MAIDENCREEK TOWNSHIP
BERKS COUNTY, PENNSYLVANIA

ORDINANCE NO. _______

AN ORDINANCE OF MAIDENCREEK TOWNSHIP, BERKS
COUNTY, PENNSYLVANIA AMENDING THE MAIDENCREEK
TOWNSHIP CODE OF ORDINANCES, AS AMENDED TO: DEFINE
DATA CENTER AND RELATED DEFINITIONS UNDER ARTICLE II;
CORRECT CODE REFERENCE IN SECTION 220-48.C; ALLOW DATA
CENTERS, AND RELATED USES BY CONDITIONAL USE IN THE
INDUSTRIAL ZONING DISTRICTS; PROVIDE REGULATIONS FOR
SUCH USES IN ARTICLE XVI RELATED TO DIMENSIONAL
REQUIREMENTS, AESTHETICS, LANDSCAPE BUFFERS AND
BERMS, EQUIPMENT SCREENING, EMERGENCY MANAGEMENT
AND ACCESS, NOISE CONTROL, NOISE STUDY, ONSITE
GENERATION AND BACKUP POWER, OTHER PERFORMANCE
STANDARDS, AIR/GROUND/WATER POLLUTION CONTROLS,
DECOMMISSIONING, PARKING, ELECTRONIC WASTE
STANDARDS, AND PUBLIC ENGAGEMENT

WHEREAS, Maidencreek Township, Berks County, Pennsylvania (“Township”) is a
township of the second class operating pursuant to the Second-Class Township Code, 53 P.S. §§
65101, et seq., and the Municipalities Planning Code (“MPC”), 53 P.S. §§ 10101, et seq.;

WHEREAS, the Township enacted The Maidencreek Township Zoning Ordinance of
2017, as amended (“Zoning Ordinance”);

WHEREAS, Data Centers and those related uses are not regulated by the Zoning
Ordinance, although developers now seek to develop the same in many places throughout the
Commonwealth of Pennsylvania in support of artificial intelligence and other computer-based
activities;

WHEREAS, the development and operation of Data Centers and those related uses
potentially pose some hazards to public health, safety, and welfare, including but not limited to
excessive noise and vibrations, strain upon finite natural resources and the electrical grid,
increased emissions and fire risks, and disrupting the aesthetics of the community; and

WHEREAS, the Board of Supervisors of the Township, therefore, desires to regulate the
development and operation of Data Centers and those related uses to protect public health, safety,
and welfare.

NOW THEREFORE, BE IT ENACTED AND ORDAINED by the Board of Supervisors
of Maidencreek Township, Berks County, Pennsylvania as follows:

Section 1. Purpose of Zoning Ordinance Amendments. The Board of Supervisors of
Maidencreek Township, Berks County, Pennsylvania hereby recognizes that Data Centers and
those related uses may be important for economic development in the twenty-first century within

1

the Township, the County of Berks, the Commonwealth of Pennsylvania, and the United States
of America. The Board of Supervisors of Maidencreek Township, Berks County, Pennsylvania,
therefore, declares that the purpose of this Ordinance is not to directly or effectively prohibit the
development and operation of Data Centers and those related uses. Rather, the Board of
Supervisors of Maidencreek Township, Berks County, Pennsylvania enacts this amendment to
the Zoning Ordinance for the purpose of regulating and, thereby, minimizing or preventing
issues that may arise from the development and operation of Data Centers and those related uses,
including but not limited to noise, vibrations, strain upon finite natural resources and the
electrical grid, increased emissions and fire risks, and disruption to the aesthetics of the rural
community, which threaten public health, safety, and welfare.

Section 2. Definitions. Section 220-11, Definitions, of Article II of the Zoning
Ordinance is hereby amended and supplemented to add the following terms and associated
definitions (to be inserted in alphabetical order), as follows:

Data Center
A facility primarily used to house, operate, or co-locate computers, computer
communications, or computer storage equipment and to process, organize,
handle, store, or back up computer data necessary, all of which are necessary
for the operation of artificial intelligence, web or cloud-based computing,
computing services, or storage, or another similar business, organizational
entity, or the like. A ‘Data Center’ includes Data Center Equipment (DCE) and
Data Center Accessory Uses when located on the same parcel as the Data
Center or an assemblage of adjacent parcels to the Data Center if developed as
one unied development. This use shall also include cryptocurrency mining,
blockchain transaction processing and server farms. This use does not include
computers or telecommunications-related equipment that is secondary and
incidental to an otherwise permitted use on a property such as a server
associated with an office building.

