Maidencreek Township Authority
September 17, 2020

Attending Board Members Via Teleconference: Karl Bolognese, Jerry Hartman, Jack May, Jim
Nothwehr, Dan Novakovich

Also Attending: Patrick Donovan and Debbie Kline of the Maidencreek Township Authority.
Also Attending Via Teleconference: Greg Unger and Ty Leinneweber of SDE, Daniel Becker of
Kozloff Stoudt

Jack May called the September 17, 2020 meeting of the Maidencreek Township Authority
(MTA) to order at 5:00 p.m. via Zoom video conference and asked everyone to rise for the
Pledge of Allegiance to the Flag.

APPROVAL OF THE MINUTES

A motion was made by Dan Novakovich to waive the reading of the minutes and approve
the August 20 & 26, 2020 regular meeting minutes as presented. The motion was seconded by
Jim Nothwehr and hearing no questions on the motion, it passed unanimously.

NEW BUSINESS
Redner’s Quick Shop and Car Wash
Ty Leinneweber of SDE reported the review letter was sent to Redner’s on August 21, 2020, and
SDE is currently awaiting a reply.

Route 73 Water Main Break
Patrick Donovan provided an email to the Board for their review prior to the meeting. The Rt 73
water main break on September 1, 2020 occurred as a result of an error by Barrasso Excavation,
Inc. Mr. Donovan spoke to Matthew Barrasso regarding the costs incurred by the MTA as a
result of the water main break and the possibility of submitting the costs to the contractor for
payment. Mr. Barrasso informed Mr. Donovan the contractor has two change orders that they
could submit to the MTA for the project. Mr. Barrasso suggested that he will not submit the
change orders if the MTA does not submit the additional costs for the water main break. The
Board discussed the matter in detail. Greg Unger of SDE recommended closing out the project
with no additional change orders on either side.

A motion was made by Jim Nothwehr to instruct SDE to communicate to Barrasso
Excavation, Inc., that the MTA will agree to the offer by Matthew Barrasso not to submit the
costs associated with the Rt 73 water main break to Barrasso Excavation, Inc., and Barrasso
Excavation, Inc., will not submit any additional change orders for the project to the MTA. The
motion was seconded by Dan Novakovich and hearing no questions on the motion, it passed
unanimously.

Giorgio Foods
Mr. Donovan reported that Kevin Manmiller of Giorgio Foods approached him about purchasing
100,000 gallons of potable water per day from the MTA. Mr. Donovan provided the Board with
an email with preliminary costs prior to the meeting. Kevin will discuss the preliminary costs
provided with Giorgio’s upper management. The Board has agreed to assist Giorgio Foods with
Page | 1

Maidencreek Township Authority
September 17, 2020

their request for the purchase of water should upper management approve moving forward.
Kevin will provide the MTA with the As-Built drawings and piping within the facility. This
information will be forwarded to Greg Unger of SDE to review and determine how best to
provide Giorgio with a direct connection to the Authority’s water system.

Route 73 Water Line Replacement
Ty Leinneweber of SDE provided an update for the Rt 73 Water Line Replacement project. All
services have been switched over on the new 8” and 12” lines. On September 1, 2020, Barrasso
had a water line break on the new 12” line in the area of the 500 block on Main Street. As a
result of the water main break, there was a loss of water pressure in the township. Barrasso
repaired the break and service was restored to the 500 block on Main Street. The MTA issued a
Boil Water Advisory to all township residents. The results of bacteria tests received at three
locations in the township showed no presence of bacteria. The Boil Water Advisory was
removed September 3, 2020.

A motion was made by Jerry Hartman to approve and authorize Change Order #2
presented by SDE on behalf of Barrasso Excavation, Inc. in the amount of $2,000.00 to plug
existing 6” water line. The motion was seconded by Jim Nothwehr and hearing no questions on
the motion, it passed unanimously.

A motion was made by Jerry Hartman to approve and authorize Change Order #3
presented by SDE on behalf of Barrasso Excavation, Inc. for consideration of Time Extension
from 09/07/2020 to 11/03/2020 without change to contract price. The motion was seconded by
Jim Nothwehr and hearing no questions on the motion, it passed unanimously.

PA Game Commission Cooperative Agreement

A motion was made by Jim Nothwehr to approve the signing of the Public Access
Program Cooperative Agreement. The motion was seconded by Karl Bolognese and hearing no
questions on the motion, it passed unanimously.

GSP Escrow Release
Ty Leinneweber reported that SDE received a request to reduce the existing Letter of Credit by
$48,086.37, which would bring the LOC balance down to $33,729.11.

A motion was made by Dan Novakovich to authorize Patrick Donovan to sign the
Authorization for Reduction of the Letter of Credit for GSP Properties. The motion was
seconded by Jerry Hartman and hearing no questions on the motion, it passed unanimously.

Pension Plan Administrator
A motion was made by Karl Bolognese to appoint Dan Novakovich, the 2021 Chairman

of the Authority, as the Pension Plan Administrator. The motion was seconded by Jerry Hartman
and hearing no questions on the motion, it passed unanimously.

Page | 2

Maidencreek Township Authority
September 17, 2020

MMO Pension Obligation 2021

A motion was made by Dan Novakovich to approve the MMO Pension Obligation for
2021 in the amount of $52,297.00. The motion was seconded by Karl Bolognese and hearing no
questions on the motion, it passed unanimously.

