FLB
FITZPATRICK LENTZ BUBBA
ATTORNEYS AT LAW
FITZPATRICKLENTZ&BUBBA,P.C.4001SCHOOLHOUSELANEPOBOX219CENTERVALLEY,PA18034-0219
STABLER
CENTER:
PHONE:610.797.9000
610.797.6663
CORPORATE
FAX: 6
www.flblaw.com
Edward J. Lentz
James G. Kellar
1927-2002
kdurso@flblaw.com
Joseph A Fitzpatrick, Jr.
Douglas Panzer*
Direct Dial: 610-797-9000, Ext.334
Of Counsel
Intellectual Property Law
Joseph A. Bubba
July 7, 2015
Albertina D. Lombardi*
Timothy D. Charlesworth
Kathleen M.Mills
Of Counsel
SENTVIAFEDERALEXPRESS
Douglas J. Smillie*
Emil W. Kantra II
Maidencreek Township
1 Quarry Road
Joseph S. D'Amico, Jr*
P.O. Box 319
Michael R. Nesfeder
Blandon, PA 19510
Catherine E. N. Durso
Re:
Preliminary/Final Land Development Submission -- Verizon Wireless
Jane P Long
Facility - RDG-Evansville -- 220 Buena Vista Road
Erich J. Schock
Dear Planning Commission and Board of Supervisors Members:
James A. Bartholomew
On behalf of our client, Cellco Partnership d/b/a Verizon Wireless (“Applicant"),
Jacob M. Sitman*
the following waivers/modifications ("waivers") from the noted sections of the
Edward Hoffman, Jr*
Stormwater Management Ordinance (SMO) and the Subdivision and Land Development
Ordinance (SALDO) are requested:
Steven T. Boell
Joshua A. Gildea
1.
SMO Section 182-13. A waiver is requested from designing infiltration
stormwater management facilities which provide on-site ground water recharge. The
Marie K.McConnell*
proposed installation will be located within a 50' x 50' fenced compound. The total area
Anthony S. Rachuba IV*
of disturbance is only +/- 7,950 SF. The proposal is going to generate a de minimis
amount of runoff and thus, infiltration and ground water recharge should not be required.
Barbara S.Zichermanf
2.
SMO Section 182-14. A waiver is requested from providing storage and
Maraleen D. Shields
treatment facilities for stormwater runoff. The area of disturbance is so small and will
Thomas J. Schlegel*
generate a de minimis amount of runoff that this requirement should be waived.
3.
Colin J Keefet
SMO Section 182-15. A waiver is requested from the stream bank erosion
requirements. The area of disturbance will generate such a de minimis amount of runoff
Gretchen L. Geisser*
that a BMP to detain stormwater runoff downstream should not be required.
Accordingly, a waiver is appropriate.
Kenneth R. Charette*
Mallory J.Sweeney*
tAlso admitted in New York
*Also admitted in New Jersey
FLB
FITZPATRICKLENTZBUBBA
ATTORNEYS AT LAW
Maidencreek Township
July 7, 2015
Page 2
4.
SMO Section 182-22. Applicant requests a waiver from having to provide
a Drainage Plan. A waiver is appropriate given the de minimis amount of run-off to be
generated by the limited area of disturbance. A Soil Erosion and Sediment Control Plan
is provided and the required notes are included.
5.
SALDO Sections 190-15(E), (L), & (M). To the extent necessary,
Applicant requests waivers from showing all streets, roads, etc. within 1,o00 feet of the
property; all sewer lines, water lines, and other required items within 100 feet of the
property; and all tree masses on the property. The property is over 113 acres in size with
the tower site only occupying a 2,500 SF portion of the property. Depicting features off-
site should not be necessary since the proposed improvements are accurately depicted.
Moreover, all existing features within the area of development are shown on the plan.
6.
SALDO Section 190-17(2). A waiver from performing a full boundary
survey is requested. The area of development has been field surveyed. Given the +/- 113
acre size of the property and the fact that the fenced compound is only 2,500 SF in size, a
waiver is appropriate.
7.
SALDO Section 190-24(A). A waiver is requested to permit the
application to proceed as a preliminary/final plan filing. A waiver is appropriate given
the minimal amount of land disturbance that is proposed. Moreover, the plan accurately
depicts the proposed improvements.
8.
SALDO Section 190-34. A waiver is requested from the sidewalk
requirements. The facility is unmanned and will not generate any pedestrian traffic
necessitating the need for sidewalks. Accordingly, a waiver should be granted.
9.
SALDO Section 190-38. A waiver is requested from having to provide a
sanitary sewer disposal system as the facility is unmanned and no sanitary system is
proposed or required.
10.
SALDO Section 190-40. A waiver is requested from having to provide a
water supply system as the facility will be unmanned and no water system is proposed or
necessary.
11.
SALDO Section 190-42. A waiver is requested from having to provide
stormwater drainage as the facility is so small and will generate a de minimis amount of
run-off will be generated such that drainage structures are not necessary as the area of
disturbance is only +/- 7,950 SF.
FLB
FITZPATRICKLENTZ
XBUBBA
ATTORNEYS AT LAW
Maidencreek Township
July 7, 2015
Page 3
Pursuant to SALDO Section 190-54, the above-requested waivers/modifications
should be granted as literal enforcement of the requirements will inflict a hardship on the
Applicant. Moreover, granting the waivers/modifications will not have an adverse impact
to public safety or welfare. Accordingly, the waivers/modifications should be granted.
Very truly yours
Catherine E. N. Durso
CEND:nmr
cc:
Mr. Michael Cleary (via e-mail only)