning Commission may wish to determine the
efficacy of a crosswalk at the given intersection.

MaidencreekTownshipPlanning Commission
August 5, 2020
Re:
Redner's Quickshop and Carwash
Page 5 of 9
Preliminary Plan Review#2
1. Outstanding. The applicant stated that the plan is consistent with
the Crossings at Maidencreek; however, the Crossings at
Maidencreek subdivision is not related. The applicant should
coordinate crosswalks with the PennDOT Rt 73/222 traffic lighting
plans.
3. Per §190-44, Landscaping
The selected species - Prunus serrulate (Kwanzan Cherry) and Juniperus Chinesis
(Seagreen Juniper) - are not included on the Townships recommended list.
o The Applicant should address the need for the selected species or the
Applicant should amend the landscaping plan with species included on the
Township's recommended list.
1. Partialy Addressed. Clarification provided; however, we would like
to reserve judgement on the selected species in order to give our
Landscape Architect a chance to comment.
In addition to the above landscaping comments, the applicant should amend the
landscaping plan to comply with Buffer Yard requirements found in Section g220.
64.
A ten-foot bufferyard is required.
1. Addressed. Clarification is provided. The proposed development
would not encroach any further on the existing residential use to
the northeast. Therefore, the lack of a buffer yard is interpreted as
an existing non-conformity
STORMWATER MANAGEMENT:
1. Per S182-11, Erosion and Sediment Control -. The Erosion & Sediment Control Plan should
be submitted to the Berks County Conservation District for review and approval. A copy
of the approval letter should be submitted to the Township prior to Final Plan approval.
2. Per s182-13., Groundwater Recharge -- The detention basin should be provided with an
impermeable liner to prevent infiltration and potential groundwater contamination from
polluted runoff entering the basin from the fueling area, unless the justification required
by $182-13.D is provided.

Maidencreek Township Planning Commission
August 5, 2020
Re:
Redner's Quickshopand Carwash
Page 6 of 9
Preliminary Plan Review #2
3. Per $182-17.C.(4), Design Criteria for Stormwater Management and Conveyance BMPs -
The interior basin side slopes should be no steeper than 3:1. The side slopes are noted to
be 3:1 on the basin cross-section detail; however, the grading plan contours reflect slopes
that are approximately 1.5:1.
4. Per 3182-17.D.(1), Design Criteria for Stormwater Management and Conveyance BMPs -
Design computations for the proposed storm sewer system and diversion swale should be
provided.
5. Per §182-17.D.(3), Design Criteria for Stormwater Management and Conveyance BMPs -
Notes should be provided on the plans specifying the required storm sewer pipe material.
6. Per §182-22. E.(2)(d), Drainage Plan Contents - The Certificate of Owner should be revised
to include this additional wording.
7. Per $182-24.F - The proposed storm sewer connections to the proposed inlet located
within the SR 0222 right-of-way, as well as the driveway modifications, will require a
PennDOT Highway Occupancy Permit. A copy of the HOP(s) should be submitted to the
Township prior to Final Plan approval.
8. Per 182-30, Performance Guarantee - A financial guarantee should be provided for the
9. Per $182-32 and $182-34, Operations and Maintenance Agreement for Privately Owned
Stormwater Controls and BMPs - The Stormwater Management Controls and Best
Management Practices Operations and Maintenance Agreement in Appendix A of the
Stormwater Management Ordinance should be submitted for review and approval by the
Township.
MISCELLANEOUS STORMWATER MANAGEMENT PLAN AND REPORT COMMENTS:
1. Based on the off-site topography that was added to the plan, it appears that additiona!
off-site area to the north of pre-development drainage areas DA-1 and Bypass-1 drains
onto the site and contributes runoff to Points of Interest POl-2 and POl-3. The additional
off-site runoff should be accounted for in both the pre-development and post-
development runoff computations to these Points of Interest and for the diversion swale.
2. Based on the existing contours provided behind the existing buifding it appears that the
area behind the building drains to POl-3, not POl-2.
3 