2021 Rate Increase – Mr. Donovan reported that in October of this year the MTA will have
completed four full years of the 3% increase of the five-year plan to increase rates. Mr. Becker
will prepare the 2021 rate resolutions.

A motion was made by Jerry Hartman to authorize Mr. Becker to prepare the rate
resolutions for a 3% rate increase for 2021. The motion was seconded by Dan Novakovich and
hearing no questions on the motion, it passed unanimously.

UPDATES
Authority Extension
Mr. Becker provided an update and stated this is on schedule to be completed in the next few
months.

PMRS Pension Plan Review
Mr. Donovan has spoken to Peter Karapelou of Beyer-Barber Company and the evaluation is
moving forward.

Water Tank Inspection
Mr. Donovan provided an update. He stated the water tank inspections have been completed. The
tank at Tree Tops received a score of 8/10, and the tank at Mountain Springs received a score of
7/10. When the full report is received from the contractor, Mr. Donovan will provide the Board
with the recommendations.

Manhole Inspection Project
Mr. Donovan stated he is working with SDE to come up with a plan to inspect the MTA
manholes. The contractor will inspect the 65 manholes, take pictures of each manhole and
complete the SDE manhole inspection sheet. SDE will then make recommendations based on the
inspections. The cost of the project will be approximately $9,000.00. Mr. Donovan is requesting
approval to complete this project.

A motion was made by Jim Nothwehr for authorization to proceed with the manhole
inspection project. The motion was seconded by Dan Novakovich and hearing no questions on
the motion, it passed unanimously.

Status of Storm Damage
Ty Leinneweber of SDE provided an update on the status of the storm damage. The entrance to
the waste water treatment plant has been repaired with larger rock to help prevent further
damage in the future. A berm was provided to direct the off-site water into an existing headwall
to prevent water coming onto the waste water treatment plant property and into the treatment
facilities. Ty stated that SDE is very confident that the repairs/changes made will prevent further
damages from occurring as a result of future storms. Mr. Donovan will submit all costs incurred
as a result of the storm damage to the MTA insurance provider.

Page | 3

Maidencreek Township Authority
September 17, 2020

PennDot Coke Conflict Area
Mr. Becker provided an update. Mr. Becker had a phone call with Larry Ditty of PennDot to
discuss the status of the reimbursement agreement. Dave Radar reached out to Karen Pollock
requesting an updated estimate of the design and legal costs to date. Mr. Donovan provided this
information to Karen to forward to Dave. At this time, the MTA is awaiting PennDot’s decision
in regards to the new reimbursement agreement.

Route 222 Project
Ty Leinneweber of SDE reported the project is continuing as expected. On 08/26/2020 a new
water line was connected to the existing line on Rt 73. SDE is working to provide As-Built
information on the portions completed to date. Surveyed/GPS positions will be provided for the
MTA GIS system. The construction crew is currently working on the Betterment portion along
Rt 222 between Rt 73 and CVS. The contractor is currently working nights to construct the
crossings of all traffic lanes.

SOLICITOR’S REPORT
Mr. Becker had nothing further to add.

ENGINEER’S REPORT
SDE submitted a written report. Mr. Unger had nothing further to add.

AUTHORITY REPORT
Mr. Donovan had nothing further to add.

PAYMENT OF BILLS

A motion was made by Karl Bolognese to accept the Treasurer’s Report and authorize the
following payments: Routine/Regular Bill List - $45,067.21, Construction in Progress -
$32,399.53, Reimbursable Expenses Paid by Developer - $2,544.06, Emergency Account
Transfer from Operator Acct - $3,000.00, Validate Checks Signed Between Meetings -
$19,287.50, Special Checks Requiring Special Handling - $33,363.27, Additional Checks after
Board Book Delivery - $47,452.85. Jim Nothwehr seconded the motion and hearing no questions
on the motion, it passed unanimously.

ENGINEER’S/SOLICITOR’S REIMBURSABLE EXPENSES:

A motion was made by Dan Novakovich to approve all Professional Staff Reimbursable
Expenses as follows: SDE invoice #101470 in the amount of $1,374.46, Kozloff Stoudt invoice
#178548 in the amount of $1,169.60. The motion was seconded by Jerry Hartman and hearing no
questions on the motion, it passed unanimously.

A motion was made by Dan Novakovich and seconded by Jim Nothwehr to adjourn the meeting
at 6:15 PM.

Page | 4

Maidencreek Township Authority
September 17, 2020

Respectfully Submitted,

Debbie Kline

Debbie Kline
Recording Secretary

Minutes are subject to change prior to approval of the Maidencreek Township Authority.

cc: Maidencreek Township Authority Board Maidencreek Township Board of Supervisors

Patrick Donovan, Maidencreek Township Authority General Manager Maidencreek Township Planning Commission

Greg Unger, Systems Design Engineering, Inc., MTA Engineer Eugene Orlando, Esq., Orlando Law Firm, Solicitor

Daniel Becker, Kozloff Stoudt, MTA Solicitor Diane Hollenbach, Maidencreek Township Manager

Maidencreek Township Authority Plant Operators Ontelaunee Township, Kosmerl & Company

Page | 5

Archived from the Maidencreek Township website. Reproduced unaltered; not an official records repository.