Data Center Campuses
A large plot of land containing multiple, interconnected high-tech facilities
dedicated to housing computing infrastructure, servers and massive data
storage systems.

Data Center Equipment (DCE) and Data Center Accessory Uses
The utilities, utility lines, electrical substations, pump stations, water and
cooling towers, mechanical equipment, environmental controls (air
conditioning or cooling towers, re suppression, etc.), redundant/backup
power sources, storage, and supplies, redundant data communications
connections, and high security necessary for a Data Center.

Sensitive Receptor
Any of the following existing or under construction at the time of the
submission of any zoning relief application for a Data Center: a school,
preschool, day-care center, in-home daycare, health or healthcare facility, such as
a hospital, outpatient clinic, long term care or rehabilitation facility, or retirement

2

or nursing home, community center, place of worship, park or preserve (excluding
trails), campground, prison, dormitory, any residence, or agricultural use, when
any of the foregoing is not located on a parcel with an existing industrial or
commercial use.

Section 3. Article XIV I Industrial District, Section 220-48.C of the Zoning Ordinance
shall be rewritten to refer to section 220-11, as follows:

220-48 Permitted Uses
…

C. Uses by Conditional Use. The following uses will be considered by the Board of
Supervisors as conditional uses subject to the following criteria, and further subject to the
provisions of §220-111.

Section 4. Article XIV I- Industrial District within 220-48 Permitted Uses, subsection
C Uses by conditional use in the Zoning Ordinance is hereby amended and supplemented to add
subsection (7) as follows:

(7). Data Center, Data Center Equipment, and Data Center Accessory
Uses, subject to the regulations in this zoning district, and all
applicable provisions of Section 220-81.1 of this chapter.

Section 5. Article XVI, “Supplementary Regulations,” the Zoning Ordinance is
hereby amended and supplemented to add new Section 220-81.1 as follows:

220-81.1 Data Centers, Data Center Equipment, and Data Center Accessory Uses

A. Dimensional Regulations.

1. The minimum lot size for any Data Center shall be 5 acres.

2. The maximum height for any Data Center shall be 60 feet.

3. The maximum height for any Data Center Equipment or Data
Center Accessory Uses shall be 60 feet.

4. The maximum building coverage for any Data Center, Data
Center Equipment, or Data Center Accessory Uses shall be 40%.

5. The maximum lot coverage for any Data Center, Data Center
Equipment, or Data Center Accessory Uses shall be 50%

6. The Data Center, Data Center Equipment and Data Center
Accessory Uses shall be set back at least 100 feet from any lot
line and any ultimate right-of-way, although the parking and

3

loading/unloading areas, and internal driveways must be at
least 50 feet from any lot line.

7. Notwithstanding the foregoing, the Data Center, Data Center
Equipment and Data Center Accessory Uses shall be set back at
least 1000 feet from any Sensitive Receptor and from the
boundary of any residential zoning district. This distance may be
reduced to 500 feet if the applicant can successfully demonstrate
how it will exceed other environmental performance standards
including noise levels that do not exceed ambient noise for that area,
visual screening and/or aesthetic improvements that mask the data
center use, and do not contribute to any thermal air changes that
would affect the closest sensitive receptors.

8. Data Center Equipment and Data Center Accessory Uses shall
not be located between the principal building of the Data Center
and any street and must be separated from any adjacent
dwelling or residential zoning district by the principal building.

B. Aesthetics
1. Any Data Center, Data Center Equipment (DCE), and Data
Center Accessory Uses building façade that faces a road or
sensitive receptor must incorporate at least two of the following
design elements every 150 horizontal feet:
a. A change in building material, pattern, texture or color;
b. A change in building height;
c. Building step-backs or recesses having a minimum depth
of five (5) feet.