Maidencreek Township Planning Commission
August 5, 2020
Re:
Redner'sQuickshopand Carwash
Page 7 of 9
Preliminary Plan Review #2
3. The design should address the probable impact of the tailwater elevation in the Rt. 222
storm sewer on the operation of the detention basin, since the invert of the basin outlet
pipe is at essentially the same elevation as the Rt. 222 storm sewer invert.
4. The emergency spillway invert is set approximately 2' lower than the revised Rt. 222 top
of curb elevation. Please confirm that the Rt. 222 and site survey elevations are on the
same datum. In addition, the survey datum information should be noted on Sheet 1.
5. A list of additional detailed design review comments will be forwarded to the engineer
rather than include them in this letter.
COMMENTS ON THE GRADING & UTILITY PLAN:
1. The pipe sizes and/or materials should be noted for the proposed sanitary and water
services to the car wash. In addition, the existing water and sanitary mains in Rt. 222
should be labeled.
2. The existing fuel storage tanks should be shown on the plan, including any additional work
necessary to repair the area excavated for the tank removal.
3. The proposed gas fueling area canopy and the carwash roof drain pipe system should be
shown, including pipe size, material and inverts.
4. All proposed contours should be labeled.
5. In order to provide the drainage area boundary shown for Bypass-2, the 344 contour must
be revised and bottom of curb/paving spot elevations added to ensure runoff does not
run down the driveway to Rt. 222.
6. All existing and proposed storm sewer sizes and materials should be labeled.
7. The junction structure below OS-1-1 and ES-1-1 should be labeled.
MISCELLANEOUS DRAFTING COMMENTS:
1. A list of additional detailed design review comments will be forwarded to the engineer
rather than includethem inthis letter.
SDE

Maidencreek Township Planning Commission
August 5, 2020
Re:
Redner's Quickshop and Carwash
Page 8 of 9
Preliminary Plan Review #2
MISCELLANEOUS:
1. The three (3) existing lots should be combined prior to Final Plan approval. The plan
states this is the intention. A deed should be provided.
Addressed. A deed of consolidation was submitted. It will need to be recorded
with the approved Final Plan.
2. MTA approval is required. The plans should be submitted to the Maidencreek Township
Authority and an approved review letter should be provided to the Township upon
receipt.
Partially addressed. The plan was submitted to MTA. Receipt of approval by the
MTA should be submitted to the Township office and to SDE.
3. The proposed iocation of the fuel tanks block the southwestern access to Allentown Pike.
An alternative location for the fuel tanks should be investigated.
Addressed. Fuel tanks have been appropriately relocated.
4. An approved PennDoT Highway Occupancy Permit should be provided for access points
along Allentown Pike.
Outstanding. An approved HOP has not been provided. The applicant stated that
it will be provided once received.
5. Existing and proposed stop sign locations and details shouid be provided.
Addressed. Clarification was provided.
6. Curb Radii
 The applicant should explain or amend the 2-foot curb exit radius at the
northeastern access point to Us Route 0222.
o Outstanding. The 2-foot curb radii have been amended to 5 feet. These
will need to be reviewed and approved by PennDOT as part of the HOp
approval.

Maidencreek Township Planning Commission
August 5, 2020
Re:
Redner's Quickshop and Carwash
Page 9 of 9
Preliminary Plan Review #2
Curb radii at the new parking
o Addressed. Clarification was provided.
7. Turn radi in and out of the car wash seem inappropriate given the current layout. A
turning radius plot should be provided for large pick-up trucks entering and exiting the car
wash. The layout may need to be modified to provide adequate access.
Addressed according the provided Truck Turn on Sheet 11.
. Curb grades should be provided for proposed car wash curbing.
Addressed. Clarification was provided.
If you should have any questions or comments, please do not hesitate to contact our office.
Sincerely,
SYSTEMS DESIGN ENGINEERING, INC.
Philip J. Ashear
Township Planning Consultant
Cc:
Maidencreek Township Planning Commissioners
Diane Hollenbach / Township Manager
Eugene Orlando, Jr. / Township Solicitor
Bogia Engineering, Inc.

SUMMARY
IMPROVEMENT AGREEMENTS INVOICES
APPROVEDFOR PAYMENT
MAIDENCREEK TOWNSHIP BOARD OF SUPERVISORS
AUGUST 7, 2020
DATE OF INVOICE/PAYEE
INVOICE NO.
AMOUNT
1. GSP Properties, LLC
7/31/20 Maidencreek Twp. -- Re: SDE, Inc.
$292.69
8/07/20 GSP Properties
Appl. #2
$247.501.31
AMOUNT DUE
$247,794.00
TOTAL AMOUNT DUE
$247.794.00
I:/ProjectsiMaidencreek Township/lmprovement Agreement Summaries/202018.7.20.doc