C. Landscape Buffer and Berm. The Data Center, Data Center Equipment
(DCE), and Data Center Accessory Uses shall, along all lot lines, have a
50-foot landscaped buffer with a 15 foot earthen berm at a slope ratio
of 2:1. The landscape buffer shall include plantings to achieve a dense,
opaque, four-season screen and shall consist of native species as follows
1. One (1) large evergreen tree per twenty-five (25) linear feet of
buffer. The size of large evergreen trees shall be a minimum of
eight (8) feet in height at the time of planting.
2. One (1) deciduous canopy (shade) tree per seventy-five (75)
linear feet of buffer. Size of canopy (shade) tree shall be a
minimum of 2 ½ inch caliper at the time of planting.
3. One (1) ornamental/flowering tree per fifty (50) linear feet of
buffer. The size of the ornamental/flowering trees shall be a
minimum height of eight (8) feet for multi-stemmed varieties or
2 ½ inch caliper at the time of planting for single-stemmed
varieties.
4. Five (5) shrubs per twenty-five (25) linear feet of buffer. Size of
shrubs shall be fully branched and minimum of three (3) in

4

height at time of planting. Shrubs shall be a combination of
evergreen and deciduous species, with a minimum of 50% being
evergreen.
5. Attempts shall be made to preserve mature trees on the site.

D. Equipment Screening. All rooftop and ground-mounted Data Center
Equipment (DCE) shall be fully enclosed where not mechanically
feasible based on the manufacturer’s specifications. If it is not
mechanically feasible to fully enclose equipment, the equipment shall
be fully screened from public view by parapet walls or architectural
screening of compatible materials and color, opaque landscaping to a
height not less than the equipment, or a combination thereof.

E. Emergency Management and Access.

1. The applicant shall submit an Emergency Response Plan (ERP)
prepared by a qualified professional. The ERP shall:
a. Be reviewed and accepted by the local fire department
and emergency management coordinator as part of the
conditional use process;
b. Include detailed procedures for fire suppression,
containment, ventilation and evacuation that are
sufficiently protective of public health, safety and
welfare;
c. Demonstrate compliance with NFPA standards for fire
suppression systems designed for battery storage if
proposing battery storage or any other device or group
of devices capable of storing energy in order to supply
electrical energy at a later time, whether stored on-site or
off-site;
d. Ensure that all first responders receive adequate training
on the installed systems;
e. Include provisions for an annual fire safety inspection by
a qualified professional on behalf of the Data Center;
f. Evaluate access roads and hydrant locations to ensure
suitable access.

2. The Data Center shall have an adequate means of secondary
ingress and egress suitable for emergency vehicles in accordance
with the standards of the underlying district, if any, as approved
by the Township Engineer in consultation with the Chief of the
Volunteer Fire Company serving that area of the Township.

F. Noise Control. When measured from any lot line, the Data Center, Data
Center Equipment, and Data Center Accessory Uses, during normal
operations, as well as testing and maintenance operations (e.g. all
standby emergency equipment, including but not limited to generators
running), shall not exceed a maximum decibel level of 55 dB(A) at all

5

times. Notwithstanding the foregoing, during a power outage, the
maximum decibel levels specied above shall not apply up to eight (8)
hours per month.

G. Noise Study. A Noise Study shall be conducted by a professional
acoustical expert concluding that the Data Center, Data Center
Equipment, and Data Center Accessory Uses will comply with the
Noise Control regulations above and what noise reduction materials,
systems or other improvements are proposed for that purpose. The
Noise Study shall also evaluate the noise with respect to the above
regulations when the power is out. The Noise Study shall be conducted
using Sound Level Meters described in ANSI S1.4-2014, and generally
accepted criteria. The Noise Study shall occur in the following phases:

1. Preliminary Noise Study – A preliminary noise study for the
Data Center, Data Center Equipment, and Data Center
Accessory Uses shall be filed with the conditional use
application. It shall establish the pre-construction
ambient/baseline noise level, estimate the anticipated noise
levels during normal operations and during power outages, and
propose the noise reduction materials, systems or other
improvements to meet the above noise control regulations.

2. Interim Noise Study – An interim noise study shall be filed
during the land development review process based upon the
expected user or users of the Data Center. The noise reduction
materials, systems and other improvements recommended by
the interim noise study shall be incorporated into the
construction plans for the Data Center.

3. As-Built Noise Study – An as-built noise study shall be filed no
more than 6 months after issuance of the Certicate of
Occupancy for the Data Center but prior to the nal escrow
release for any land development phase. An as- built noise study
may also be required thereafter by the Township upon request.
If the Township determines that a violation of the above noise
control regulations has occurred or is occurring, then the owner,
operator, or user of the Data Center shall promptly remediate
the violation into compliance with the aforesaid noise limits.

The costs for the interim and as-built noise studies shall be posted as part of
the financial security prior to release and recordation of the final land
development plan.

6

H. Onsite Generation and Backup Power.

1. To reduce grid dependency, at least a portion of the power for
the Data Center shall be produced onsite from roof-mounted
Accessory Solar Energy System (ASES), subject to any non-
conflicting regulations of the Zoning Ordinance, covering at
least sixty-five percent (65%) of the roof of the principal building
of the Data Center, which must be continually maintained and
operable.

2. The Data Center may provide backup power through emergency
generators, solar power, wind power, fuel cells, and battery storage
installed, used, and maintained in accordance with all applicable
federal, state, and local laws, rules, regulations, and codes.

a. All diesel generators shall meet U.S. EPA Tier 4 emissions
standards or better.

b. Generators shall be equipped with secondary containment
for fuel systems, sized to contain 110% of tank capacity.

c. Cumulative generator maintenance and testing shall not

exceed 8 hours per month.

d. Generator exhaust stacks shall be directed away from
adjacent residential uses.

I. Other Performance Standards.

1. Air, Ground, and Water Pollution Controls. The Data Center, Data
Center Equipment, and Data Center Accessory Uses shall
comply with all standards in Section 220-63 of this chapter, the Air
Pollution Control Act, 35 P.S. §§ 4001 through 4015, as amended,
and the following standards:

a. Visible Emissions. Visible air contaminants shall not be
emitted in such a manner that the opacity of the emissions
is equal to or greater than 20% for a period or periods
aggregating more than three minutes in any one hour, or
equal to or greater than 60% at any time, and shall comply
with Pennsylvania Code Title 25, Chapters 123 and 127A(7),
or their most recent update.

b. Particulate, Vaporous and Gaseous Emissions. No owner or
operator of the Data Center, Data Center Equipment, or
Data Center Accessory Uses shall cause, suffer or permit
the emission of fugitive particulate, vaporous or gaseous

7

matter from any source in such a manner that the emission
is visible or detectable outside the property of that use.

c. Hazardous Air Emissions. All emissions shall comply with

National Emissions Standards for Hazardous Air

Pollutants promulgated by the United States

Environmental Protection Agency under the Federal Clean

Air Act (42 U.S.C. § 7412) as promulgated in 40 CFR 61, or

its most recent update.

d. Odor. No owner or operator of the Data Center, Data
Center Equipment, or Data Center Accessory Uses shall
cause, suffer or permit the emission into the outdoor
atmosphere of any malodorous air contaminants from any
source in such a manner that the malodors are detectable
outside the property of that use. The prohibition on odors
shall not apply to odor emissions arising from the premises
of a farm operation. Any process which causes an odor
emission shall be operated in a manner such that escaping
odors are eliminated. Backup odor reduction equipment
shall be maintained to support primary odor reduction
equipment.

e. Toxic and Hazardous Substances. No owner or operator of
the Data Center, Data Center Equipment, or Data Center
Accessory Uses shall cause, suffer, or permit toxic or
hazardous substances to be emitted, leached, deposited, or
detectable beyond the property of that use.

f. Water Protection. No owner or operator of the Data Center,

Data Center Equipment, or Data Center Accessory Uses

shall cause, suffer, or permit harm to or the endangerment

of ground water levels and quality in the area beyond the

property of that use, nor adversely affect ground water

supplies of the same.

2. Vibration Control. No owner or operator of the Data Center, Data
Center Equipment, or Data Center Accessory Uses shall cause,
suffer, or permit any vibration, exceeding 200 micrometers per
second (RMS) or which is discernible to the human sense of feeling,
beyond the property for that use.

3. Glare and Heat Control. Any operation producing intense glare or
heat shall be performed within an enclosed building or behind a
solid fence in such manner as to be completely imperceptible from
any point beyond the lot lines.

8

a. A heat mitigation plan shall be required and implemented
that identifies primary sources of heat and designs
measures to mitigate heat.

b. Site lighting shall be cool temperature LED lighting (less
than 3000k) with zero uplight. No light shall be emitted
above 80 degrees from nadir. To prevent nuisance glare to
neighboring parties, Data Centers must use cut off shields,
glare control devices, motion activated security lighting or
other measures to reduce the impact of the site lighting. Site
lighting shall be reduced to 2 lux during late night hours to
preserve dark skies.

4. Control of Radioactivity or Electrical Disturbance. No owner or
operator of the Data Center, Data Center Equipment, or Data
Center Accessory Uses shall cause, suffer, or permit the emission
of dangerous or harmful radioactivity. There shall be no electrical
disturbance (except from domestic household appliances)
adversely affecting the operation of any equipment located beyond
the property boundary of the creator of such disturbance.

5. Fire and Explosive Hazards. No owner or operator of the Data
Center, Data Center Equipment, or Data Center Accessory Uses
shall cause, suffer, or permit flammable and explosive materials to
be stored, used and transported unless in accordance with the
applicable state and federal regulations regarding such materials
and associated storage vessels.

6. Outdoor Storage. All outdoor storage facilities for fuel, flammable
or explosive materials and raw materials shall be enclosed by a
fence adequate to prevent the access of children and other members
of the general public. No materials or waste shall be deposited upon
a lot in such form or manner that they may be transferred off the
lot by natural causes or forces. All material or waste which might
cause fumes or dust or which constitute a fire hazard, or which may
be edible or otherwise be attractive to rodents or insects, shall be
stored outdoors only in closed, sealed containers.

7. Waste Disposal. No Data Center, Data Center Equipment, or Data
Center Accessory Uses shall cause industrial waste to be stored,
discharged, incinerated or otherwise disposed of except in
conformance with the applicable state and federal regulations
regarding solid and hazardous wastes.

8. Electrical Power. The Data Center, Data Center Equipment, and
Data Center Accessory Uses shall be designed and operated so
that the service lines, substation, etc., shall conform to the most
acceptable safety requirements recognized by the Pennsylvania

9

Bureau of Labor and Industry, shall be so constructed, installed,
etc., as to be an integral part of the architectural features of the plant
or, if visible from abutting residential properties, shall be concealed
in accordance with the landscaping requirements herein.

9. Electric Report. The applicant shall submit an interconnection
agreement from the electric service provider indicating that
transmission and distribution capacity are available, the data center
will be served, and the upgrades required to the grid before such
service. Any and all upgrades to the grid related to transmission or
distribution shall be borne solely by the applicant. The impact upon
electric rates or the availability of electricity for others uses as a
result of the Data Center shall be thoroughly addressed, projected,
and explained.

10. Water. The Data Center, Data Center Equipment, and Data
Center Accessory Uses must have sufficient water. The Data
Center, Data Center Equipment, and Data Center Accessory
Uses shall have a close-loop system which must recirculate, reuse
and recycle water at the site, and the same shall be explained and
shown in a separate report and plan. The Data Center, Data Center
Equipment, and Data Center Accessory Uses must have water
usage effectiveness consistent with or better than the then-existing
industry standards. No such use shall be permitted that poses
adverse impact on any source of water. As such, the owner or
operator of the Data Center, Data Center Equipment, and Data
Center Accessory Uses shall connect the same with a public
water system. In the event that the Data Center, Data Center
Equipment, and Data Center Accessory Uses cannot be served
by public water, the Township may allow the same to utilize a
nonpublic source of water. Regardless of whether public water
supply or groundwater is to be utilized, the following information
must be set forth in a study, under the seal of a professional
engineer licensed in the Commonwealth with the requisite
education, qualifications, and experience on the following matters,
presented by the applicant:

a. An analysis of raw water needs for all capacity, including
domestic and cooling uses, indicating quantity of water
required.

b. A geologic map of the area with a radius of at least one mile
from the site with the locations of all existing and proposed
wells within 3,000 feet of the site (with a notation of the
capacity of all high-yield wells) and all streams within 1,000
feet of the site (with all known point sources of pollution).

10

c. The long-term safe yield shall be determined based on the

geologic formation(s) underlying the site.

d. A determination of the effects of the proposed water supply
system on the quantity and quality of water in nearby wells,
streams, and the groundwater table.

11. Hydrological Study. The applicant shall submit a hydrological
study prepared and sealed by a Professional Geologist licensed in
the Commonwealth of PA indicating that the proposed use will not
have any adverse impact on ground water supply and quality in
the area.

12. Wastewater/Sewage Report. The Data Center, Data Center
Equipment, and Data Center Accessory Uses must have a
sufficient method of handling wastewater and sewage. No such use
shall be permitted that poses adverse impact upon the
environment. As such, the owner or operator of the Data Center,
Data Center Equipment, and Data Center Accessory Uses shall
connect the same with a public sanitary sewer system and
present the Township with a will-serve letter from the
applicable public authority. The issuance of a Will Serve Letter
shall be at the sole discretion of the public sewer system provider.
In the event that the Data Center, Data Center Equipment, and
Data Center Accessory Uses cannot be served by public sewer,
the Township may allow the same to utilize another method for
sewage disposal if all applicable federal, state, and local laws, rules,
and regulations are followed.

13. Delaware River Basin Commission. If the use is to rely upon non-
public sources of water, the applicant shall provide proof of review
and approval from the Delaware River Basin Commission for any
Data Center proposing: water withdrawals of 50,000 gallons per
day (gpd) or more over a 30-day average from any source or
combination of sources within the Delaware River Basin; or any
consumptive water use of 20,000 gpd or more over a 30-day average
from any water source.

14. All costs (including but not limited to permitting, engineering,
legal, administrative, construction and contingencies) associated
with increasing conveyance, treatment, capacities, and/or
upgrading any public sanitary sewer and water system facilities, if
required by the system Owner, shall be borne by the Data Center
developer.

11

J. Decommissioning.

1. The owner or operator of the Data Center shall, at its sole
obligation, cost, and expense, complete decommissioning of the
Data Center within 12 months of the end of its useful life or the Data
Center no longer being in operation for a consecutive period of 12
months, whichever comes first.

2. The owner or operator of the Data Center shall inform the
Township in writing within 30 days of the Data Center reaching the
end of its useful life or having not been operable for a period of at
least 12 consecutive months.

3. Decommissioning shall include complete and total deinstallation
and removal of all structures and facilities, components, features,
and appurtenances of the Data Center, whether above, equal to or
below ground, in strict accordance with any and all applicable
federal, state, and local laws, rules, regulations, and codes.
Materials shall be recycled or reused where applicable. Stormwater
facilities and healthy landscaping shall remain undisturbed.

4. An independent, certified professional engineer licensed to practice
in the Commonwealth of Pennsylvania shall be retained to estimate
the total cost of decommissioning without regard to salvage value
of the equipment, and the cost of decommissioning net salvage
value of the equipment (the “Net Decommissioning Cost”). Said
estimates shall be submitted to the Township prior to final approval
of the land development plan, and after the first year of operation
and every fifth year thereafter.

5. The owner or operator of the Data Center shall prepare a
decommissioning plan for review and approval during the
conditional use hearing and shall prepare a cost estimate of the
decommissioning as set forth in the plan. Thereafter, the owner or
operator of the Data Center shall post and maintain financial
security pursuant to said approved plan and cost estimate to ensure
the proper and timely decommissioning before or
contemporaneous with the Township’s release of the final land
development plan.

6. The funds for the financial security for decommissioning shall be
posted and maintained with a bonding company, or federal- or
commonwealth-chartered lending institution chosen by the owner
or operator of the Data Center; provided, however, that the
bonding company or lending institution is authorized to conduct
such business within the commonwealth and is approved by the
Township.

12

7. The financial security for decommissioning may be in the form of a
performance bond, surety bond, letter of credit or other form of
financial assurance as may be acceptable to the Township.

8. If the owner or operator of the Data Center fails to complete
decommissioning within the prescribed period, then the
landowner shall have 6 months to complete decommissioning.

9. If neither the owner or operator of the Data Center nor the
landowner complete decommissioning within the periods
prescribed herein, then the Township may take such measures as
necessary to complete decommissioning through the use of the
financial security for decommissioning provided by the owner or
operator of the Data Center.

10. The entry into the municipal improvements agreement by the
landowner shall constitute consent of the parties to the
decommissioning.

K. Parking.

1. Data Centers are to be provided with at least one parking space per
6,000 square feet of floor area designed and intended to be
accessible regularly by employees, or one parking space for every
one employee, based upon the maximum number of employees on
site during the largest shift, plus 15 spaces for visitors, whichever is
greater.

2. Notwithstanding the above, the Township may ask for an additional
25 percent of required parking spaces to be held in reserve.

L. Electronic Waste Standards.

1. An Electronic Waste Plan shall be submitted with the conditional

use application outlining procedures for safe removal and recycling

and/or disposal of server infrastructure, hazardous materials,

batteries, electronic waste, and related products that meet all state

and federal requirements, which will apply in cases when the

equipment within the data center is updated or decommissioned. The

Report shall be subject to review and comment by the Township.

The Township shall have the right to require supplemental or

amended reports based upon comments by the Township prior to

any zoning approval.

13

M. Public Engagement Process.

1. The applicant shall hold a public meeting prior to the first planning
commission meeting when the proposed land development or
conditional use application is discussed. The purpose of the
meeting shall be to inform the public about the nature of the
proposed development, including the location, scale, and general
characteristics. A representative(s) of the applicant with knowledge
of the project and the ability to answer general questions from the
public about the project’s general location, scale, and parameters
shall participate in the meeting. The public meeting shall be
advertised, at the cost of the applicant, consistent with “public
notice” as defined by the Pennsylvania Municipalities Planning
Code (PA Act 247).

2. The applicant shall create and maintain a project website for
viewing by the general public. The site shall explain the project
parameters, including maps and elevations/renderings, beginning at
least two weeks prior to the meeting discussed above, and until the
time of final land development approval. The site shall provide a
description of the proposed use, construction timelines and phasing
plans, dates of public meetings with Township bodies, and status of
permits.

N. Conflict. If the regulations of the underlying zoning district where the Data
Center is proposed to be developed, or any applicable provision in any
other Article in the Code of Maidencreek Township conflict with these
regulations in this Ordinance then these regulations shall control.

Section 6. Severability. If any article, section, subsection, provision, regulation, limitation,
restriction, sentence, clause, phrase or word in this Ordinance, is, for any reason declared to be
illegal, unconstitutional or invalid by any Court of competent jurisdiction, such decision shall not
affect or impair the validity of this ordinance as a whole, or any other article, section, subsection,
provision, regulation, limitation, restriction, sentence, clause, phrase, word or remaining portion
of the within Ordinance. The Board of Supervisors of Maidencreek Township, Berks County,
Pennsylvania, hereby declares that it would have adopted the within Ordinance and each article,
section, subsection, provision, regulation, limitation, restriction, sentence, clause, phrase and
word thereof, without the limitation, restriction, sentence, clause, phrase or word declared illegal,
unconstitutional or invalid.

Section 7. Effective Date. This Ordinance shall become effective at the earliest date
permitted by law.

14

DULY ENACTED AND ORDAINED as an Ordinance of Maidencreek Township, Berks
County, Pennsylvania on this ________ day of _________________, 2026.

BOARD OF SUPERVISORS
MAIDENCREEK TOWNSHIP
BERKS COUNTY, PENNSYLVANIA

___________________________________
Joshua G. Meck, Chairman

___________________________________
Eric Bauman, Vice Chairman

____________________________________
Dawn Geschwindt, Member

Attest: ____________________________
Christina L. Hafer, Secretary

15

MUNICIPAL CERTIFICATION
I, Diane Hollenbach, Township Manager, certify that this is a true and correct copy of the
Ordinance enacted by the Board of Supervisors of Maidencreek Township, Berks County,
Pennsylvania on ___________ _____, 2026.

____________________________________
Diane Hollenbach, Manager

16

Archived from the Maidencreek Township website. Reproduced unaltered; not an official records repository.